RESOLVED that – (a) Cabinet confirm the assumptions noted within the Plan, and (b) members request further reports to Cabinet in January 2016 and at regular intervals thereafter on the progress being made on each of the projects identified in Appendix 1 to the report.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Lead Member / Officer: Councillor Julian Thompson-Hill / Richard Weigh, Chief Finance Officer
Report Author: Steve Gadd, Chief Accountant
Title: Corporate Plan - Financial Update
1. What is the report about?
The report provides an updated financial position on the Corporate Plan as requested by Cabinet Members.
2. What is the reason for making this report?
The purpose of the report is to provide an update on the financial elements of the Corporate Plan.
3. What are the Recommendations?
Members confirm the assumptions noted within the Plan.
4. Report details
When the Corporate Plan was launched in 2012, it set out an ambitious programme of capital investment in schools, roads, social care and modernisation that underpinned the priorities the council set for the current administrative term. The ambition within the Plan was set against the financial reality of delivering significant investment in priorities at the same time as reducing expenditure in other areas.
The delivery of the Plan is reliant on the council securing revenue budget to fund borrowing and identifying and maintaining cash reserves. It also relies upon government grant to help deliver the 21 st Century Schools programme and in previous financial years, government grant has also supported the funding of additional investment highways. However, in 2012, although a funding plan was identified, it was not certain that the costs identified and levels of resource to fund them could actually be secured.
Since 2012, as the Plan has developed, the funding underpinning it has moved from an aspirational forecast to a robust, affordable strategy. To make the Plan affordable, some revisions have been necessary alongside changes in planning assumptions. Such changes are inevitable in long-term financial planning. In February 2015, as part of the proposals to set the budget for 2015/16, a decision was taken to prioritise the delivery of the Corporate Plan in future budget rounds. The key changes to the original Plan was the removal of the Office Accommodation project and a reduced estimated cost of the 21st Century Schools programme. In the report that went to Cabinet in June this year it was also agreed to increase Highways expenditure by £3.2m to £18.4m through the additional allocation of £800k per year which was possible due to lower borrowing costs than had been included in the original Corporate Plan.
As was reported in the June Cabinet report the key assumption in the Plan at that point was that funding of the faith school project under the 21 st Century Schools programme was based on the council funding 15% of the total estimated cost of £23m. At that point Welsh Government had not confirmed that the remainder of the funding would be made available. After negotiations with Welsh Government a revised Strategic Outline Programme was submitted in June 2015 which allows the full Modernising Education Programme included in the Corporate Plan to be delivered. This Programme involved the inclusion of the four Corporate Plan Projects (the Rhuthun Town school, Ysgol Carreg Emlyn, Llanfair / Pentrecelyn Areas and Ysgol Pendref in Denbigh) into the wider 21st Century Schools Programme and funding all schemes at 50%. Latest indications are that this is acceptable to Welsh Government although formal written approval is still awaited.
A copy of the latest version of the Plan, based on the assumption that the revised 21st Century Schools Programme is formally approved, is shown as Appendix 1 and summarised below.
as at Nov 2015 Corporate Plan - Summary £m
Schools – 21st Century Programme 86.1 Social Care – Extra Care Housing 21.0 Cefndy Health Care Investment 0.5 Highways 18.4 Total Estimated Capital Cost 126.0 Funded By: Welsh Government Grant 48.0 Council Cash Reserves 24.0 Council Borrowing 40.0 External Contributions (Extra Care) 14.0 Total Funding 126.0 5. How does the decision contribute to the Corporate Priorities?
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.