RESOLVED that Cabinet – (a) confirms its financial commitment to delivering Band B proposals in accordance with the Strategic Outline Programme as submitted to the Welsh Government to enable it to meet the priority included within the Corporate Plan 2017 – 2022, and (b) confirms that it has read, understood and taken account of the Well-being Impact Assessment attached at Appendix 1 to the report as part of its consideration.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Lead Member / Officer: Councillor Huw Hilditch Roberts, Lead Member for Children, Education and Young People
Report Author: Karen Evans, Head of Education and Children’s Services
Title: Delivery of Band B – 21st Century Schools Programme
1. What is the report about?
To advise Cabinet of the approval of its Band B Programme submission for the 21st Century Schools and Education Programme and the implications for delivery for Denbighshire County Council.
2. What is the reason for making this report?
To advise Cabinet of progress in respect of Band B of the 21st Century Schools and Education Programme and to make recommendations in respect to planning for the delivery of the Programme for Denbighshire County Council.
3. What are the Recommendations?
3.1That Cabinet confirms its financial commitment to delivering Band B proposals in accordance with the Strategic Outline Programme as submitted to the Welsh Government to enable it to meet the priority included within the Corporate Plan 2017- 2022.
3.2That Cabinet confirms that it has read, understood and taken account of the Well- being Impact Assessment (Appendix 1) as part of its consideration.
4. Report details
4.1The Council over the last 4 years has made excellent progress in delivering the Band A proposals within the 21st Century Schools Programme, in partnership with the Welsh Government. By 2019 the Council will have invested over £90m in partnership with the Welsh Government to deliver 8 key projects. The Welsh Government invited local authorities to submit proposals for the next round of funding, Band B in May 2017 and the Cabinet approved a submission to the overall value of £80m in July 2017. This submission included reference to the ongoing work regarding the priorities for the Corporate Plan which was subsequently approved by Council in October 2017.
4.2In November 2017 the Education Secretary for Wales announced that across Wales a further £2.3bn was to be earmarked for investment in education infrastructure across Wales via Band B of the 21st Century Schools Programme. The Council received confirmation in December 2017 from the Welsh Government of the approval in principal of this second wave of investment, subject to the approval of individual project business cases. The approval letter also outlined the next steps for the delivery of Band B in partnership with individual local authorities and the need to develop the appropriate planning of financial resources.
4.3In view of this announcement Cabinet is requested to clarify its financial commitment to the delivery of the Band B proposals. The overall Programme approved is of a value of £80.5 million, of which Denbighshire will be required to make a contribution of £32.8m to its community schools. The planning for the Corporate Plan has made an outline assumption of an annual revenue commitment to meet the aspirations of the plan but is clear that this is subject to the overall financial position of the Council.
4.4The initial planning for the delivery of Band B suggests that should the Denbighshire contribution be delivered solely through prudential borrowing a commitment of £1.836m would be required to meet the planned spend across the proposed seven years of the Band B programme.
4.5The delivery of the Band B proposals will be overseen by the new Corporate Programme Board for Housing and Young People with individual Project Proposals to be considered in due course by the Strategic Investment Group and Cabinet.
5. How does the decision contribute to the Corporate Priorities?
The support of this recommendation would enable the Council to move forward towards planning for the delivery of Band B and seek to secure a potential £80m investment in the school estate to ensure that the priority of continuing to modernise schools via the 21st Century Schools programme is implemented.
6. What will it cost and how will it affect other services?
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.