Resolved
RESOLVED that permission be GRANTED in accordance with officer recommendation subject to the conditions imposed.
Planning Committee decided this item on Wednesday 13 December 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that permission be GRANTED in accordance with officer recommendation subject to the conditions imposed.
20 m 100 ft
© Crown copyright and database rights 2017 Ordnance Survey 100023408. 46/2017/0944 Scale: 1:1250 Printed on: 24/11/2017 at 13:49 PM © Denbighshire County Council Denise Shaw WARD : St Asaph West
WARD MEMBER(S): Cllr Peter Scott (c)
APPLICATION NO: 46/2017/0944/ PC
PROPOSAL: Retention of existing sheds used as a workshop (B1 light industrial use) and for personal use (retrospective application)
LOCATION: Queensland House The Roe St Asaph
APPLICANT: [name removed]: C1 Flood Zone
PUBLICITY Site Notice - No UNDERTAKEN: Press Notice - No Neighbour letters - Yes
REASON(S) APPLICATION REPORTED TO COMMITTEE: Scheme of Delegation Part 2
• Recommendation to grant / approve – Town / Community Council objection
CONSULTATION RESPONSES:
ST ASAPH CITY COUNCIL ‘City Council Feedback regarding 46/2017/0944 1. We understand this request was originally opposed by the people that lived around the property. 2. We understand Bill Cowie took it to DCC Planning some years ago and it was delayed for further investigations, what was the outcome of this investigation? 3. We believe it should go back to DCC Planning to be reviewed again as this area should not be used for light industrial use. 4. Local residents have been suggesting there are smells of paint spraying of vehicles coming from within the building. Is there a lack of proper filtration systems? 5. The City Council would like this application to be reviewed again by DCC Planning as we object on the above grounds.’
NATURAL RESOURCES WALES Flood Risk The site lies entirely in Zone C1 as defined by the Development Advice Map (DAM) referred to within TAN15: Development & Flood Risk. NRW Flood Map information also confirms that the site lies within the extreme flood risk outline and Historic Flood Event information indicates that the site has been affected by flooding, most recently in November 2012.
NRW are in the process of completing an improved Flood Risk Management Scheme in St. Asaph, that will on completion, provide improved flood protection to existing properties and residents of St. Asaph. Whilst the improved flood defences will deliver significant flood risk improvements, it will not completely eliminate flood risks.
The retrospective planning application seeks approval to allow for a new “less vulnerable” development (see Figure 2 of TAN15) to be established within the rear garden of the property. NRW are of the view that the provision of additional commercial/light industrial units would constitute an increase in development density since it would be in addition to the existing residential unit, which would remain. Given the potential flood risks at this site, and recognising that development has already been completed, it is probable that the new premises would not be able to comply with the requirements of Table A1.14 of TAN15. In particular, NRW would be concerned that the premises could, without the need for further planning permission, be sold to a separate owner, thereby increasing the number of people affected in the event of a flood. Additionally, it could set a precedent whereby additional commercial premises could be created within flood-zones, without considering compliance with TAN15.
Notwithstanding the above, NRW recognise that the development is relatively limited in scale and seeks approval to establish 60m2 of new “less vulnerable” development. In addition, the development will result in the demolition of an existing workshop building, which from a flood risk perspective will partly offset the risks associated with the two replacement workshop units. In these circumstances, and in the absence of a Flood Consequences Assessment (FCA), your Authority may consider the flood risks to be acceptable on the basis of the Applicant being informed of the potential flood risks.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
APPLICATION NO. 46/2017/0944- Queensland House, The Roe, St AsaphFrontsheet | 6 KB | Download |
PDF |
Final Report 46-2017-0944Report | 758 KB | DownloadRead as text |
Follow Planning Committee at Denbighshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | MINUTESthat the minutes from the meeting held on the 15 July 2026 be received and approved as a true and correct record of t... | Approved | Open |
| 15 Jul 2026 | MINUTESthat the minutes from the meeting held on the 17 June 2026 be received and approved as a true and correct record of t... | Approved | Open |
| 17 Jun 2026 | MINUTESthat the minutes of the Planning Committee meeting held on the 13 May 2026 be received and approved as a true and cor... | Approved | Open |
| 13 May 2026 | Appointment of chairRESOLVED that Councillor Mark Young be appointed Chair of the Planning Committee for the 2026/27 municipal year. | Decided | Open |
| 13 May 2026 | Appointment of vice-chairRESOLVED that Councillor Alan James be appointed Vice-Chair of the Planning Committee for the 2026/27 municipal year. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.