Denbighshire County Council
Performance Scrutiny Committee, Thursday 16 April 2015 at 9.30am

CORPORATE RISK REGISTER REVIEW - APRIL 2015

Decided Scrutiny 3 papers

Performance Scrutiny Committee decided this item on Thursday 16 April 2015. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

RESOLVED – that Performance Scrutiny Committee:- ( a ) subject to the above observations, notes the deletions, additions and amendments to the Corporate Risk Register; and (b) requests the 'Cutting Our Cloth' Task and Finish Group to assess the impact of ... view the full minutes text for item 6.
Word for word from the decision Denbighshire published for this meeting. Source: moderngov.denbighshire.gov.uk

Follow this further

Built from Denbighshire's papers

What the report saysPro

Report to Performance Scrutiny Committee

Report to: Performance Scrutiny Committee

Date of Meeting: 16th April 2015

Lead Member / Officer: Lead Member for Modernisation & Performance/ Head of Business Improvement & Modernisation

Report Author: Strategic Planning Manager

Title: Corporate Risk Register review, April 2015

1. What is the report about?

1.1The April 2015 formal revision to the Corporate Risk Register.

2. What is the reason for making this report?

2.1A formally updated version of the Corporate Risk Register was agreed at Cabinet Briefing and is presented for consideration at Performance Scrutiny.

3. What are the recommendations?

3.1That Performance Scrutiny notes the deletions, additions and amendments to the Corporate Risk Register, and has the opportunity to comment.

4. Report details

4.1The Corporate Risk Register enables the Council to manage the likelihood and impact of risks that it faces by evaluating the effect of any current mitigating actions, and recording deadlines and responsibilities for further action that should enable tighter control.

4.2The Corporate Risk Register has been developed by, and is owned by, the Corporate Executive Team. The process for reviewing the Corporate Risk Register is as follows: - Services are encouraged to review their risk registers twice per year (according to the Corporate Risk Management methodology) prior to each Corporate Risk Register review, and also prior to their Service Performance Challenge meetings. Any issues or queries are discussed in the Service Performance Challenge meetings. - The Corporate Improvement Team analyses all service risk registers to identify any risks of corporate significance, or any risk themes emerging across services. - Updates on current corporate risks are collected from risk owners, and updates on mitigation actions are collected from action owners. - Individual meetings are held with the Chief Executive and each Corporate Director to discuss the risks for which they are lead. Consideration is given to whether the risk remains, whether the scores are accurate, and whether any new risks under their jurisdiction need to be included. - A risk workshop is held with Cabinet and CET to review existing risks; discuss progress on agreed mitigation actions; discuss and agree new corporate risks; review and update residual risk scores; update existing controls (in light of completed actions); and agree any new actions required to mitigate risks.

4.3The Corporate Risk Register is formally reviewed twice yearly by Cabinet and CET. However, any significant new or escalating risks are brought to the attention of CET (via the Corporate Improvement Team) as and when they are identified. CET then take a view as to whether that risk should be included in the Corporate Risk Register.

4.4Following each formal review of the Corporate Risk Register (twice per year), the revised document is presented to Performance Scrutiny.

4.5On this occasion, Cabinet Briefing formally reviewed the Corporate Risk Register on Monday, 13th April. Any amendments to the register made at that meeting will be verbally reported to Performance Scrutiny on Thursday 16 th April.

4.6Actions identified to address corporate risks are included in Service Plans (where appropriate), which enables Performance Scrutiny Members to monitor progress. Any performance issues in relation to the delivery of these activities should be highlighted as part of the Service Performance Challenge process.

4.7The Council’s Internal Audit function provides independent assurance on the effectiveness of the internal control procedures and mechanisms in place to mitigate risks across the council. It also offers independent challenge to ensure the principles and requirements of managing risk are consistently adopted throughout the council. Internal Audit Services also use information from our service and corporate risk registers to inform its forward work programme.

5. How does the decision contribute to the Corporate Priorities?

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CORPORATE RISK REGISTER REVIEW: APRIL 2015Report 73 KB DownloadRead as text
PDF
Corp Risk App 1Appendix 71 KB Download
PDF
Corp Risk App 2Appendix 3.5 MB Download

At this meeting

Whole meeting

On this subject at Denbighshire

Search all
  1. CORPORATE RISK REGISTER REVIEW - APRIL 2015This decision
  2. Information report - corporate risk register review - september 2025Noted
  3. Corporate risk register reviewNoted
  4. Corporate risk registerNoted
  5. Corporate risk register (february review)Decided
  6. Corporate risk register review - september 2021Decided

More from Denbighshire Performance Scrutiny Committee

All decisions
MeetingDecisionOutcome
16 Jul 2026 Minutes of the last meetingResolved : that the minutes of the Performance Scrutiny Committee meeting held on 11 June 2026 be approved as a true ... Approved Open
16 Jul 2026 Scrutiny work programmeResolved : subject to the changes and additions reported during the report’s presentation, along with those agreed du... Agreed Open
11 Jun 2026 Appointment of vice-chairResolved : to elect Councillor Gareth Sandilands as Vice-Chair of Performance Scrutiny Committee for the 2026/27 muni... Decided Open
11 Jun 2026 Minutes of the last meetingResolved : subject to the inclusion of Councillor Ellis’ name in the list of apologies, that the minutes of the Perfo... Approved Open
11 Jun 2026 Scrutiny work programmeResolved : subject to the inclusions agreed during the course of the meeting, to confirm its programme of future work... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies