Resolved
RESOLVED that Cabinet – (a) note the 2015/16 budgets and savings , and (b) approve the proposals to increase expenditure on highway maintenance by £800k per year and confirm the assumptions noted within the Plan.
Cabinet noted this item on Tuesday 2 June 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that Cabinet – (a) note the 2015/16 budgets and savings , and (b) approve the proposals to increase expenditure on highway maintenance by £800k per year and confirm the assumptions noted within the Plan.
Report To: Cabinet
Date of Meeting: 2nd June 2015
Lead Member / Officer: Councillor Julian Thompson-Hill /Paul McGrady
Report Author: Richard Weigh, Chief Accountant
Title: Finance Report & Corporate Plan Update
1. What is the report about?
The report sets out the council’s budget, agreed savings and Capital Plan for 2015/16. The report also provides an updated position on the Corporate Plan and a proposal to increase the investment in highway maintenance.
2. What is the reason for making this report?
The purpose of the report is to provide an update on the council’s current financial position and to approve amendments to the Corporate Plan.
3. What are the Recommendations?
Members note the 2015/16 budgets and savings.
Members approve the proposals to amend the Corporate Plan:
Increase expenditure on highway maintenance by £800k per year and confirm the assumptions noted within the Plan
4. Report details
The report provides a summary of the council’s revenue budget for 2015/16 detailed in Appendix 1. The council’s net revenue budget is £185m (£188m in 14/15). A summary of saving proposals agreed is shown as Appendix 2.
Corporate Plan
When the Corporate Plan was launched in 2012, it set out an ambitious programme of capital investment in schools, roads, social care and modernisation that underpinned the priorities the council set for the current administrative term. The ambition within the Plan was set against the financial reality of delivering significant investment in priorities at the same time as reducing expenditure in other areas.
The delivery of the Plan is reliant on the council securing revenue budget to fund borrowing and identifying and maintaining significant cash reserves. It also relies upon government grant to help deliver the 21st Century Schools programme and in previous financial years, government grant has also supported the funding of additional investment highways. However, in 2012, although a funding plan was identified, it was not certain that the costs identified and levels of resource to fund them could actually be secured.
Since 2012, as the Plan has developed, the funding underpinning it has moved from an aspirational forecast to a robust, affordable strategy. To make the Plan affordable, some revisions have been necessary alongside changes in planning assumptions. Such changes are inevitable in long-term financial planning.
In February 2015, as part of the proposals to set the budget for 2015/16, a decision was taken to prioritise the delivery of the Corporate Plan in future budget rounds. Alongside this, a summary of the latest version of the Plan was presented which is set out below:
Aspirational Affordable Plan Plan 2012 Feb 2015 £m £m Schools – 21st Century Programme 74 69 Schools – Modernisation Programme 23 17 Social Care – Extra Care Housing 21 21 Regeneration – Office Accommodation 6 0 Highways 10 12 Total Estimated Capital Cost 134 119 Funded By: Welsh Government Grant 42 48 Council Cash Reserves 20 24 Council Borrowing 58 33 External Contributions (Extra Care) 14 14 Total Funding 134 119
The key changes to the original Plan are the removal of the Office Accommodation project and a reduced estimated cost of the 21 st Century Schools programme. These adjustments, along with the resources already identified and earmarked, mean that the Plan is now both affordable and deliverable. Crucially, the council has continued to prioritise the delivery of the Plan and in doing so has ensured the resources required have been actually committed. This has been underpinned by a policy of any unallocated cash surpluses or contingencies being used to support the Plan.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
FINANCE REPORT: APP 1Appendix | 30 KB | Download |
PDF |
FINANCE REPORT: APP 2Appendix | 225 KB | Download |
PDF |
FINANCE REPORT: APP 3Appendix | 124 KB | Download |
PDF |
FINANCE REPORT AND CORPORATE PLAN UPDATEReport | 68 KB | DownloadRead as text |
Follow Cabinet at Denbighshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Jul 2026 | ApologiesChief Executive | Decided | Open |
| 28 Jul 2026 | Declaration of interestsCouncillor Jason McLellan – Personal and Prejudicial Interest – Agenda Item Nos. 9 & 10 | Decided | Open |
| 28 Jul 2026 | Urgent mattersNo urgent matters had been raised. | Decided | Open |
| 28 Jul 2026 | MINUTESRESOLVED that the minutes of the meeting held on 30 June 2026 be received and confirmed as a correct record. | Decided | Open |
| 28 Jul 2026 | Denbighshire county council digital strategy 2026 - 2031RESOLVED that Cabinet – (a) approve the Denbighshire County Council Digital Strategy 2026 – 2031 (Appendix 1 to the r... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.