RESOLVED that Cabinet agree the recommended approach – (a) to adopt a ‘preferred developer’ approach to the delivery of improved tourism and leisure facilities in Rhyl , including a new Aquatic Centre and to invite expressions of interest from developers for consideration by the Council; (b) to include development opportunities in all Council facilities/land/assets along Rhyl Promenade (Marine Lake to Splash Point) within the invitation for expressions of interest; (c) in parallel, to use the Council’s existing framework agreement with Alliance Liesure to produce a detailed business feasibility study and an appraisal of design and build options for the Nova; (d) to make a commitment in principle ro ring-fence operational savings generated as a result of the re-development proposals to support potential capital contributions from the Council towards delivery of the ‘whole project’, and (e) to meet with Welsh Government to explore support for a ‘special’ partnership approach to the coastal regeneration.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Lead Member / Officer: Cllr Hugh Evans / Cllr Huw Jones
Report Author: Tom Booty, Economic & Business Development Manager Jamie Groves, Head of Communication, Marketing & Leisure
Title: Renewal of Coastal Facilities in Rhyl & Prestatyn
1. What is the report about? In January 2013, Cabinet agreed to explore options for the future of the coastal leisure and tourism facilities in Rhyl & Prestatyn. Over the last 12 months, officers have worked with the Council’s Leisure Framework provider to understand the current and potential future offer for the facilities and have undertaken a soft market testing exercise. This report sets out the recommended approach to secure the development of a new Aquatic Centre in Rhyl and redevelopment of the Nova in Prestatyn.
2. What is the reason for making this report? The report is necessary to enable Cabinet to make decisions to progress the Coastal Facilities projects to the next stage.
3. What are the Recommendations?
1. Aquatic Centre, Rhyl: To adopt a ‘preferred developer’ approach to the delivery of improved tourism and leisure facilities in Rhyl, including a new Aquatic Centre and to invite expressions of interest from developers for consideration by the Council 2. To include development opportunities in all Council facilities/land/assets along Rhyl Promenade (Marine Lake to Splash Point) within the invitation for expressions of interest 3. Re-development of the Nova: In parallel, to use the Council’s existing framework agreement with Alliance Leisure to produce a detailed business feasibility study and an appraisal of design and build options for the Nova. 4. Approaches to Funding: To make a commitment in principle to ring-fence operational savings generated as a result of the re-development proposals to support potential capital contributions from the Council towards delivery of the ‘whole project’ . 5. Funding Approach to Welsh Government: To meet with Welsh Government to explore support for a ‘special’ partnership approach to the coastal regeneration
These recommendations to Cabinet were considered and supported by the Coastal Facilities Project Board at its meeting on 7th January. 4. Report details A Project Board has been established to govern the overall project to renew the leisure and tourism facilities in Rhyl & Prestatyn. Its membership includes representatives from Rhyl & Prestatyn Member Area Groups together with relevant Lead Members and officers.
The Coastal Facilities Project Board met in January and reviewed the work undertaken to date by officers following the Cabinet decision in January 2013. Having considered the advice provided, the Board supported the recommendation that two separate procurement approaches be adopted for developing the Coastal Facilities. These are as follows:
1. The recommendation to follow the route of inviting Expressions of Interest to secure a preferred developer for the new Aquatic Centre and associated developments in Rhyl was agreed for the following reasons:
The overall Coastal Facilities project (excluding the Nova development) is beyond the financial capacity of the Council at this time and external grant and private sector funding is required. However the private sector on its own is unlikely to see this as a sufficiently attractive investment opportunity, with returns on investment constrained. Therefore a shared private and public partnership approach is more likely to be achievable. But formal procurement is not achievable within the timescales the Council is considering and is also unlikely to achieve a cost effective solution – the ‘preferred developer’ route provides more opportunity for creativity and innovation from the private sector.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies