RESOLVED that Cabinet – (a) note the latest financial position and progress against the agreed budget strategy; (b) agree in principle the arrangement of a loan to Llangollen Town Council to assist with the cash flow supporting a capital investment and to delegate authority to the Head of Finance and Assets to progress the arrangement if and when required; (c) agree that £100k of the refund payment made under the Carbon Reduction Scheme be set aside for investment in new energy efficiency schemes, and (d) that a study be carried out into the impact of the reduction in car parking charges in Ruthin on the levels of car park usage and income earned from car parking in the town.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Lead Member / Officer: Councillor Julian Thompson-Hill /Paul McGrady
Report Author: Richard Weigh, Chief Accountant
Title: Finance Report
1. What is the report about?
The report gives details of the council’s revenue budget and savings as agreed for 2013/14. The report also provides a summary update of the Capital Plan as well as the Housing Revenue Account and Housing Capital Plan.
2. What is the reason for making this report?
The purpose of the report is to provide an update on the council’s current financial position and to gain agreement in principle to provide a short term loan to Llangollen Town Council.
3. What are the Recommendations?
Members note the progress against the agreed budget strategy.
To agree in principle the arrangement of a loan to Llangollen Town Council to assist with the cash flow supporting a capital investment and to delegate authority to the Head of Finance & Assets to progress the arrangement if and when required.
4. Report details
The report provides a summary of the council’s revenue budget for 2013/14 (Appendix 1). The council’s net budget is £192m. At the end of October, there is a forecast under spend on service and corporate budgets of £763k (£1,194k last month) which represents a variance of 0.60%.
Appendix 2 to the report shows the progress to date against the savings highlighted in the Medium Term Financial Plan for 2013/13. A savings target of £3.061m was agreed for the year and so far 67% have been achieved.
5. How does the decision contribute to the Corporate Priorities?
Effective management of the council’s revenue and capital budgets and delivery of the agreed budget strategy underpins activity in all areas, including corporate priorities. 6. What will it cost and how will it affect other services? Narrative supporting service forecasts where necessary is detailed below:
Business Planning & Performance - As reported last month, the service is currently projected to under spend by £40k in total. Although there is no movement to report this month, the projection includes an estimate for the investment in the digitisation of archived records. A change in the timing of this work will affect the projected outturn and will be reported on in future reports
Highways & Environment Services – The service is now showing an over spend of £237k, an increase of £88k from that reported last month. It is still hoped that the net overspend may be reduced when the full impact of the service restructure has been resolved. The main points are:
A pressure remains within School Transport relating to the number of school days in 2013/14 (one-off effect that has been largely met through the use of one-off under spends) and also an increase in demand. The service overspent by £178k last financial year, and these budgetary pressures have continued this year. Parking income levels are down compared to previous years resulting in a pressure of £108k. This has been partly offset by the allocation of £40k from last year’s under spend. The main areas affected are Rhyl and Prestatyn, the latter in particular is due to the availability of free parking at the retail park and will be a recurring pressure for the service.
Children & Family Services - The projected under spend is forecast to be £311k this month but this might rise slightly if the current demand for placements remains stable for the remainder of the financial year. The current under spend excludes the previously agreed £250k which is being set aside in a new Children with Disabilities (CWD) reserve.
Communication, Marketing & Leisure – is currently showing a small overall under spend of £7K (break-even last month). The under spend is mainly as a result of plans being put into place in advance to begin achieving next year's savings targets for the Department. It is assumed that the new Ruthin Leisure development meets its member targets over the winter months and the early indications are very encouraging.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.