CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Dacorum Borough Council
Cabinet, Tuesday 9 June 2026 at 7.30pm

Paradise Depot

Noted Executive 3 papers

AI summaryDacorum Cabinet noted updated Paradise Depot costs and approved a revised split between the Housing Revenue Account and General Fund. The scheme forecasts a net underspend of about £1.9m after warranty reclaims following contractor insolvency.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedRevised cost split between HRA and General Fund
MoneyNet underspend approximately £1.9mHRA underspend offsets £52k General Fund exposure
What happens nextWarranty claim being managedFunds extra costs after previous contractor insolvency
Who it affectsCouncil housing finances and tenantsPlus new DENS community headquarters

What was decided

Cabinet noted the updated cost position for the Paradise Depot development.

Cabinet approved the revised cost apportionment between the Housing Revenue Account and the General Fund.

Why

The original contractor became insolvent, so the project needs a revised cost position that still delivers a compliant, warrantable and operational scheme. Report P6, P18

A significant underspend in the Housing Revenue Account more than offsets the £52k General Fund exposure, leaving a net favourable position of about £1.9m. Report P20

What happens next

The warranty claim will be managed to fund the additional costs beyond budget that followed the previous contractor's insolvency. Report P18, P4

Health and Safety, construction regulations, and asset management arrangements will continue, with the project monitored through established governance. Report P13

The increase in General Capital Fund budget sits within the 2026/27 capital budget already approved by Council. Report P4, P18

The money

  • approximately £1.9m net underspend forecast for the overall project Report P20
  • £52k forecast exposure on the General Fund Report P20

Implications

  • Financial: The Housing Revenue Account shows a significant underspend that more than offsets a £52k General Fund exposure, giving a net underspend of about £1.9m after warranty reclaims. Report P20, P4
  • Financial: A warranty claim is being managed to fund the additional costs beyond budget caused by the previous contractor's insolvency. Report P4, P18
  • Equalities: A Community Impact Assessment found no detrimental impacts; the proposals benefit low income households, with homes let under the Council's Housing Allocation Policy and improved community facilities via the new DENS HQ. Report P8, P9
  • Climate: The construction specification is set to significantly exceed building regulation environmental requirements, with Secured by Design standards and overheating and ventilation strategies in place. Report P10, P11
  • Risk: The revised cost position reflects the current project status and delivers a compliant, warrantable and operational scheme following the original contractor's insolvency. Report P6
  • Legal: There are no direct legal implications arising from this report, and the Monitoring Officer has no further comments. Report P5, P15, P16

Who and where

  • Housing Revenue Account finances Report P20, P18
  • General Fund finances Report P20, P4
  • Low income households on the housing waiting list Report P9
  • DENS, which gains a new headquarters at the development Report P9
  • Future residents of the new homes Report P9, P10

Timeline

  • 18 February 2026: Council approved the 2026/27 capital budget, which incorporates the increased General Capital Fund budget Report P4
  • 2026/27: Capital programme period covering the revised expenditure Report P4, P18

Plain English for the jargon

  • HRA: Housing Revenue Account, the ringfenced account for council housing income and spending
  • General Fund: The council's main revenue account for non housing services
  • Secured by Design: Police crime prevention standards used in the design of new buildings
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

Cabinet: Noted the updated project cost position for the development and approved the revised cost apportionment between the HRA and General Fund. Media
Word for word from the decision Dacorum published for this meeting. Source: democracy.dacorum.gov.uk

Follow this further

Built from Dacorum's papers

What the report saysPro

Report to Cabinet

www.dacorum.gov.uk Cabinet

Report for: Cabinet

Title of report: Updated Project Costs and Forecast Outturn Position - Paradise Depot, Hemel Hempstead

Date: 9th June 2026

Report on behalf Councillor Simy Dhyani, Portfolio Holder for Housing and Property Services. of: Part: I If Part II, reason: N/A

Appendices: Appendix A – Community Impact Assessment Appendix B – Proposed Site Plan

Background Cabinet Report 19th November 2024 papers: Glossary of GF – General Fund acronyms and HRA – Housing Revenue Account any other ITT – Invitation to Tender JCT – Joint Contracts Tribunal abbreviations D&B – Design & Build used in this EA – Employers Agent report:

Report Author / Responsible Officer Oliver Donohoe – Investment & Delivery Senior Project Manager [email protected]

Corporate Priorities Community engagement: Engage with residents and partners to have a real say on our services and the borough Service improvement and delivery: Running the Council efficiently and putting residents at the heart of everything we do Vibrant communities: Foster arts, culture and leisure opportunities Sustainable future: Take action on the Climate and Ecological Emergency Clean, safe and green: Provide a clean, safe and green-focussed environment Homes to be proud of: Enable well-maintained and affordable homes, where people want to live Proud and thriving borough: Realise our potential as a great place to live and work with a thriving business community

Wards affected: Hemel Hempstead Town

Purpose of the report: To provide Cabinet with an updated financial position for the Paradise Depot development, which includes the residential scheme and the DENS building.

Recommendation(s) to the decision maker(s): That Cabinet:

Notes the updated project cost position for the Paradise Depot development and approves the revised cost apportionment between the HRA and General Fund.

Period for post There will be a 12-month defect liability period after practical completion. A policy/project review: 2-year review period is therefore recommended for this project. 1 Introduction/Background:

Paradise Depot is situated on Paradise Industrial Estate, approximately 0.2km to the east of Hemel Hempstead town centre. Planning permission was granted in March 2023 to construct a new residential building, providing 56 apartments for social rent, and a standalone commercial unit for DENS.

Cabinet previously approved the appointment of of ARJ Construction Ltd as Principal Contractor in June 2023. Construction commenced in November 2023. On 30th April 2024, the Council was formally notified that ARJ Construction Ltd had ceased trading and entered administration.

In November 2024, Cabinet approved the appointment of Bugler Developments Ltd to complete the remaining works following a negotiated procurement process. Since recomencment of the works, further detailed design development, cost reconcilliation and scope clarification has taken place.

The approved scope of the Paradise Depot development remains unchanged. The scheme continues to comprise 56 residential apartments for social rent (HRA) and a standalone commercial building providing a permanent Headquarters facility for DENS (General Fund).

However, as the project has progressed to detailed design and delivery following the change in contractor, several project variations have been identified, and this has resulted in a cost pressure to the General Fund cost whilst overall the project remains within the overall approved budget.

2 Key Issues/proposals/main body of the report:

The table below summarises the updated cost position for the project that is now showing a pressure on the General Fund element i.e. the DENS building. This reflects scope changes as the project progressed following the appointment of the replacement contractor.

The project variance has been presented on a gross basis and shows the impact of any potential recovery under the warranties associated with the previous contractor’s insolvency.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
FINAL: Appendix A: Paradise Depot CIA signedAppendix 403 KB Download
PDF
FINAL: Appendix B: Proposed Site PlanAppendix 591 KB Download
PDF
Paradise DepotReport 340 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Dacorum

Search all
  1. Paradise DepotThis decision
  2. Appointment of Principal Contractor for Paradise Depot, Hemel HempsteadApproved
  3. Appointment of Contractor Paradise DepotAgreed

More from Dacorum Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 MinutesCabinet Agreed the of the previous meeting. Agreed Open
22 Sep 2026 Apologies for absenceThere were no apologies for absence. Decided Open
22 Sep 2026 Declarations of InterestThere were no declarations of Interest Decided Open
22 Sep 2026 Public ParticipationThere was no public participation. Decided Open
22 Sep 2026 Referrals to CabinetThere were no referrals to Cabinet. Decided Open