Resolved
RESOLVED that permission be GRANTED in accordance with officer recommendation as detailed within the report.
Planning Committee decided this item on Wednesday 12 September 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that permission be GRANTED in accordance with officer recommendation as detailed within the report.
50 m 100 ft
© Crown copyright and database rights 2017 Ordnance Survey 100023408. 43/2018/0522 Scale: 1:2500 Printed on: 21/8/2018 at 10:11 AM © Denbighshire County Council Emer O'Connor WARD : Prestatyn South West
WARD MEMBER(S): Cllr Gareth Davies Cllr Bob Murray (c)
APPLICATION NO: 43/2018/0522/ PS
PROPOSAL: Removal of condition no. 3 of planning permission code no. 43/2018/0030 ('The site shall only be used for caravans on tour and no caravan shall stay on the site for any period longer than 21 days')
LOCATION: Four Winds Farm Caravan Site Ffordd Ffynnon Prestatyn LL19 8BE
APPLICANT: [name removed]: None
PUBLICITY Site Notice - No UNDERTAKEN: Press Notice - No Neighbour letters - Yes
REASON(S) APPLICATION REPORTED TO COMMITTEE: Scheme of Delegation Part 2 • Recommendation to grant – Community Council objection.
CONSULTATION RESPONSES: PRESTATYN TOWN COUNCIL– “Objection. Removal of this condition will set a precedent resulting in other caravan parks with this condition imposed to apply for removal”
DENBIGHSHIRE COUNTY COUNCIL CONSULTEES – Public Protection Environmental Health Officer – Awaiting response.
RESPONSE TO PUBLICITY: None received.
EXPIRY DATE OF APPLICATION: 25/07/2018
EXTENSION OF TIME AGREED? 14/09/2018
REASONS FOR DELAY IN DECISION (where applicable): • Delayed owing to consideration at Committee.
PLANNING ASSESSMENT: 1. THE PROPOSAL: 1.1 Summary of proposals 1.1.1 The application seeks to remove a condition which was attached to planning consent reference 43/2018/0030, granted on 18th April 2018 for “Alterations to existing touring caravan park area for the siting of 12 touring caravan pitches in lieu of existing provision for 5 pitches”. The site is at Four Winds Farm in Prestatyn.
1.1.2 Condition 3 of the permission relates to the touring caravan element of the development and reads as follows: “The site shall only be used for caravans on tour and no caravan shall stay on the site for any period longer than 21 days.
The reason for the Condition was – “To ensure that no unauthorised permanent residential occupation of holiday units takes place on site.”
1.1.3 The application is accompanied by a Statement which puts forward the case for the removal of the condition. It is contended that as the site is a seasonal caravan site with a condition restricting use during the winter period, 31st March until 1st April, that the holiday units could not become permanent residential units. It is argued that the removal of the condition would result in less traffic on the adjacent road, as caravans would be towed onto the site and left for longer periods than the specified 21 days.
1.2Description of site and surroundings
1.2.1 Four Winds Farm is located off Ffordd Ffynnon to the west of Prestatyn. The site is accessed off a lane which also serves Pydew Farm and the Abandoned Animals Association Rescue Centre.
1.2.2 The building complex at Four Winds comprises of a bungalow which has recently been granted permission to be extended, and a small range of single storey outbuildings.
1.2.3 The character of the area is open flat agricultural land along the coastal plain between Prestatyn and Rhyl to the west.
1.3Relevant planning constraints/considerations
1.3.1 The site is outside of any development boundary in an area without any specific designation in the Local Development Plan.
1.4Relevant planning history
1.4.1 The site has been in use in the past for the stationing of caravans under Caravan Club exemptions.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
APPLICATION NO. 43/2018/0522: FOUR WINDS FARM CARAVAN SITE, FFORDD FFYNNON, PRESTATYNFrontsheet | 6 KB | Download |
PDF |
Final report 43_2018_0522Report | 424 KB | DownloadRead as text |
Follow Planning Committee at Denbighshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | MINUTESthat the minutes from the meeting held on the 15 July 2026 be received and approved as a true and correct record of t... | Approved | Open |
| 15 Jul 2026 | MINUTESthat the minutes from the meeting held on the 17 June 2026 be received and approved as a true and correct record of t... | Approved | Open |
| 17 Jun 2026 | MINUTESthat the minutes of the Planning Committee meeting held on the 13 May 2026 be received and approved as a true and cor... | Approved | Open |
| 13 May 2026 | Appointment of chairRESOLVED that Councillor Mark Young be appointed Chair of the Planning Committee for the 2026/27 municipal year. | Decided | Open |
| 13 May 2026 | Appointment of vice-chairRESOLVED that Councillor Alan James be appointed Vice-Chair of the Planning Committee for the 2026/27 municipal year. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.