Denbighshire County Council
Cabinet, Tuesday 16 February 2016 at 10.00am

RHYL WATERFRONT DEVELOPMENT PROJECT UPDATE

Approved Executive 4 papers

Cabinet approved this item on Tuesday 16 February 2016. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

RESOLVED that Cabinet – (a) gives approval to enter into the Overarching Regeneration Agreement on the basis of the funding models set out therein; with each element of the regeneration being phased and subject to further approval (whether by Cabinet or via Delegated Decision dependant on the value) to proceed, and (b) approves the establishment of a project budget funded by reallocating existing corporate resources.
Word for word from the decision Denbighshire published for this meeting. Source: moderngov.denbighshire.gov.uk

Follow this further

Built from Denbighshire's papers

What the report saysPro

Report to Cabinet

Appendix 1 Summary of Heads of Terms relating to the Rhyl Waterfront Overarching Development Agreement

Generally the Heads of Terms provides a comprehensive set of headings for agreement by both parties which will be carried through to the Development Agreement and detailed out to the satisfaction of both parties’ legal, financial and property advisers.

1. The Heads of Terms run from 31 / 1 16 and replaces the exclusivity agreement previously entered into by DCC and Neptune Developments Ltd and grants a further period of exclusivity ie Denbighshire will not negotiate with another party.

The overarching development agreement once agreed will commence from a date to be determined.

2. Parties – Denbighshire County Council and Neptune Developments Ltd

3. The Council and Developer seek to achieve a comprehensive redevelopment of the “Core area” – essentially the Rhyl Waterfront but with the potential by agreement to expand into an extended development area within the Town Centre.

4. The Heads of Terms propose that the Council and developer enter into an “Overarching Development Agreement” with the facility for individual phases to be entered into (denoted at Section 6 below ) provided that all necessary conditions are met and the Financial Appraisal for each phase proves viable.

5. The Development Agreement will set out all the relevant mechanisms for project delivery including;

a. Costs b. Developer / Council Returns c. Land values d. Overage ( if applicable )

6. Phasing – the Heads of Terms and Development Agreement set out the relevant project delivery phases; a. Hospitality b. Cinema / Children’s Village c. Aquatics d. Active leisure

7. Conditionality – there are 3 sets of conditions which need to satisfied by both parties;

a. Primary Conditions: - Agreement of master plan - General Appraisal for master plan - Any Council Authority required - Submission of Planning Application - Agreed target and longstop dates

b. General Phase Conditions: - Detailed phase financial appraisal - Approval of phase proposal - Detailed delivery phase programme - Individual Phase agreement by both parties - Council to satisfy developer that it can input land and resolve any title matters arising

c. Phase Specific Agreements ( where required ) - Aquatic Zone agreement - Management agreement ( if needed) - Lease / Licences / land transfers required

8. Definition of Development Costs – listed out and agreed ( with precise definitions to be included and agreed in the Development Agreement ).

9. VAT Conditions

10. Variations – how they are put forward, resolved and agreed between the parties.

11. Procurement issues – the Developer commits to an OJEU compliant process for the appointment of Design Team and Contractors plus the form of contract ( Industry Standard JCT 2011)

In addition the Contractor will enter into a direct agreement with the Council where required for the purpose of warranties.

12. Commitment to collaborate – binding on both parties

13. Confidentiality – relating to Press and Freedom of Information requests requiring the agreement by both parties

14. Service of Notices – registered addresses and responsible officers of Council and developer.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
RHYL WATERFRONT DEVELOPMENT: APP1Report 194 KB DownloadRead as text
PDF
RHYL WATERFRONT DEVELOPMENT PROJECT UPDATEReport 87 KB Download
PDF
RHYL WATERFRONT PROJECT: APP 2Appendix 49 KB Download
PDF
RHYL WATERFRONT PROJECT: EQIAReport 103 KB Download

More from Denbighshire Cabinet

All decisions
MeetingDecisionOutcome
28 Jul 2026 ApologiesChief Executive Decided Open
28 Jul 2026 Declaration of interestsCouncillor Jason McLellan – Personal and Prejudicial Interest – Agenda Item Nos. 9 & 10 Decided Open
28 Jul 2026 Urgent mattersNo urgent matters had been raised. Decided Open
28 Jul 2026 MINUTESRESOLVED that the minutes of the meeting held on 30 June 2026 be received and confirmed as a correct record. Decided Open
28 Jul 2026 Denbighshire county council digital strategy 2026 - 2031RESOLVED that Cabinet – (a) approve the Denbighshire County Council Digital Strategy 2026 – 2031 (Appendix 1 to the r... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies