RESOLVED that Cabinet – (a) approve and recommend to County Council the revisions to the MRP policy for 2017/18 – · Policy for 2017/18 – Option 3 (Asset Life Method – straight line) to be used for calculating MRP on outstanding supported borrowing as at 31 March 2017. The calculation will be the ‘straight line’ method over 50 years. This represents a change from Option 1 (Regulatory Method) as approved by Council on 14 February 2017 · Policy for 2017/18 – Option 3 (Asset Life Method – straight line) to be used for calculating MRP on Supported borrowing incurred on or after 1 April 2017. The calculation will be the ‘straight line’ method over an appropriate number of years, dependent on the period of time that the capital expenditure is likely to generate benefits. This also represents a change from Option 1 · Policy for 2017/18 – Option 3 (Asset Life Method – straight line) to be used for calculating MRP on all capital expenditure funded from unsupported borrowing. This represents a continuation of the approved policy, (b) approve the use of the cash saving in 2017/18 and the recurring budget saving from 2018/19 as set out in the latest version of the Medium Term Financial Plan and summarised below – · 2017/18 Cash Saving – it is recommended that the cash saving of £1.861m is placed in the Budget Mitigation Reserve in order to help mitigate the effects of budget reductions in 2018/19 · Ongoing saving of from 2018/19 – it is recommended to reduce the capital financing budget by £1.861m as part of the strategy to balance the 2018/19 budget.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
1. What is the report about? Following a review of the Council’s current MRP Policy it has been identified that by changing the method for making the MRP a significant saving opportunity would be delivered. The proposed change also introduces a more equitable method for apportioning the costs associated with the capital programme.
2. What is the reason for making this report? The purpose of the report is to seek approval for a revision to the MRP Policy for 2017/18.
3. What are the Recommendations? 3.1 Members are requested to approve and recommend to County Council the revisions to the MRP policy for 2017/18:-
3.1.1 Policy for 2017/18 – Option 3 (Asset Life Method – straight line) to be used for calculating MRP on outstanding supported borrowing as at 31 March 2017.The calculation will be the ‘straight line’ method over 50 years. This represents a change from Option 1 (Regulatory Method) as approved by Council on 14 February 2017.
3.1.2 Policy for 2017/18 – Option 3 (Asset Life Method – straight line) to be used for calculating MRP on Supported borrowing incurred on or after 1 April 2017. The calculation will be the ‘straight line’ method over an appropriate number of years, dependent on the period of time that the capital expenditure is likely to generate benefits. This also represents a change from Option1.
3.1.3 Policy for 2017/18 – Option 3 (Asset Life Method –straight line) to be used for calculating MRP on all capital expenditure funded from unsupported borrowing. This represents a continuation of the approved policy.
3.2Members are requested to approve the use of the cash saving in 2017/18 and the recurring budget saving from 2018/19 as set out in the latest version of the Medium Term Financial Plan and summarised below:-
3.2.1 2017/18 Cash Saving – it is recommended that the cash saving of £1.861m is placed in the Budget Mitigation Reserve in order to help mitigate the effects of budget reductions in 2018/19. 3.2.2 Ongoing saving of from 2018/19 – it is recommended to reduce the capital financing budget by £1.861m as part of the strategy to balance the 2018/19 budget.
4. Report details 4.1 Local Authorities are required to set aside some of their revenue resources as provision for the repayment of debt annually. Regulations require an authority to make an amount of minimum revenue provision (MRP) each year which it considers to be prudent. Proper practice expects that the Council agrees a statement of its policy prior to the start of each financial year.
4.2Members will be acutely aware of the continuing need to make budget reductions to close the annual resource shortfall to ensure that a balanced budget can be set each year.
4.3Budget reductions generally take the form of efficiency savings made by services, cuts to services, or the raising of additional income through fees and charges. Many budget reductions impact on employment either directly through Council jobs (non- replacement of staff or redundancy), or indirectly through externally procured services. It is therefore very important to consider what other forms of budget reductions can be achieved which will protect both our services to the public and employment.
4.4As part of the budget strategy for 2018/2019 officers have been critically reviewing the current MRP Policy. The Medium Term Financial Plan has included an estimate of savings from this review of £2m budget reduction from 2018/19 and £2m cash savings from implementing the policy in 2017/18. This has resulted in a reduction of the savings target for services of £4m for the current annual budget cycle to set the 2018/19 budget. The difference between the estimated saving and the actual saving will be covered by additional efficiencies identified within Corporately held budgets.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.