Resolved
RESOLVED that the minutes of the meeting held on 18 April 2013 be received and approved as a correct record.
Communities Scrutiny Committee approved this item on Thursday 23 May 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the minutes of the meeting held on 18 April 2013 be received and approved as a correct record.
COMMUNITIES SCRUTINY COMMITTEE
Minutes of a meeting of the Communities Scrutiny Committee held in Conference Room 1a, County Hall, Ruthin on Thursday, 18 April 2013 at 9.30 am.
PRESENT
Councillors Huw Hilditch-Roberts (Chair), Rhys Hughes, Win Mullen-James, Bob Murray, Joe Welch, Cefyn Williams, Cheryl Williams and Huw Williams (Vice-Chair)
Observers: Councillors Meirick Davies and Huw Jones
ALSO PRESENT
Corporate Director Customers (HW), Rhyl Going Forward Manager (TB), Active Lifestyles Manager (RR), Sport and Physical Activity Programme Manager (SB), Corporate Communications and Marketing Manager (GW), Communications Marketing and Leisure Officer (VSM), Public Protection Manger (EJ), Scrutiny Coordinator (RE) and Committee Administrator (KEJ)
1 APOLOGIES
Councillors James Davies and Carys Guy
2 DECLARATION OF INTERESTS
No declarations of personal or prejudicial interest had been raised.
3 URGENT MATTERS AS AGREED BY THE CHAIR
No urgent matters were raised.
4 MINUTES
The minutes of the Communities Scrutiny Committee held on 28 February 2013 were submitted.
Matters Arising – Page 2, Item No. 4 Minutes: Grit Issues – The Scrutiny Coordinator advised that this item had been placed on the agenda of the next Dee Valley Member Area Group meeting on 29 April where clarification would be provided as requested.
RESOLVED that the minutes of the meeting held on 28 February 2013 be received and approved as a correct record.
5 RHYL GOING FORWARD UPDATE
The Rhyl Going Forward Manager (RGFM) submitted a report (previously circulated) providing an update on the Rhyl Going Forward (RGF) Regeneration Strategy. The strategy contained the following four work streams – West Rhyl Regeneration Area Town Centre Seafront and Tourism Live & Work in Rhyl
The RGFM elaborated upon the each of the work streams summarising the main aims and objectives for the particular areas; progress in reaching those targets, and future considerations. He also responded to a number of issues raised by members during consideration of their last update report.
Members questioned the RGFM regarding progress with individual projects and sought assurances regarding future outcomes for particular developments. He responded as follows –
explained the lack of progress with developing the Ocean Plaza site because of issues relating to the electricity power supply and flood risk confirmed that the demolition of the Honey Club was imminent following completion of the outstanding contractual issue the public enquiry for the compulsory purchase order for properties in West Rhyl would commence in May and it was hoped a second phase of demolition to create green space would be carried out at the end of May revised plans for the next phase of coastal defence works were awaited in order to assess the possibility of relocating the Skatepark to that area confirmed that a compulsory purchase order had been made for the burnt out arcade on the promenade with a public enquiry scheduled for June and negotiations were still ongoing to acquire the premises provided an update on the future of the Suncentre and its present condition and dialogue between the Council and Clwyd Leisure Limited in that regard; it was hoped that the Suncentre would continue operating as long as possible until the development of any new proposals; confirmation regarding the revised opening date for the 2013 season was still awaited.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MINUTESMinutes | 131 KB | DownloadRead as text |
Follow Communities Scrutiny Committee at Denbighshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jul 2026 | Appointment of vice-chairRESOLVED that Councillor Cheryl Williams be appointed as Vice-Chair of Communities Scrutiny Committee for the 2026-20... | Decided | Open |
| 2 Jul 2026 | MINUTESthat the minutes of the meeting held on the 19 March 2026 be received and approved as a true and correct record of th... | Approved | Open |
| 2 Jul 2026 | Scrutiny work programmethat subject to the above, the Communities Scrutiny Committee Forward Work Programme be agreed and noted. | Agreed | Open |
| 19 Mar 2026 | MINUTESthat the minutes of the meeting held on the 22 January 2026 be received and approved as a true and correct record of ... | Approved | Open |
| 19 Mar 2026 | Scrutiny work programmethat subject to the above, the Communities Scrutiny Committee Forward Work Programme be agreed and noted. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.