Resolved
Cabinet: Noted the updated project cost position for the development and approved the revised cost apportionment between the HRA and General Fund. Media
AI summaryDacorum Cabinet noted updated Paradise Depot costs and approved a revised split between the Housing Revenue Account and General Fund. The scheme forecasts a net underspend of about £1.9m after warranty reclaims following contractor insolvency.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
Cabinet: Noted the updated project cost position for the development and approved the revised cost apportionment between the HRA and General Fund. Media
www.dacorum.gov.uk Cabinet
Report for: Cabinet
Title of report: Updated Project Costs and Forecast Outturn Position - Paradise Depot, Hemel Hempstead
Date: 9th June 2026
Report on behalf Councillor Simy Dhyani, Portfolio Holder for Housing and Property Services. of: Part: I If Part II, reason: N/A
Appendices: Appendix A – Community Impact Assessment Appendix B – Proposed Site Plan
Background Cabinet Report 19th November 2024 papers: Glossary of GF – General Fund acronyms and HRA – Housing Revenue Account any other ITT – Invitation to Tender JCT – Joint Contracts Tribunal abbreviations D&B – Design & Build used in this EA – Employers Agent report:
Report Author / Responsible Officer Oliver Donohoe – Investment & Delivery Senior Project Manager [email protected]
Corporate Priorities Community engagement: Engage with residents and partners to have a real say on our services and the borough Service improvement and delivery: Running the Council efficiently and putting residents at the heart of everything we do Vibrant communities: Foster arts, culture and leisure opportunities Sustainable future: Take action on the Climate and Ecological Emergency Clean, safe and green: Provide a clean, safe and green-focussed environment Homes to be proud of: Enable well-maintained and affordable homes, where people want to live Proud and thriving borough: Realise our potential as a great place to live and work with a thriving business community
Wards affected: Hemel Hempstead Town
Purpose of the report: To provide Cabinet with an updated financial position for the Paradise Depot development, which includes the residential scheme and the DENS building.
Recommendation(s) to the decision maker(s): That Cabinet:
Notes the updated project cost position for the Paradise Depot development and approves the revised cost apportionment between the HRA and General Fund.
Period for post There will be a 12-month defect liability period after practical completion. A policy/project review: 2-year review period is therefore recommended for this project. 1 Introduction/Background:
Paradise Depot is situated on Paradise Industrial Estate, approximately 0.2km to the east of Hemel Hempstead town centre. Planning permission was granted in March 2023 to construct a new residential building, providing 56 apartments for social rent, and a standalone commercial unit for DENS.
Cabinet previously approved the appointment of of ARJ Construction Ltd as Principal Contractor in June 2023. Construction commenced in November 2023. On 30th April 2024, the Council was formally notified that ARJ Construction Ltd had ceased trading and entered administration.
In November 2024, Cabinet approved the appointment of Bugler Developments Ltd to complete the remaining works following a negotiated procurement process. Since recomencment of the works, further detailed design development, cost reconcilliation and scope clarification has taken place.
The approved scope of the Paradise Depot development remains unchanged. The scheme continues to comprise 56 residential apartments for social rent (HRA) and a standalone commercial building providing a permanent Headquarters facility for DENS (General Fund).
However, as the project has progressed to detailed design and delivery following the change in contractor, several project variations have been identified, and this has resulted in a cost pressure to the General Fund cost whilst overall the project remains within the overall approved budget.
2 Key Issues/proposals/main body of the report:
The table below summarises the updated cost position for the project that is now showing a pressure on the General Fund element i.e. the DENS building. This reflects scope changes as the project progressed following the appointment of the replacement contractor.
The project variance has been presented on a gross basis and shows the impact of any potential recovery under the warranties associated with the previous contractor’s insolvency.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
FINAL: Appendix A: Paradise Depot CIA signedAppendix | 403 KB | Download |
PDF |
FINAL: Appendix B: Proposed Site PlanAppendix | 591 KB | Download |
PDF |
Paradise DepotReport | 340 KB | DownloadRead as text |
Follow Cabinet at Dacorum and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Sep 2026 | MinutesCabinet Agreed the of the previous meeting. | Agreed | Open |
| 22 Sep 2026 | Apologies for absenceThere were no apologies for absence. | Decided | Open |
| 22 Sep 2026 | Declarations of InterestThere were no declarations of Interest | Decided | Open |
| 22 Sep 2026 | Public ParticipationThere was no public participation. | Decided | Open |
| 22 Sep 2026 | Referrals to CabinetThere were no referrals to Cabinet. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.