RESOLVED that Cabinet – (a) notes the impact of the Draft Local Government Settlement 2020/21; (b) supports the proposals outlined in Appendix 1 to the report, and detailed in Section 4 of the report, and recommends them to the full Council in order to finalise the budget for 2020/21; (c) recommends to Council the average Council Tax rise of 4.3% proposed; (d) recommends to Council that authority is delegated to the Head of Finance and Property in consultation with the Lead Member for Finance to adjust the use of cash included in the budget proposals by up to £500k if there is movement between the draft and final settlement figures in order to allow the setting of Council Tax in a timely manner, and (e) confirms that it has read, understood and taken account of the Well-being Impact Assessments submitted as part of the report.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Report author Steve Gadd, Head of Finance and Property
Title Budget 2020/21 - Final Proposals
1. What is the report about?
The report sets out the implications of the Local Government Settlement 2020/21 and proposals to finalise the budget for 2020/21.
2. What is the reason for making this report?
2.1The Council is legally required to set a balanced and deliverable budget before the start of each financial year and to set the resulting level of Council Tax to allow bills to be sent to residents.
2.2To provide an overview of the budget process and the impact of the Local Government Settlement and to approve the budget for 2020/21, including the level of Council Tax.
3. What are the Recommendations?
3.1To note the impact of the Draft Local Government Settlement 2020/21.
3.2That Cabinet supports the proposals outlined in Appendix 1, and detailed in Section 4, and recommends them to the full Council in order to finalise the budget for 2020/21.
3.3To recommend to Council the average Council Tax rise of 4.3% proposed.
3.4To recommend to Council that authority is delegated to the Head of Finance and Property in consultation with the Lead Member for Finance to adjust the use of cash included in the budget proposals by up to £500k if there is movement between the draft and final settlement figures in order to allow the setting of Council Tax in a timely manner.
3.5That Cabinet confirms that it has read, understood and taken account of the Well-being Impact Assessment.
4. Report details
4.1The Draft Local Government Settlement for 2020/21 was received by the council on 16th December and resulted in a positive settlement of +4.3%, which was also the Welsh average position. The Final Settlement is expected on the 25th February but Welsh Government (WG) have indicated that there should be very few changes.
4.2As part of the settlement there were ‘transfers in’ of £1.794m mainly relating to grant transfers for part year for Teachers Pay and Teachers Pension Grant. The full year effect of these grants need to be funded from the general settlement.
4.3The final proposals to balance the 2020/21 budget are shown in the Medium Term Financial Plan (MTFP) in Appendix 1. The main areas of growth and pressures are:
Pay pressures of £1.124m Price and energy inflation of £250k Fire Service Levy of £93k Allowance for increase in Council Tax Reduction Scheme of £350k Schools inflationary pressures are recognised amounting to £2.852m Schools demographic pressure of £716k £2.6m to recognise demand pressures and forecasts in Community Support Services as part of the council’s long term strategy to manage care budgets £1.546m to recognise existing pressures in Education and Children’s Services relating to Out of County Placements and Recoupment. £1.4m pressures in Waste Services have been recognised based on in year pressures A further £600k pressure recognised relating to School Transport £529k pressure has been included to fund Corporate Plan Priorities In light of the scale of the pressures a contingency of £358k has been included
4.4The pressures identified above amount to £12.418m.The impact of using £2m of cash in 19/20 (which has the effect of just delaying the need to identify savings) means that the total shortfall amounted to £14.418m. A draft settlement of +10% would have been required in order to fund all these pressures. The +4.3% settlement generates £6.219m additional revenue leaving a funding gap of £8.199m. The following items are included in the proposals in order to bridge that gap:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.