Communities Scrutiny Committee, Thursday 23 January 2014 at 9.30am

RHYL GOING FORWARD PROGRAMME (QUARTERLY REPORT)

Agreed Scrutiny 6 papers

Communities Scrutiny Committee agreed this item on Thursday 23 January 2014. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

It was agreed by all Committee Members present that their thanks be recorded and passed on to the E&BDM and the Coastal Team Leader for the tremendous work they were carrying out. RESOLVED that Members of the Communities Scrutiny Committee noted the progress made.
Word for word from the decision Denbighshire published for this meeting. Source: moderngov.denbighshire.gov.uk

Follow this further

Built from Denbighshire's papers

What the report saysPro

Report to Communities Scrutiny Committee

Report to: Communities Scrutiny Committee

Date of Meeting: 23 January 2014

Lead Member: Leader and Lead Member for Economic Development

Report Author: Economic and Business Development Manager

Title: Rhyl Going Forward Programme Quarterly Report

1. What is the report about?

This report provides an update on the Rhyl Going Forward Programme.

2. What is the reason for making this report?

To evaluate and monitor the Programme’s progress and achievements in delivering its anticipated outcomes, and to identify any slippage with the programme’s delivery.

3. What are the Recommendations?

That members comment on the progress made.

4. Report details.

The most recent Programme Update reports are attached as Appendices 1a to 1d which demonstrate that in terms of the four workstreams of the programme:

West Rhyl Regeneration Area has a current status of YELLOW (Appendix 1a) Town Centre has a current status of ORANGE (Appendix 1b) Seafront and Tourism has a current status of YELLOW (Appendix 1c) Live & Work in Rhyl has a current status of ORANGE (Appendix 1d)

West Rhyl

Following the Minister’s decision to approve the Compulsory Purchase Order (CPO), work has continued both on the acquisition of the remaining properties required to deliver the Housing Improvement Project and also on the relocation of the affected residents. The team appointed to design the Green Space have undertaken community consultation events and have prepared an initial concept design for the area. The next phase of demolition will commence once the purchase of the remaining properties has been completed.

Town Centre

The County Council delivered a programme of events in the weeks before Christmas which was well received and footfall was higher than in the same period in the previous year. A task and finish group has started work on the development of a strategy for the town centre, and members of the Town Centre Management Group are continuing to look at the different models adopted by towns in neighbouring authority areas to inform the development of the future arrangements for Rhyl. Details are still awaited of the arrangements for applying for the funding set aside by Welsh Government for areas which were not successful at the first stage of the Vibrant & Viable Places application process.

Seafront & Tourism

Work has continued on the development of the case for new leisure facilities along the coast and an agenda item about future delivery options for facilities operated by Clwyd Leisure was programmed for the Cabinet meeting which was held on 14th January. Pre-application consultations about the design of the hotel proposed for the site of the former Honey Club have been taking place with the County Council’s Planning & Public Protection service and a Planning application from the chosen developer will follow. It is still anticipated that the hotel should be completed and operating by autumn 2014. The construction of the new harbour side building has continued and remains on schedule for completion in early 2014.

Live & Work in Rhyl

This is currently the least developed of all the work streams and a task and finish group has started work on the development of a Town & Area Plan for Rhyl which will identify priority actions which will contribute to the achievement of the aims and objectives for this work stream. In the interim, an officer has been appointed to deliver the Green Links project and householders in the eligible area of the town’s West ward have been approached to take advantage of the energy efficiency improvements available through the next phase of the “Arbed” scheme.

Relationship with the proposed Town & Area Plan for Rhyl

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
RGF Report: App 1a 230114Appendix 154 KB Download
PDF
RGF Report: App 1b 230114Appendix 93 KB Download
PDF
RGF Report: App 1c 230114Appendix 109 KB Download
PDF
RGF Report: App 1d 230114Appendix 96 KB Download
PDF
RGF Report: App 2 230114Appendix 99 KB Download
PDF
RHYL GOING FORWARD PROGRAMME (QUARTERLY REPORT)Report 75 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Denbighshire

Search all
  1. RHYL GOING FORWARD PROGRAMME (QUARTERLY REPORT)This decision
  2. Rhyl going forward - review and next stepsNoted
  3. Rhyl going forward programme quarterly reportNoted

More from Denbighshire Communities Scrutiny Committee

All decisions
MeetingDecisionOutcome
2 Jul 2026 Appointment of vice-chairRESOLVED that Councillor Cheryl Williams be appointed as Vice-Chair of Communities Scrutiny Committee for the 2026-20... Decided Open
2 Jul 2026 MINUTESthat the minutes of the meeting held on the 19 March 2026 be received and approved as a true and correct record of th... Approved Open
2 Jul 2026 Scrutiny work programmethat subject to the above, the Communities Scrutiny Committee Forward Work Programme be agreed and noted. Agreed Open
19 Mar 2026 MINUTESthat the minutes of the meeting held on the 22 January 2026 be received and approved as a true and correct record of ... Approved Open
19 Mar 2026 Scrutiny work programmethat subject to the above, the Communities Scrutiny Committee Forward Work Programme be agreed and noted. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies