It was agreed that the Scrutiny Co-ordinator be asked to clarity the position and report back thereon · DCC013 ‘ The risk of significant financial and reputational liabilities resulting from management of an Arm’s Length organisation’ – the absence of an allocated Lead Member for this risk was noted and officers confirmed it was an oversight and advised that Councillor Huw Jones, Lead Member for Tourism, Leisure and Youth would likely be assigned to that risk. · DCC017 ‘ The risk that the impact of welfare reforms is more significant than anticipated’ – Councillor Meirick Davies queried whether DCC017 strictly met the definition of a risk within the Council’s defined criteria. The CIM agreed that this risk did not fall strictly within the definition but it was a matter of significant importance and the Corporate Executive Team requested its inclusion together with DCC018 ‘The risk that change/modernisation projects are not implemented as intended, hindering benefit realisation. ’ The Chair referred to his recent meeting with [name removed] from the Wales Audit Office and referred to the positive Improvement Assessment Letter which had been issued. One of the two proposals for improvement highlighted the need for more information to be included on the status and outcomes of the Council’s collaboration projects and concern had been expressed over the lack of methodology for corporate governance of such projects. Consequently the Chair queried whether this aspect should be considered a risk linked to DCC015 ‘ The risk that the council cannot influence the collaboration agenda, and that further collaboration is forced upon us rather than entered into voluntarily ’. The Corporate Director Economic and Community Ambition reported ... view the full minutes text for item 6.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Lead Member / Officer: Cllr Barbara Smith / Alan Smith
Report Author: Nicola Kneale
Title: Corporate Risk Register review, February 2013
1. What is the report about?
1.1The February 2013 formal revision to the Corporate Risk Register.
2. What is the reason for making this report?
2.1To present Performance Scrutiny with the latest version of the Corporate Risk Register, as agreed by CET.
3. What are the Recommendations?
3.1That Members note the deletions, additions and amendments to the Corporate Risk Register
3.2That Members confirm that the attached Corporate Risk Register provides full coverage of the major risks facing the council at this time, and that the actions identified in the Corporate Risk Register are appropriate to address the identified risks.
4. Report details.
4.1The main changes made to the Corporate Risk Register are:
i) The revision to DCC001, ‘The risk of a serious safeguarding error where the council has responsibility’. Further work is required, so a revised deadline of 31 March 2013 has been applied.
ii) Removal of DCC002, ‘The risk of a judicial review of care home fees ruling against the council’. A regional methodology has now been agreed. The risk will continue to be monitored at a service level, but the inherent risk has reduced enough for it to be downgraded.
iii) The revision to DCC004, ‘The risk that we are unable to develop the staff and management capability to deliver the change agenda’. It was considered that the risks around HR are wider than just the change agenda. Hence the risk has been changed to, ‘The risk that the HR framework doesn't support the organisation's aims’. iv) Removal of DCC005, ‘The risk that the time and effort invested in existing large-scale collaboration projects is disproportionate to the benefits realised’. Due to the fact that the collaboration projects referred to are now almost complete, and project management has been strengthened, this is no longer considered to be a risk.
v) Revision to DCC006, ‘The risk that the economic environment worsens beyond current expectations, leading to additional demand on services and reduced income’. The residual risk was originally a C2 but has been downgraded to a D2; this reflects our predictions for the next two years. The wording has also been altered to refer to the financial climate, reflecting the fact that a partner’s budget can impact on us.
vi) Revision to DCC007, ‘The risk that critical or confidential information is lost or disclosed’. The responsibility for implementing EDRMS solutions has transferred to Alan Smith, and another mitigating action around raising awareness of information legislation to MMC has been included.
vii) Removal of DCC009, ‘The risk that strategic ICT does not enable improvement and support change’. It was felt that this has been addressed by development and delivery of a corporately-endorsed strategy. A related risk has been developed (see DCC017).
viii) Removal of DCC010, ‘The risk that our asset portfolio becomes an unmanageable liability and an obstacle to strategic planning’. CET felt much was in place to address this now, so the risk should reduce. Hence, it can also be managed at service level now.
ix) Revision to DCC011, ‘The risk of a severe weather event, over and above expected patterns of seasonal weather’. A risk was proposed around an unexpected outbreak of food poisoning. CET considered that a common theme across these two events was the fact that they were emergency events, and would be responded to in similar ways through emergency planning arrangements. Hence, the risk description has changed to ‘The risk of a severe weather, contamination, or public health event’, and the list of examples of problems has been extended.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.