HOUSING SERVICES IMPROVEMENT PLAN

Noted Scrutiny 6 papers

Performance Scrutiny Committee noted this item on Thursday 1 May 2014. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

RESOLVED : (a) Notwithstanding the further work required to achieve the Service’s ambition to be an excellent service, to note the considerable progress made to date in relation to service improvement (b) That officers feedback to local members the outcomes of their housing estate visits and the progress made in addressing issues raised (c) That the additional information requested by members be provided, and (d) That elected members be involved with the development of the new tenancy agreement from an early stage.
Word for word from the decision Denbighshire published for this meeting. Source: moderngov.denbighshire.gov.uk

Follow this further

Built from Denbighshire's papers

What the report saysPro

Report to Performance Scrutiny Committee

Report To: Performance Scrutiny Committee

Date of Meeting: 1 May 2014

Lead Member / Officer: Councillor Hugh Irving

Report Author: Peter McHugh

Title: Housing Service Improvement Plan

1. What is the report about?

The report details the service improvements made to the Housing Service as a result of the “mock inspection” carried out by the Housing Quality Network in 2011 and outlines the performance management framework which has been established to support the service aim of continuous improvement.

2. What is the reason for making this report?

This report shall enable members to review the progress which has been made in relation to the key weaknesses identified within the “mock inspection” and to comment upon the performance management framework which has been developed.

3. What are the Recommendations?

That the Committee:

3.1Notes the progress which has been made in relation to service improvement

3.2Provides observations and comment upon the performance management framework which has been developed.

4. Report details

4.1Mock Inspection – August 2011

The Head of Housing was appointed in April 2011 and in July 2011 commissioned a “mock inspection” from the Housing Quality Network to assess performance of the service against established audit commission ratings which ranged from 3 star excellent service (top 25% of performers across the UK) to 0 star performers (bottom 10% of performers).

The inspectors used a variety of tools of techniques to undertake the inspection which included a desk top review, mystery shopping, focus group interviews, 121 meetings with staff, tenants and residents, analysis and assessments of key documents which informed their findings. The findings were then reviewed and moderated by an independent team to ensure they were consistent, rigorous and robust.

The findings from the mock inspection concluded that the service was predominantly a “traditional landlord service”, it was reactive not proactive, weaknesses outweighed strengths and commons problems were experienced across all teams. The inspection identified a number of key areas of concern which included: No performance management system was in place Lack of confidence in the IT system which resulted in lots of manual or non standardised processes No Customer satisfaction data was collected No benchmarking was undertaken No defined relet standard existed

The Housing Quality Network therefore concluded that the service was a “0” star performer and required significant improvement.

4.2Service Response to the Mock Inspection

The mock inspection provided a very damning verdict on the performance of the service and was met by a combination of shock, incredulity, anxiety and denial by some managers and staff. Further internal audit reports relating to maintenance and income management services were received which give further cause for concern.

However, the mock inspection was also a catalyst for change and discussions with staff confirmed that most staff members yearned for change and were up for it. Given the scale of the challenge and the fact that every single service area had been assessed as being weak the Head of Housing embarked upon a root and branch review and restructuring programme.

A quality and performance team was established with the stewardship of a newly appointed Quality and Performance Manager who has taken a lead role in developing the performance management framework.

The following services have been restructured to meet the recommendations arising from the mock inspection:

Senior Management Team Housing Management Tenant Participation Business Support Asset Management Warden Service Housing Strategy

The restructuring of the Homelessness and Housing Options Team is due to be completed in September 2014 which shall bring to a conclusion the major review and restructuring of all the key service areas bar the DLO which shall undergo significant change as a result of the Housing Excellence project.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
App 1 Quality & Perfo Challeenge Framework. v1 April 14Appendix 309 KB Download
PDF
App 2 Excellent HousingAppendix 104 KB Download
PDF
App 3 Quarter 3 PI's in top quartileAppendix 15 KB Download
PDF
App 4 Lettable standard feb 2012Appendix 458 KB Download
PDF
App 5 Communities Scrutiny report on SIP 1 May 2014 Equality Impact Assessment TemplateAppendix 180 KB Download
PDF
HOUSING SERVICES IMPROVEMENT PLANReport 60 KB DownloadRead as text

At this meeting

Whole meeting

More from Denbighshire Performance Scrutiny Committee

All decisions
MeetingDecisionOutcome
16 Jul 2026 Minutes of the last meetingResolved : that the minutes of the Performance Scrutiny Committee meeting held on 11 June 2026 be approved as a true ... Approved Open
16 Jul 2026 Scrutiny work programmeResolved : subject to the changes and additions reported during the report’s presentation, along with those agreed du... Agreed Open
11 Jun 2026 Appointment of vice-chairResolved : to elect Councillor Gareth Sandilands as Vice-Chair of Performance Scrutiny Committee for the 2026/27 muni... Decided Open
11 Jun 2026 Minutes of the last meetingResolved : subject to the inclusion of Councillor Ellis’ name in the list of apologies, that the minutes of the Perfo... Approved Open
11 Jun 2026 Scrutiny work programmeResolved : subject to the inclusions agreed during the course of the meeting, to confirm its programme of future work... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies