Report To: Cabinet
Date of Meeting: 26th July 2016
Lead Member / Officer: Cllr. Hugh Evans, Leader
Report Author: Alan Smith, Head of Business Improvement & Modernisation
Title: TAP funded projects update
1. What is the report about?
The Town Champions Group have met to consider the progress of the outstanding projects derived from the Town and Area Plans. These are their recommendations.
2. What is the reason for making this report?
The Town Champions Group has considered the position of the outstanding projects and would like to recommend that for some the funding is withdrawn and that others are funded in their place.
Because the funding for these projects is required to be spent by the end of the financial year, the Town Champions have requested an urgent decision from Cabinet on the matter, to maximise the time available for successful delivery.
3. What are the Recommendations?
1. That the uncommitted funding is used to support the schemes identified in the report.
4. Report details
In June 2015 the Town Champions Group undertook a rigorous review and prioritisation of TAP funded projects. These are the ‘Horizon’ projects, all of which were expected to have been completed by March 31 st 2017. Since then, the group has been monitoring their progress, including planning to re-allocate any project underspend that might arise.
The Town Champions were concerned that some projects on the list appeared at risk of not being delivered within the agreed timescale. These were:
St Asaph Library £100k Corwen Pavillion £50K Llangollen pre-school project £30K
At the Town Champions meeting of the 25th July, all three of these projects were reviewed and Members concluded that: The funding for the Corwen pavillion project should continue to be made available, as current information indicated that this scheme would be delivered in the timescale.
The original proposal for the Llangollen pre-school project had proved unviable, however a modified proposal had been submitted to improve the existing building instead. Members considered that this provided similarly improved outcomes for pre-school children and could be delivered in the available timescale, but wanted further information before making a decision.
Members considered a significantly expanded proposal for the St Asaph Library project. They have asked for more information on this in order to decide whether to support this revised proposal or to restrict funding to the original scheme. Members also wanted to be confident that either version of this scheme can be delivered in the timeframe available.
At the previous meeting of the 28th June, the group had requested proposals from Members for projects that could utilise the then expected underspend of £49,000. During the review of current projects, a further underspend of £20,000 was identified on the Llantysilio Link Path scheme, and so this too was added to the available pot, making £69,000 funding available for re-allocation.
17 proposals had been submitted to the group, and these were assessed using the same scoring system as had the original bids. Two projects were also re-assessed on the 25th July after additional information had been submitted. On the basis of these assessments, the group recommends to Cabinet that the following proposals should be funded:
Llangollen Sports Club – new grass cutting equipment £ 5,400 Pentredwr – Community Centre refurbishment £ 3,000 Cunning Green environmental improvements £ 1,500 Rhuddlan Library Community Hub accessibility £12,000 Rhyl Coastal Defence enhancement Phase 2 £35,000 Offa’s Dyke Trail Brass Plaques, Prestatyn £ 5,000 Total £61,900
At the September Town Champions meeting, Members will consider further information on the prioritised projects list and recommend how any further underspends could be used to support unfunded projects.
5. How does the decision contribute to the Corporate Priorities?
This decision will support the effective deployment of Council funds to support community initiatives.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
URGENT MATTERSReport | 57 KB | DownloadRead as text |
Follow Cabinet at Denbighshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Jul 2026 | ApologiesChief Executive | Decided | Open |
| 28 Jul 2026 | Declaration of interestsCouncillor Jason McLellan – Personal and Prejudicial Interest – Agenda Item Nos. 9 & 10 | Decided | Open |
| 28 Jul 2026 | Urgent mattersNo urgent matters had been raised. | Decided | Open |
| 28 Jul 2026 | MINUTESRESOLVED that the minutes of the meeting held on 30 June 2026 be received and confirmed as a correct record. | Decided | Open |
| 28 Jul 2026 | Denbighshire county council digital strategy 2026 - 2031RESOLVED that Cabinet – (a) approve the Denbighshire County Council Digital Strategy 2026 – 2031 (Appendix 1 to the r... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.