Resolved
RESOLVED that Cabinet approves two year extensions for each of the services as identified in Appendix 1 to the report.
Cabinet approved this item on Tuesday 21 November 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that Cabinet approves two year extensions for each of the services as identified in Appendix 1 to the report.
Report To: Cabinet
Date of Meeting: 21 November 2017
Lead Member / Officer: Bobby Feeley / Phil Gilroy
Report Author: Katie Newe / Alison Heaton, Community Support Services
Title: DENBIGHSHIRE LEARNING DISABILITY COMMUNITY LIVING SCHEMES – Extensions to existing contracts.
1. What is the report about?
This report provides Cabinet with information regarding the contractual arrangements for supporting individuals with learning disabilities in supported living services, including a request that current contracts can be extended pending the regional exercise to tender across North Wales.
2. What is the reason for making this report?
A decision is required on the extension of 18 Learning Disability Community Living Contracts for a period of two years as required by the Council’s Financial Guidelines (Contract Procedure Rules), pending the approval of future procurement arrangements for these services. Please see appendix 1 for the detail of each contract.
3. What are the Recommendations?
That Cabinet approves 2 year extensions for each of these services,
4. Report details
4.1In line with national guidelines, Community Living is well established as Denbighshire’s preferred way of meeting the needs of people with a Learning Disability who are no longer able to live with their Carers. The procurement of such services must be in accordance with the Council’s Contract Procedure Rules (CPRs) and compliant with the domestic and EU law, namely the Public Contracts Regulations 2015.
4.2Community Support Services (CSS) have been looking at alternative ways to procure Learning Disability Community Living Support. Currently, when contracts are due to expire, the approved procedure would be to extend the contract with the current Provider in line with current CPRs and subject to satisfactory performance. If this is not an option, a full tender exercise would be undertaken in line with the Public Contracts Regulations and CPRs.
4.3Future commissioning plans consist of two ongoing work streams. Locally we are looking at the option of offering Support Budgets to enable Citizens to directly procure support from their preferred Provider and, regionally, CSS are working with the other 5 North Wales Local Authorities and Betsi Cadwaladr University Health Board (BCUHB) and are about to start the process of tendering for a Regional Framework for the provision of Domiciliary Care amongst other Services.
4.4The tendering will consist of three Phases. Phase 1 will be for the provision of standard domiciliary care, Phase 2 will be for the provision of enhanced domiciliary care and Phase 3 will be the provision of services into supported living settings. The contracts referred to in this report fall within Phase 3 and will be subject to an OJEU process.
4.5There is a requirement to extend the existing contracts to allow sufficient time to prepare fully to engage with the market under the procurement process as set out above. The reason for extending the current contracts rather than re-procuring at this time is based upon the cost impact of undertaking 2 different tenders for the same Service provision and the inherent possibility of confusing the market providers. The proposed Framework will create efficiencies in terms of the amount of staff time involved in tendering for services, whilst ensuring quality and value for money when awarding contracts.
4.6The current estimated time frame for Phase 3 is between 18 months to 2 years and on that basis the Contracts would need to be extended for a period of 2 years to 31st March 2020. This will also allow for any unforeseen delays. Should the process be completed earlier, the contracts can be terminated earlier. We are confident that a robust and transparent process is currently being developed in the procurement of this Framework, phase 3 is due to go to the Market in mid 2019, enabling us to use the Framework, once in place, to procure these services for a period of 7 years from the date of the Framework.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CONTRACT EXTENSION: APP 2Appendix | 161 KB | Download |
PDF |
DENBIGHSHIRE LEARNING DISABILITY COMMUNITY LIVING SCHEMES: EXTENSIONS TO EXISTING CONTRACTSReport | 212 KB | DownloadRead as text |
Follow Cabinet at Denbighshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Jul 2026 | ApologiesChief Executive | Decided | Open |
| 28 Jul 2026 | Declaration of interestsCouncillor Jason McLellan – Personal and Prejudicial Interest – Agenda Item Nos. 9 & 10 | Decided | Open |
| 28 Jul 2026 | Urgent mattersNo urgent matters had been raised. | Decided | Open |
| 28 Jul 2026 | MINUTESRESOLVED that the minutes of the meeting held on 30 June 2026 be received and confirmed as a correct record. | Decided | Open |
| 28 Jul 2026 | Denbighshire county council digital strategy 2026 - 2031RESOLVED that Cabinet – (a) approve the Denbighshire County Council Digital Strategy 2026 – 2031 (Appendix 1 to the r... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.