RESOLVED that Cabinet – (a) authorise the commencement of feasibility studies in respect of the projects set out in Appendix 2 to the report, the completion of which will be subject of future budget decisions; (b) note the authority will continue to maintain provision at Ysgol Borthyn; (c) note the requirement to consult on the future of Ysgol Rhewl following the feasibility study of the Glasdir site, and (d) approve proceeding to formal consultation for the proposed change to a school with religious designation for Ysgol Esgob Morgan by closing it as a community school and re-opening it as a Church in Wales Voluntary Controlled school as of the 1st September 2015.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Lead Member / Officer: Councillor Eryl Williams, Lead Member for Education
Report Author: Head of Customers and Education Support
Title: Modernising Education Programme
1. What is the report about?
This report is to update Cabinet Members of the progress on the Modernising Education Programme, and in particular seek approval for projects within the Programme. It also provides an overview of potential projects to be funded as part of the Corporate Plan.
2. What is the reason for making this report?
The Council is progressing an ambitious programme for investment in the school estate. This report provides information for Members to review current progress and understand the capital required for all of the projects. It also seeks approval to progress to the next stage of work for some projects.
3. What are the Recommendations?
Cabinet are asked:
(i) To authorise the commencement of feasibility studies in respect of the projects set out in Appendix 2, the completion of which will be subject of future budget decisions.
(ii) To note the authority will continue to maintain provision at Ysgol Borthyn.
(iii) To note the requirement to consult on the future of Ysgol Rhewl following the feasibility study of the Glasdir site.
(iv) To approve proceeding to formal consultation for the proposed change to a school with a religious designation for Ysgol Esgob Morgan by closing it as a community school and re-opening it as a Church in Wales Voluntary Controlled school as of the 1st September 2015. 4. 21st Century Schools Programme
4.1The 21st Century Schools Programme continues to make progress with the business case approval mechanisms now completed for 3 of the 5 projects as illustrated below. The current financial commitments for 21st Century Schools Programme are attached in Appendix 1.
Project Strategic Outline Full Business Timelines Outline Business Business Justification Case (SOC) Case (OBC) Case Case (BJC) (FBC) Rhyl New Approved Combined Business Case Anticipated School September Approved March 2014 Completion 2013 date – January 2016 Ysgol Glan Approved Approved Scheduled Anticipated Clwyd May 2013 October to be Completion 2013 submitted date – July Spring 2015 2017 Shared Submitted tbc Tbc Anticipated Faith May 2014 Completion Secondary date – August 2018 Ysgol Bro Approved Completed Dyfrdwy April 2013 – March 2014 Bodnant Approved Anticipated Community April 2013 Completion School date – July 2016
4.2Rhyl New School Project
4.3In February 2014 Council gave approval for the Full Business Case for the Rhyl New School project to be submitted to the Welsh Government who subsequently confirmed their approval in April 2014. A separate Part II report is on this agenda regarding the next steps for this project.
4.4Bodnant Community School
4.5The Bodnant Community School extension project continues to progress. Members approved the Detailed Design stage of this project in February 2013. The Business Justification Case was approved by the Welsh Government in April 2013 and this allowed the Council to enter into a contract with the Welsh Government for the sum of £1.67m as their element of match funding for the project. Approval will be sought via the Council’s regular Capital reports for the remainder of the Council’s contribution of approximately £1.411m towards this project. 4.6 The planning application was submitted in June 2014, and is scheduled to be determined in July 2014. The current project timetable suggests an award of contract by November 2014. This should enable commencement of works by the start of 2015 and an estimated completion date of July 2016.
4.7Faith Schools
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.