BUDGET PROCESS 2015/16 - 2016/17

Agreed Finance 6 papers

Governance and Audit Committee agreed this item on Wednesday 28 January 2015. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

RESOLVED – that Corporate Governance Committee:- (a) receives and notes the contents of the report on the latest update, and (b) agrees that a report of the outcome of the SLT meeting on the 5 th February, 2015 be presented to the Corporate Governance Committee. (RW to Action)
Word for word from the decision Denbighshire published for this meeting. Source: moderngov.denbighshire.gov.uk

Follow this further

Built from Denbighshire's papers

What the report saysPro

Report to Governance and Audit Committee

Report To: Corporate Governance Committee

Date of Meeting: 28th January 2015

Lead Member / Officer: Councillor Julian Thompson-Hill /Paul McGrady

Report Author: Richard Weigh, Chief Accountant

Title: Budget Process 2015/16

1. What is the report about?

The report gives an update on the process to deliver the revenue budget for 2015/16.

2. What is the reason for making this report?

To provide an update of the latest position.

3. What are the Recommendations?

To consider the latest update and comment as appropriate.

4. Report details

Since the last update, the budget process has moved into Phase 3 which is focussed on finalising the 2015/16 budget (Appendix 1 shows the illustration of the budget process for reference). The process will revert to consideration of the 2016/17 budget with member budget workshops arranged to focus on saving proposals in February and March 2015 (this will become Phase 4). The forecast budget gap for 2016/17 is approximately £8.8m. Savings of £2.7m have been approved as part of the current process meaning the remaining gap is approximately £6.1m.

The table of key events in the process to the end on March 2015 is shown as Appendix 2. Further dates and details will be added following a scheduled budget session with SLT in February and will be informed by the forthcoming budget workshops:

A report was approved by Cabinet on 13th January 2015 that set out recommendations to be made to Council on 3 rd February. The full report and appendices are attached as Appendix 3.

The report sets out the proposals to balance the 2015/16 budget, including raising Council Tax by an average of 2.75% (the level assumed in the council’s budget plans) and use of general balances. Following the member budget workshop in December, it also includes a formal recommendation to prioritise the delivery of the Corporate Plan in future budget rounds. : 5. How does the decision contribute to the Corporate Priorities?

Effective management of the council’s budgets and delivery of the agreed budget strategy underpins activity in all areas, including corporate priorities.

6. What will it cost and how will it affect other services?

The council may need to deliver savings of approximately £17m over the next two financial years.

7. What are the main conclusions of the Equality Impact Assessment (EqIA) undertaken on the decision?

An EqIA will be completed for all relevant proposals as the process develops.

8. What consultations have been carried out with Scrutiny and others?

The report to Council on 9th December highlighted the significant consultation process built into the process. This includes:

In addition to regular reports on the process to the Corporate Governance Committee, the budget process has been considered by CET, SLT, Cabinet Briefing and Council Briefing meetings. Two of the individual proposals have also been considered by scrutiny committees – these are CCTV (PPP08) and Provider Services (ABS02). The latter proposal has also been the subject of a specific Task & Finish Group set up by the Performance Scrutiny Committee to examine options for delivering high quality care services.

By the end of the 2015/16 budget setting process, there will have been at least ten budget workshops held with elected members to examine service budgets and consider budget proposals.

Details about the purpose and responses to the ‘Cutting Our Cloth’ public engagement exercise - which has yielded 822 survey responses and over 5,000 website hits.

In addition to the public engagement exercise, the council had informed all Town and Community councils about the proposed cuts and hosted a meeting for all the councils to discuss and debate the proposals. There are ongoing discussions between some of the county council's services and some Town councils about the impact of the proposals and whether or not the Town councils would consider funding some of the activities if the cuts are made. These discussions are continuing.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
BUDGET PROCESS 2015/16: 2016/17Report 60 KB DownloadRead as text
PDF
Budget App 1Appendix 55 KB Download
PDF
Budget App 2Appendix 165 KB Download
PDF
Budget App 3aAppendix 238 KB Download
PDF
Budget App 3bAppendix 29 KB Download
PDF
Budget App 3cAppendix 30 KB Download

At this meeting

Whole meeting

On this subject at Denbighshire

Search all
  1. BUDGET PROCESS 2015/16 - 2016/17This decision
  2. Budget update - medium term financial plan (mtfp) and budget processNoted
  3. Budget processDecided
  4. Budget process updateDecided
  5. Budget process 2017/18Decided
  6. Budget process 2017/18Decided

More from Denbighshire Governance and Audit Committee

All decisions
MeetingDecisionOutcome
22 Jul 2026 MINUTESRESOLVED that subject to the above, the minutes of the meeting held on the 10 June 2026 be received and approved as a... Approved Open
22 Jul 2026 Treasury management 2026/27 updateRESOLVED that; 1. The Governance and Audit committee note the performance of the TM function during 2025/26 and its c... Noted Open
22 Jul 2026 Annual governance and audit committee report 2025/26RESOLVED that, members of the Governance and Audit Committee approve the draft Annual Governance and Audit Committee ... Approved Open
22 Jul 2026 Membership of the governance and audit sub-committee of the north wales corporate joint committeeRESOLVED that Councillor James Elson be nominated as the substitute representative. Decided Open
22 Jul 2026 Governance and audit committee work programmethat subject to the above, the Governance and Audit Committee Forward Work Programme be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies