Resolved
RESOLVED that Council unanimously approve the Final Business Case for Ysgol Glan Clwyd.
County Council approved this item on Tuesday 14 April 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that Council unanimously approve the Final Business Case for Ysgol Glan Clwyd.
Report To: Full Council
Date of Meeting: 14th April 2015
Lead Member / Officer: Councillor Eryl Williams, Lead Member for Education
Report Author: Head of Customers and Education Support
Title: Approval of Final Business Case for Ysgol Glan Clwyd Redevelopment
1. What is the report about?
The report seeks to inform Council of the current position with regard to the Council’s submission of the Final Business Case for Ysgol Glan Clwyd, St Asaph to the Welsh Government.
2. What is the reason for making this report?
The Welsh Government has previously approved the Strategic Outline Case (May 2013) and Outline Business Case (October 2013) for this project. Approval is now required for the Final Business Case to be considered for approval by Welsh Government.
3. What are the Recommendations?
Recommend approval of the Final Business Case for Ysgol Glan Clwyd.
4. Report details.
4.1The Council’s Corporate Plan details the Council’s ambition to deliver significant investment in the Council’s School Building’s portfolio between 2012-17. A significant element of this work will be the delivery of the Band A projects for the 21st Century Schools Programme.
21st Century Schools Programme
The Welsh Government provided approval in principal for £36.7m as their 50% contribution towards the 21st Century Schools Programme which includes 5 projects in December 2011. Subsequent to this the Welsh Government have worked with all local authorities to ascertain how the overall £1.2 billion investment across Wales can be allocated into deliverable workstreams for individual local authorities.
All projects within the 21st Century Schools Programme (21st CSP) will be required to follow the guidance for Business Case approvals as defined in the HM Treasury Model. For projects below £5m a Business Justification Case will require approval whilst for projects above £5m approval of the Strategic Outline Case (SOC), Outline Business Case (OBC) and Full Business Case (FBC) will be required.
4.2The Ysgol Glan Clwyd project will provide an extended and refurbished school building to meet the growing demand for Welsh Medium Education in the north of the County.
Cabinet gave approval in July 2013 for approximately £1.0m to fund Phases 1 & 2 (Concept and Detailed Design) works which would enable the project to be progressed to a stage where approval could be sought for the full business case and contractors proposals received.
In August 2014 Willmott Dixon were appointed as the lead contractor following a mini competition amongst the six contractors appointed to the relevant value band for the North Wales Construction Framework. They have been engaged to produce the design stages of the school with appropriate break clauses prior to the construction stage.
The Stage C Design Report was submitted by Willmott Dixon to Denbighshire in late January 2015 and is a key milestone document which summarises the feasibility undertaken over past 4 months.
The key objectives are: • Give a comprehensive overview of the feasibility undertaken; • Demonstrate technical proficiency appropriate to the design of the building and site; • Present costing information which demonstrates that the school can be delivered to an agreed budget; • Demonstrate an achievable master programme for the project which reflects possible outcomes of the planning process; • Highlight any risks which remain with the project and show these can be mitigated and managed through the next stages of the project; • Present a level of information on the feasibility to receive successful Denbighshire / Welsh Government funding approval and to enable the authority to move forward to the detailed stages of the project.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
APPROVAL OF FINAL BUSINESS CASE FOR YSGOL GLAN CLWYD REDEVELOPMENTReport | 239 KB | DownloadRead as text |
PDF |
Council 14042015: Ysgol Glan Clwyd: Equality Impact AssessmentReport | 141 KB | Download |
PDF |
Council 14042015: Ysgol Glan Clwyd: Full Business Case v1.0Report | 832 KB | Download |
Follow County Council at Denbighshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Jul 2026 | MINUTESRESOLVED that the minutes of the meeting held on the 12 May 2026 subject to the agreed corrections be received and co... | Agreed | Open |
| 7 Jul 2026 | Council performance self-assessment 2025 to 2026 and performance update report october 2025 to march 2026RESOLVED that the Council I. noted the six-monthly Performance Update Report and Citizens' Voice Report; II. noted th... | Noted | Open |
| 7 Jul 2026 | Strategic equality and diversity group (sedg) annual statement 2025 to 2026RESOLVED that Council: I. acknowledged the Strategic Equality and Diversity Group Annual Statement for 2025/26; and I... | Decided | Open |
| 7 Jul 2026 | Pay policy statement 2026/27RESOLVED that Council: I. approved the Pay Policy Statement for 2026/27 as recommended by the Senior Leadership Remun... | Approved | Open |
| 7 Jul 2026 | Appointment of county councillor to the standards committeeRESOLVED that Councillor Andrea Tomlin be appointed as the County Council representative on the Standards Committee. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.