Cabinet, Tuesday 30 June 2015 at 10.00am

FINANCE REPORT

Agreed Executive 5 papers

Cabinet agreed this item on Tuesday 30 June 2015. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

RESOLVED that Cabinet notes the budgets set for 2015/16 and progress against the agreed budget strategy .
Word for word from the decision Denbighshire published for this meeting. Source: moderngov.denbighshire.gov.uk

Follow this further

Built from Denbighshire's papers

What the report saysPro

Report to Cabinet

Report To: Cabinet

Date of Meeting: 30th June 2015

Lead Member / Officer: Councillor Julian Thompson-Hill /Richard Weigh

Report Author: Steve Gadd, Chief Accountant

Title: Finance Report

1. What is the report about?

The report gives details of the council’s revenue budget and savings as agreed for 2015/16. The report also provides a summary update of the Capital Plan as well as the Housing Revenue Account and Housing Capital Plan.

2. What is the reason for making this report?

The purpose of the report is to provide an update on the council’s current financial position.

3. What are the Recommendations?

Members note the budgets set for 2015/16 and progress against the agreed budget strategy.

4. Report details

The report provides a summary of the council’s revenue budget for 2015/16 detailed in Appendix 1. The council’s net revenue budget is £185m (£188m in 14/15). The position on service and corporate budgets is a forecast underspend of £0.534m. Further narrative around the reasons for variances and the risks and assumptions underlying them are outlined below.

Savings of £7.3m were agreed as part of the budget and a summary of the savings is shown as Appendix 2. 72% of the savings have already been achieved. Progress on the remaining 28% will be monitored closely over the coming months, however there is a high degree of confidence that the majority of these savings will also be achieved.

5. How does the decision contribute to the Corporate Priorities?

Effective management of the council’s revenue and capital budgets and delivery of the agreed budget strategy underpins activity in all areas, including corporate priorities. 6. What will it cost and how will it affect other services?

Significant service narratives are shown in the following paragraphs.

Children’s Services – The service is currently expected to underspend by £80k due to a projected decrease in legal costs. However projections in this service can change as the year progresses due to possible in-year changes in high cost placements.

Other Service Risks / Assumptions – Although other services are currently projected to break even there are a number of risks and assumptions that will be monitored closely over the coming months and reported to Members. These include: Early indications are that Leisure income levels remain strong and may result in a positive budget position as the year progresses. Risks around School Transport, Parking and the work carried out on behalf of the Trunk Road Agency remain in 2015/16. It is currently projected that management action already identified during 2014/15 will allow the Highways and Environmental Service to break-even overall this year. The proposal to create and increase a severe weather reserve from the previous year’s Highways and Environmental Service underspend contained in the Financial Outturn Report (which also absorbed the existing winter maintenance reserve and a previous provision set aside for floods) will help to mitigate the financial risks associated with the cost of responding to any future severe weather events. It is projected that this contingency will enable volatile service areas such as Winter Maintenance to be delivered within existing budgets.

Schools brought forward balances of £3.538m from 2014/15. They are currently working on detailed financial plans for the new academic year.

Corporate – It is currently projected that there will be an underspend on Corporate budgets of £0.454m as a result of an ongoing review of contingency budgets held centrally. The current assumption is that corporate underspends will be used to support the delivery of the Corporate Plan.

Corporate Plan cash reserves at the beginning of 2015/16 are £17.413m. Allowing for projected funding and expenditure during the year, the Corporate Plan balance at the end of the year is estimated to be £6.538m.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
FINANCE REPORT: APP 1Appendix 46 KB Download
PDF
FINANCE REPORT: APP 2Appendix 225 KB Download
PDF
FINANCE REPORT: APP 3Appendix 19 KB Download
PDF
FINANCE REPORT: APP 4Appendix 290 KB Download
PDF
FINANCE REPORTReport 96 KB DownloadRead as text

More from Denbighshire Cabinet

All decisions
MeetingDecisionOutcome
28 Jul 2026 ApologiesChief Executive Decided Open
28 Jul 2026 Declaration of interestsCouncillor Jason McLellan – Personal and Prejudicial Interest – Agenda Item Nos. 9 & 10 Decided Open
28 Jul 2026 Urgent mattersNo urgent matters had been raised. Decided Open
28 Jul 2026 MINUTESRESOLVED that the minutes of the meeting held on 30 June 2026 be received and confirmed as a correct record. Decided Open
28 Jul 2026 Denbighshire county council digital strategy 2026 - 2031RESOLVED that Cabinet – (a) approve the Denbighshire County Council Digital Strategy 2026 – 2031 (Appendix 1 to the r... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies