Resolved
RESOLVED – that Corporate Governance Committee:- (a) receives and notes the contents of the report, and (b) endorses the draft framework. (IB to Action)
Governance and Audit Committee decided this item on Monday 28 September 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – that Corporate Governance Committee:- (a) receives and notes the contents of the report, and (b) endorses the draft framework. (IB to Action)
Report To: Corporate Governance Committee
Date of Meeting: 28 September 2015
Lead Member / Officer: Barbara Smith – Lead Member for Modernising & Housing Alan Smith – Head of Business Improvement & Modernisation
Report Author: Ivan Butler – Head of Internal Audit
Title: Monitoring of Council Funded Service Providers
1. What is the report about?
This report provides the Corporate Governance Committee with an opportunity to comment on and contribute to the draft framework for setting up and monitoring Council Funded Service Providers (CFSPs).
2. What is the reason for making this report?
The Committee requested a progress update at its meetings of 20 May 2015 and 27 July 2015.
3. What are the Recommendations?
The Committee provides comments and feedback on the draft framework.
4. Report details
4.1The Corporate Governance Committee received a report on 20 May 2015 outlining the project plan for developing a new framework to provide guidance on setting up, monitoring and reporting on services delivered by CFSPs.
4.2The new framework will ensure that the Council has a robust mechanism to monitor governance, financial performance, operational performance and the use of Council funds.
4.3The draft document in Appendix 1, entitled ‘Framework for Delivering Services with Council-funded Service Providers’ has now been produced to include the following:
Why we need a framework Some ‘must dos’ The role of senior management and elected members Council representation on CFSPs Details of requirements for setting up, monitoring and reporting on CFSPs Appendices providing more detailed guidance on business cases, legal agreements and service level agreements.
4.4The draft document was presented to Corporate Executive Team (CET) on 21 September 2015, which means that CET’s comments and suggestions for any changes to the framework had not been received at the time of writing this report. A verbal update will therefore be provided at the Committee meeting.
4.5A final draft version of the document will then be discussed at Senior Leadership Team on 1 October 2015 before being formally adopted and launched later that month.
5. How does the decision contribute to the Corporate Priorities?
There is no decision required on this report; however, the work carried out by CFSPs may contribute directly or indirectly to Corporate Priorities, depending on the service being provided.
6. What will it cost and how will it affect other services?
There are no costs attached to this report.
7. What are the main conclusions of the Equality Impact Assessment (EqIA) undertaken on the decision? The completed EqIA template should be attached as an appendix to the report.
This report does not require a decision or proposal for change, so there is no impact on people who share protected characteristics.
8. What consultations have been carried out with Scrutiny and others?
Corporate Executive Team (CET) was consulted on 21 September 2015, which means that its comments and suggestions for any changes to the framework had not been received at the time of writing this report.
9. Chief Finance Officer Statement
There are no financial implications attached to this report.
10. What risks are there and is there anything we can do to reduce them?
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MONITORING OF COUNCIL FUNDED SERVICE PROVIDERSReport | 91 KB | DownloadRead as text |
PDF |
Mon Cll Fund Serv Prov App 1Appendix | 437 KB | Download |
Follow Governance and Audit Committee at Denbighshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Jul 2026 | MINUTESRESOLVED that subject to the above, the minutes of the meeting held on the 10 June 2026 be received and approved as a... | Approved | Open |
| 22 Jul 2026 | Treasury management 2026/27 updateRESOLVED that; 1. The Governance and Audit committee note the performance of the TM function during 2025/26 and its c... | Noted | Open |
| 22 Jul 2026 | Annual governance and audit committee report 2025/26RESOLVED that, members of the Governance and Audit Committee approve the draft Annual Governance and Audit Committee ... | Approved | Open |
| 22 Jul 2026 | Membership of the governance and audit sub-committee of the north wales corporate joint committeeRESOLVED that Councillor James Elson be nominated as the substitute representative. | Decided | Open |
| 22 Jul 2026 | Governance and audit committee work programmethat subject to the above, the Governance and Audit Committee Forward Work Programme be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.