AI summaryCabinet agreed to recommend the 2026/27 committee timetable to full Council, with the SPAE meeting moved from 19 May to 2 June. The timetable covers seven Cabinet meetings and three contingency dates.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSubject to formal approval by full Council
MoneyNoneNo direct financial implications
What happens nextCouncil formal adoptionTo be presented to Council for adoption
Who it affectsCouncil governanceInternal governance and meeting cycle for 2026/27
What was decided
Cabinet considered the proposed 2026/27 committee timetable with the amendment moving the SPAE meeting from 19 May to 2 June.
Cabinet agreed to send the timetable to Council for formal approval.
The timetable includes seven programmed Cabinet meetings supported by three contingency dates. Report P25
Why
The timetable balances statutory requirements, governance processes and operational capacity. Report P24
It is constructed to ensure compliance with statutory Budget, Council Tax, rent-setting, and publication deadlines. Report P7
Timely approval supports the Council in meeting its statutory decision-making responsibilities. Report P8
What happens next
The timetable will be presented to Council for formal adoption. Report P26
Establishes a clear governance cycle for the 2026/27 municipal year. Report P11
Supports effective organisational planning and meeting of statutory deadlines. Report P5
Options considered
Rejected: Approve timetable as originally proposed. Amended to move SPAE meeting from 19 May to 2 June
Chosen: Approve timetable with SPAE amendment. Recommended to Council for formal approval
Implications
Legal: Constructed to ensure compliance with statutory Budget, Council Tax, rent-setting, and publication deadlines. Report P7
Financial: No direct financial implications arise from this report. Report P4
Equalities: No equalities or community impact implications, and no Equality Impact Assessment has been completed. Report P14
Risk: Late agreement could cause difficulty meeting statutory deadlines, reduced officer preparation time, increased agenda pressure, and administrative inefficiencies. Report P10
Other: No Human Rights implications arise from this report. Report P15
Other: No direct sustainability implications, including climate, health and wellbeing, community safety, or habitats regulations. Report P17
Strategic Leadership Team and Group Leaders Report P2
Monitoring Officer and Section 151 Officer Report P2, P21, P23
Timeline
2026-03-24: Cabinet considered and recommended the 2026/27 committee timetable
2 June: SPAE meeting rescheduled from 19 May to this date
2026/27 municipal year: Seven programmed Cabinet meetings and three contingency dates to be held Report P25
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13
Resolved
That Cabinet: 1.Considered the proposed Committee Timetable for the 2026/27 municipal year (Appendix A). with the amendment requested to SPAE meeting planned for 19 th May move to the 2 nd June. RESOLVED TO RECOMMEND 2. Recommended the timetable to Council for formal approval . Media
Word for word from the decision Dacorum published for this meeting.Source: democracy.dacorum.gov.uk
Report for: Cabinet Title of report: Committee Timetable 2026/27 Date: 24th March 2026 Report on behalf Councillor William Allen, Portfolio Holder for Corporate & Commercial Services of: Part: I If Part II, reason: N/A Appendices: Appendix A – Proposed Committee Timetable 2026/27 Background None papers:
Glossary of SLT – Strategic Leadership Team acronyms and PH/SLT – Portfolio Holder / Strategic Leadership Team any other OSC – Overview & Scrutiny Committee abbreviations used in this report:
Catherine Silva Donayre, Strategic Director Corporate, Commercial and Transformation
[email protected] / 01442 228332 (ext. 2332) Corporate Priorities Service improvement and delivery: Running the Council efficiently and putting residents at the heart of everything we do.
An effective committee timetable supports good governance, transparency and timely decision- making across the Council. Wards affected All wards Purpose of the report: To present the proposed Committee Timetable for the 2026/27 committee year for Cabinet consideration and recommendation to Council for approval.
The timetable establishes the annual cycle of meetings required to support the Council’s governance and decision-making processes. Recommendation(s) to the decision That Cabinet: maker(s): 1. Considers the proposed Committee Timetable for the 2026/27 municipal year (Appendix A).
2. Recommends the timetable to Council for formal approval.
Period for post policy/project review: The Committee Timetable is reviewed annually as part of the Council’s governance cycle. 1 Introduction/Background:
The Committee Timetable sets out the structure of meetings required to support the Council’s governance and decision-making processes during the committee year.
The timetable has been developed by Democratic Services in consultation with the Strategic Leadership Team, statutory officers and Leadership Support PAs with feedback from internal departments.
The proposed timetable was shared with Group Leaders prior to submission to Cabinet in order to allow cross-party consideration of the proposed structure.
2 Key Issues:
The timetable has been developed within a number of operational and statutory constraints.
These include:
• Five integrated decision-making cycles per municipal year • Statutory Budget and Council Tax approval deadlines • Statutory rent increase notification requirements • Constitutional notice and publication deadlines • Officer drafting, consultation and sign-off time • Working days only (no weekends, bank holidays or Friday evenings) • Avoidance of the August summer recess period • Avoidance of Mondays due to Town and Parish Council meeting nights. The resulting timetable represents a balanced position across these pressures.
Governance sequencing
The Committee Timetable must also allow sufficient time for reports to progress through the Council’s governance framework.
In practice, this normally follows the sequence:
• Strategic Leadership Team (SLT) • Portfolio Holder / Strategic Leadership Team (PH/SLT) • Group Leaders • Overview and Scrutiny Committee (one of the Council’s three Overview and Scrutiny Committees depending on the subject matter) • Cabinet • Council
The timetable has therefore been structured to ensure sufficient time between meetings for reports to progress through these stages, including officer preparation, consultation, political engagement and scrutiny where required.
Cabinet meeting model
The proposed timetable includes:
• Seven programmed Cabinet meetings, and • Three contingency Cabinet dates to be used only where required.
The additional programmed meetings are intended to:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.