INTERNAL AUDIT PROGRESS REPORT

Agreed Finance 2 papers

Governance and Audit Committee agreed this item on Wednesday 3 July 2013. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

It was agreed that members be provided with a full audit report at the time of issue and that those subject to an amber/red assurance rating be considered at the committee’s next meeting. [IB to action] Members would also have the opportunity to raise issues regarding other audit reports directly with the HIAS or at the meeting. In view of members’ concerns regarding Ysgol Clawdd Offa, the HIAS provided a verbal update and the committee agreed to receive a detailed report at their next meeting. [IB to action] In response to a question from Councillor Gwyneth Kensler , the Head of Legal and Democratic Services confirmed that the Lead Member could be invited to attend. Members also considered the breakdown of internal audit work for 2013/14 and the HIAS clarified issues in response to questions thereon providing definitions for a number of work areas and the remit in terms of audit work to be carried out within those areas. With regard to School Fund Audits, the HIAS reported upon a number of school themed visits and advised that he had developed plain English guidance for schools which would be made available in September. RESOLVED that – (a) subject to implementation of the reporting requirements for the committee as detailed above, the progress report on the Internal Audit Service be received and noted, and (b) a progress report on Ysgol Clawdd Offa, Prestatyn be submitted to the next meeting of the committee on 4 September 2013 and the Lead Cabinet Member for Education also be invited to attend. [IB to action]
Word for word from the decision Denbighshire published for this meeting. Source: moderngov.denbighshire.gov.uk

Follow this further

Built from Denbighshire's papers

What the report saysPro

Report to Governance and Audit Committee

Report To: Corporate Governance Committee

Date of Meeting: 3 July 2013

Report Author: Head of Internal Audit Services

Title: Internal Audit Progress Report

1. What is the report about?

This report updates the Committee on Internal Audit’s latest progress in terms of its service delivery, assurance provision, reviews completed, performance and effectiveness in driving improvement.

2. What is the reason for making this report?

To bring the Committee up to date regarding: delivery of our Assurance Plan for 2013/14 recent Internal Audit reports issued management’s response to issues we have raised Internal Audit’s performance

3. What are the Recommendations?

 Committee considers and comments on Internal Audit’s progress and performance to date in 2013/14  Committee considers and comments on recent Internal Audit reports issued  Committee considers the responses to our follow up work

4. Internal Audit Progress

Delivery of the Internal Audit Assurance Plan 2013/14

4.1Appendix 1 provides a breakdown of our work during 2013/14, compared to the Internal Audit Strategy. It includes assurance scores and number of issues raised for the completed reviews, definitions used to form our audit assurance and the ratings used to assess the risk-levels for issues raised. Summary of Recent Internal Audit Reports

4.2Our reports use colours for assurance ratings as follows:

Green High Assurance Risks and controls well managed

Yellow Medium Assurance Risks identified but are containable at service level

Amber Low Assurance Risks identified that require meeting with Director/Lead Member

Red No Assurance Significant risks identified that require member / officer case conference

4.3Since my report in May 2013, we have issued the following reports.

Issues Raised Audit Critical Major Moderate Audit Report Comments Opinion Risk Risk Risk (Red) (Amber) (Yellow) WG Free Breakfast No report issued. Email High 0 0 0 Initiative confirmation to WG only. WG Higher Education High 0 0 0 Summary report only Student Finance Financial Systems – Medium 0 1 7 2012/13 project finalising Ruthin 2012/13

Risk Management Medium 0 0 4 2012/13 project finalising

Ysgol Clawdd Offa, Low 0 0 21 Escalation meeting 07/06/13 Prestatyn

Management’s response to issues raised by Internal Audit

4.4Most of our Internal Audit reports identify risks and control weaknesses. We rate these as critical, major or moderate risk. Management agrees actions to address the risks, including responsibilities and timescales.

4.5We report all instances where management fails to respond to our follow up work or where they exceed the agreed implementation date by more than three months. This Committee decides whether it needs to take further action, e.g. by calling the relevant people to its next meeting or asking for a written report to explain lack of progress.

4.6We currently have no issues to raise with the Committee but will provide a verbal report at the meeting on our latest follow up review of Strategic HR. Internal Audit Performance

Essential Assurance - all targets 100% Review of agreed Financial Assurance areas in Assurance Plan by 31/03/14 So far, we have completed 50% of the planned projects, with others scheduled to be completed before 31 March 2014. Review of agreed Grants & Certification Assurance areas in Assurance Plan by 31/03/14 So far, we have completed 40% of the planned projects, with others scheduled to be completed before 31 March 2014. Review of agreed Corporate Governance Assurance areas in Assurance Plan by 31/03/14 Most of these projects are scheduled for later in the year to allow time for progress on the Corporate Plan. So far, we have completed 5% of the planned projects. Review of agreed High Corporate Risk Assurance areas in Assurance Plan by 31/03/14 All of these projects are scheduled for completion by the autumn.

Customer Standards - all targets 100%

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
IA PROGRESS REPORT APPENDIXAppendix 222 KB Download
PDF
INTERNAL AUDIT PROGRESS REPORTReport 90 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Denbighshire

Search all
  1. INTERNAL AUDIT PROGRESS REPORTThis decision
  2. Internal audit scoping reportNoted
  3. Internal audit updateDecided
  4. Internal audit annual report 2023 - 24Decided
  5. Internal audit updateNoted
  6. Internal audit updateDecided

More from Denbighshire Governance and Audit Committee

All decisions
MeetingDecisionOutcome
22 Jul 2026 MINUTESRESOLVED that subject to the above, the minutes of the meeting held on the 10 June 2026 be received and approved as a... Approved Open
22 Jul 2026 Treasury management 2026/27 updateRESOLVED that; 1. The Governance and Audit committee note the performance of the TM function during 2025/26 and its c... Noted Open
22 Jul 2026 Annual governance and audit committee report 2025/26RESOLVED that, members of the Governance and Audit Committee approve the draft Annual Governance and Audit Committee ... Approved Open
22 Jul 2026 Membership of the governance and audit sub-committee of the north wales corporate joint committeeRESOLVED that Councillor James Elson be nominated as the substitute representative. Decided Open
22 Jul 2026 Governance and audit committee work programmethat subject to the above, the Governance and Audit Committee Forward Work Programme be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies