Resolved : (i) subject to the above observations to acknowledge the progress made to date in implementing the Committee’s recommendations following its inquiry into the fire on Llantysilio Mountain and its impact; (ii) confirmed that as part of their consideration they had read, understood and taken into account the Well-being Impact Assessment (WIA) on the Moorland Management and Wildfire Prevention Project (Appendix 2 to the report); and (iii) that representations ... view the full minutes text for item 7.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Lead Member / Officer Cllr. Tony Thomas (Lead Member for Housing & Communities)/Emlyn Jones (Head of Planning, Public Protection & Countryside Services)
Title Progress Report on Recommendations stemming from the Llantysilio Mountain Fire Review
1. What is the report about? 1.1 To monitor progress made in relation to implementing the Llantysilio Mountain Fire Review recommendations in conjunction with the Council’s partner agencies and organisations.
2. What is the reason for making this report?
2.1To provide update information on the recommendations made by this Committee in relation to the review into the Llantysilio Mountain Fire of Summer 2018. This is an update report and no decision is required.
3. What are the Recommendations?
3.1The Committee is requested to consider the information provided and comment accordingly. 3.2 That the Committee confirms that it has read, understood and taken account of the Well-being Impact Assessment (Appendix 2) as part of its consideration 4. Report details
4.1Following the Communities Scrutiny Review into the Llantysilio fire, a number of recommendations were suggested. These are outlined in Appendix 1, Llantysilio Mountain Fire –Monitoring Action Plan and a brief progress statement is provided where possible. A number of the recommendations were attributed to external partners individually or jointly and the Authority has limited influence in their progress. The Authority has requested an update from Partners in these cases. These responses are documented in Appendix 1 when provided.
Please find below a link to the Committee’s report, published in September 2019: https://www.denbighshire.gov.uk/en/your-council/about-the-council/Communities- Scrutiny-Committee-Llantysilio-Mountain-Fire-Report.pdf
4.2Denbighshire County Council (DCC), North Wales Fire and Rescue Service NWFRS) and Natural Resources Wales (NRW) met in November 2019 to review some of the recommendations and discuss joint funding for a Moorland Officer Post, wildfire prevention procedures and better moorland management. NWFRS were unable to contribute to the post but stated they would be partners in any initiatives to improve prevention and fire management. NRW responded positively to funding a joint post at that time and it can now be confirmed they will be contributing £20,000/yr. for the next 3 years to the post. Any further funding commitment was not possible at this time. At the time of writing, the Countryside Service had submitted a bid to the Corporate Plan Board for the remaining £84K over 3 years to fund the post. The Board will consider the case in April 2020.
4.3Following a report commissioned by NRW - Llantysilio Mountain Fire Preliminary Assessment and SSSI Management Recommendations (already circulated to the Committee and Appendix 3), NRW and the Countryside Service have met on site to discuss options for restoration of the moorland. These options vary depending on location and costs also vary. Outcomes for implementation of the report will be considered when the Moorland Officer is in post. 4.4 NRW with the Countryside Service have begun prioritising areas for response with particular attention being given to areas that are vulnerable to further damage from water run-off.
4.5The Countryside Service and AONB have been successful in securing some funding from Welsh Government to begin some restoration works this winter. Some restoration work has taken place on a trial plot on Moel y Faen – on the eastern edge of the Mountain.
4.6As requested by Members, correspondence was sent to Welsh Government in October 2019 and a reply was received from the Minister in the same month (Appendices 4a, 4b and4c). To date the responses to the Sustainable Farming and Land Use Consultation have not been published.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.