Resolved
RESOLVED that the application be DEFERRED pending investigation of the complaint made to Natural Resources Wales.
Planning Committee deferred this item on Wednesday 12 November 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the application be DEFERRED pending investigation of the complaint made to Natural Resources Wales.
Heading:
REFERENCE NO. 31/2013/1079/PFHY LAND AT ELWY MEADOWS LOWER DENBIGH ROAD, ST ASAPH
Graham Boase Application Site Head of Planning & Public Protection Denbighshire County Council Date 25/9/2014 Scale 1/2500 Caledfryn Centre = 303891 E 372442 N Smithfield Road This plan is intended solely to give an indiction of the LOCATION of Denbigh the application site which forms the subject of the accompanying report. Denbighshire LL16 3RJ It does not form any part of the application documents, and should not be taken as representative of the proposals to be considered, which are Tel: 01824 706800 Fax: 01824 706709 available for inspection prior to the meeting.
This map is reproduced from Ordnance Survey material with the permission of Ordnance Survey on behalf of the Controller of Her Majesty's Stationery Office. © Crown copyright. Unauthorized reproduction infringes Crown copyright and may lead to prosecution or civil proceedings. Denbighshire County Council. 100023408. 2011.
Atgynhyrchir y map hwn o ddeunydd yr Ordnance Survey gyda chaniatâd yr Ordnance Survey ar ran Rheolwr Llyfrfa Ei Mawrhydi © Hawlfraint y Goron. Mae atgynhyrchu heb ganiatâd yn torri hawlfraint y Goron a gall hyn arwain at erlyniad neu achos sifil. Cyngor Sir Ddinbych. 100023408. 2011. Emer O'Connor WARD : Trefnant
WARD MEMBER(S): Cllr Meirick Lloyd Davies
APPLICATION NO: 31/2013/1079/PFHY
PROPOSAL: Installation of micro hydro electric scheme
LOCATION: Land at Elwy Meadows Lower Denbigh Road St Asaph
APPLICANT: [name removed] Wales Hydro Power Ltd
CONSTRAINTS: C2 Flood Zone Main River
PUBLICITY Site Notice – No UNDERTAKEN: Press Notice – No Neighbour letters - Yes
CONSULTATION RESPONSES: CEFN MEIRIADOG COMMUNITY COUNCIL – “Cefn Meiriadog Community Council have no objections, they fully support this application”
ST ASAPH CITY COUNCIL – “Folllowing a meeting on Monday 27th October with [name removed] from Welsh Hydro Power Ltd., St. Asaph City Council have no objections to the Hydro System per se, we would insist on a maintenance programme being included and that the weir be fit for purpose prior to the installation of the Hydro System. We ask for assurance from Planning that these conditions are in place prior to approval of the planning.”
TREFNANT COMMUNITY COUNCIL - Comments awaited
NATURAL RESOURCES WALES (NRW) In relation to the amended proposals – NRW have no objection to the application. - ENVIRONMENTAL PERMITTING (ABSTRACTION / IMPOUNDMENT LICENSING) - NRW confirm they have no objection in principle to the proposals and are able to issue an abstraction licence. - FLOOD RISK – NRW have reviewed the revised Flood Consequences Assessment and confirm the contents are generally commensurate to the type, nature, and scale of the development. Welcome proposals to incorporate flood proofing measures within the turbine house. - FLOOD DEFENCE CONSENT – In accordance with the Water Resources Act 1991 and the Land Drainage Byelaws, the prior written consent of Natural Resources Wales has been granted for the works and structures located in, under, over or within 7 metres of the bank top of the Afon Elwy, designated "main river" (Consent NE2013LD125B). Temporary in- channel works require separate Flood Defence Consent from NRW. - POLLUTION CONTROL AND WASTE MANAGEMENT – NRW outline measures required to minimise impacts on the watercourse, to accommodate any oil storage facilities and disposal of waste excavation or building materials - PROTECTED SPECIES – NRW consider the surveys and assessment in respect of statutory protected species to have been completed to a satisfactory standard for the purpose of informing the decision making process
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
AGENDA ITEM 11: APPENDIXAppendix | 398 KB | DownloadRead as text |
PDF |
APPLICATION NO. 31/2013/1079/PFHY: LAND AT ELWY MEADOWS, LOWER DENBIGH ROAD, ST. ASAPHAgenda | 6 KB | Download |
Follow Planning Committee at Denbighshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | MINUTESthat the minutes from the meeting held on the 15 July 2026 be received and approved as a true and correct record of t... | Approved | Open |
| 15 Jul 2026 | MINUTESthat the minutes from the meeting held on the 17 June 2026 be received and approved as a true and correct record of t... | Approved | Open |
| 17 Jun 2026 | MINUTESthat the minutes of the Planning Committee meeting held on the 13 May 2026 be received and approved as a true and cor... | Approved | Open |
| 13 May 2026 | Appointment of chairRESOLVED that Councillor Mark Young be appointed Chair of the Planning Committee for the 2026/27 municipal year. | Decided | Open |
| 13 May 2026 | Appointment of vice-chairRESOLVED that Councillor Alan James be appointed Vice-Chair of the Planning Committee for the 2026/27 municipal year. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.