UPDATE REPORT - PROJECT MANAGEMENT OF 21ST CENTURY SCHOOLS

Noted Finance 1 paper

Governance and Audit Committee noted this item on Wednesday 21 November 2018. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

RESOLVED that the update report be received by the Corporate Governance Committee and its contents noted.
Word for word from the decision Denbighshire published for this meeting. Source: moderngov.denbighshire.gov.uk

Follow this further

Built from Denbighshire's papers

What the report saysPro

Report to Governance and Audit Committee

Report To: Corporate Governance Committee

Date of Meeting: 21 November 2018

Lead Member / Officer: Lisa Lovegrove - Chief Internal Auditor

Report Author: Lisa Lovegrove - Chief Internal Auditor

Title: Update Report – Project Management of 21st Century Schools

1. What is the report about? This report provides an update on progress in implementing the major risk action relating to Project Management of 21st Century Schools that featured within the Internal Audit Update report which was presented to this Committee in June 2018.

2. What is the reason for making this report? This report is to provide information on how the Council is implementing improvements in the programme management of 21st Century Schools since the issue of the Internal Audit report. The audit report raised a major risk issue in relation to the governance of the 21st Century Schools Programme, so the Corporate Governance Committee requested a progress update report to ensure that the issue is being addressed. This is the first progress report.

3. What are the Recommendations? The Committee to review progress with addressing the audit action.

4. Report details A report accompanying the ‘Highlight Report: 21st Century Schools Programme’ to the Young People and Housing Board on 11 October 2018 detailed the re-establishment of the Modernisation Programme Board. Following agreement with the Senior Responsible Officer, the Modernisation Programme Board was re-established and it met on 24th September 2018. At this meeting, the parameters for reporting and various roles and responsibilities were agreed. It was also agreed that: for the delivery of Band B proposals, a review of the requirement for separate project boards is required, which will be based on each individual project’s requirements. This is to oversee their establishment and progression through the design stages to delivery.

Based on strengthened governance and controls put in place, we no longer consider this to be a major risk issue.

The audit report also raised a moderate risk issue relating to absence of project management guidance. Guidance has been drafted which sets out when a project board is required and to clarify when it is permissible to “manage by exception” i.e. project manager can deliver the project within agreed tolerances which, if exceeded, must be escalated to the overarching programme board. The guidance will be presented to the Senior Leadership Team on 6 December 2018 and then circulated to officers undertaking a project management role. Both agreed actions raised within the report have therefore been suitably addressed.

5. How does the decision contribute to the Corporate Priorities? Not applicable - there is no decision required with this report.

6. What will it cost and how will it affect other services? Not applicable - there is no decision required with this report.

7. What are the main conclusions of the Well-being Impact Assessment? Not applicable - there is no decision required with this report.

8. What consultations have been carried out with Scrutiny and others? Not applicable - there is no decision required with this report.

9. Chief Finance Officer Statement Not applicable - there is no decision required with this report.

10. What risks are there and is there anything we can do to reduce them? Not applicable - there is no decision required with this report.

11. Power to make the Decision Not applicable - there is no decision required with this report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
UPDATE REPORT: PROJECT MANAGEMENT OF 21ST CENTURY SCHOOLSReport 200 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Denbighshire

Search all
  1. UPDATE REPORT - PROJECT MANAGEMENT OF 21ST CENTURY SCHOOLSThis decision
  2. Internal audit follow up - project management of queen's buildingNoted
  3. Internal audit follow up - project management of queen's buildingNoted

More from Denbighshire Governance and Audit Committee

All decisions
MeetingDecisionOutcome
22 Jul 2026 MINUTESRESOLVED that subject to the above, the minutes of the meeting held on the 10 June 2026 be received and approved as a... Approved Open
22 Jul 2026 Treasury management 2026/27 updateRESOLVED that; 1. The Governance and Audit committee note the performance of the TM function during 2025/26 and its c... Noted Open
22 Jul 2026 Annual governance and audit committee report 2025/26RESOLVED that, members of the Governance and Audit Committee approve the draft Annual Governance and Audit Committee ... Approved Open
22 Jul 2026 Membership of the governance and audit sub-committee of the north wales corporate joint committeeRESOLVED that Councillor James Elson be nominated as the substitute representative. Decided Open
22 Jul 2026 Governance and audit committee work programmethat subject to the above, the Governance and Audit Committee Forward Work Programme be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies