Resolved
Vote taken: 7 in favour, 0 against, 0 abstentions RESOLVED that Cabinet notes the budgets set for 2020/21 and progress against the agreed budget strategy.
Cabinet agreed this item on Tuesday 28 July 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
Vote taken: 7 in favour, 0 against, 0 abstentions RESOLVED that Cabinet notes the budgets set for 2020/21 and progress against the agreed budget strategy.
Report to Cabinet
Date of meeting 28th July 2020
Lead Member / Officer Julian Thompson Hill
Report author Steve Gadd, Head of Finance and Property
Title Finance Report (June 2020/21)
1. What is the report about?
The report gives details of the council’s revenue budget and savings as agreed for 2020/21. The report also provides a summary update of the Capital Plan as well as the Housing Revenue Account and Housing Capital Plan.
2. What is the reason for making this report?
The purpose of the report is to provide an update on the council’s current financial position and confirm the agreed service budgets for 2020/21.
3. What are the Recommendations?
3.1Members note the budgets set for 2020/21 and progress against the agreed strategy.
4. Report details
The report provides a summary of the council’s revenue budget for 2020/21 detailed in Appendix 1. The council’s net revenue budget is £208.302m (£198.538m in 19/20). The position on service and corporate budgets is a forecast overspend of £7.585m (£7.393m last month). This overspend does not assume any ‘income loss’ grant that may be received from Welsh Government as it is currently unknown how much grant is available, how the grant will be allocated and what categories of loss will be eligible. It is currently estimated that between £2-4m may be received by Denbighshire for Quarter 1 losses. Narrative around the current risks and assumptions underlying this assessment are outlined in Section 6 and Appendix 2.
The 2020/21 budget required service savings and efficiencies of £4.448m to be identified and agreed as detailed below: Corporate savings identified relating to the triennial actuarial review of the Clwyd Pension Fund (£2m) Schools savings of 1% (£0.692m) Service efficiencies and savings (£1.756m) – see Appendix 3 for details The corporate savings have already been achieved and the schools’ savings are delegated to the governing bodies to monitor and deliver. On top of this £1.086m of the service savings had originally been designated as savings that have already been implemented. However under the current rapidly changing situation it is really important that we review and monitor achievement of these. A full analysis will be undertaken and reported to Cabinet in September.
5. How does the decision contribute to the Corporate Priorities?
Effective management of the council’s revenue and capital budgets and delivery of the agreed budget strategy underpins activity in all areas, including corporate priorities.
6. What will it cost and how will it affect other services?
Significant service narratives explaining variances and risks are detailed in Appendix 2, however the following should also be noted:
Impact of Corona Virus - A full report has been presented to Cabinet last month which detailed the possible financial impact and the financial strategy setting out how the Council will cope with these pressures. The current short term strategy of working with Welsh Government has helped secure the following funding:
Major Grants for Wales as a whole have been announced – all claimed through the same process: £30m initial Hardship Fund – working well (for Q1) £40m Social Care Grant (April, May and now June) £33m additional Free School Meal Grant (to end of August) The table below summarises the position of the claims for DCC. The ‘Holding’ column indicates items that WG are requesting further information on:
COVID19 REVENUE CLAIMS TO WG
Previous Original total Net Claim Disallowed month Holding claim paid to date Month adjustment
March 2020 £61,701 £0 £0 £0 £61,701 April 2020 £666,927 0 -£8,865 £0 £658,062 May 2020 £1,200,170 -£6,025 -£54,538 -£203,732 £935,875
Submitted to date £1,928,798 -£6,025 -£63,403 -£203,732 £1,655,638
June 2020 £1,027,489
Grand Total £2,956,287
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
FINANCE REPORT: App 1 Revenue SummaryAppendix | 233 KB | Download |
PDF |
FINANCE REPORT: App 2 Service Variance NarrativesAppendix | 444 KB | Download |
PDF |
FINANCE REPORT: App 3 Service EfficienciesAppendix | 456 KB | Download |
PDF |
FINANCE REPORT: App 4 Capital Plan SummaryAppendix | 197 KB | Download |
PDF |
FINANCE REPORT: App 5 Major Projects Narrative UpdateAppendix | 413 KB | Download |
PDF |
FINANCE REPORTReport | 453 KB | DownloadRead as text |
Follow Cabinet at Denbighshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Jul 2026 | ApologiesChief Executive | Decided | Open |
| 28 Jul 2026 | Declaration of interestsCouncillor Jason McLellan – Personal and Prejudicial Interest – Agenda Item Nos. 9 & 10 | Decided | Open |
| 28 Jul 2026 | Urgent mattersNo urgent matters had been raised. | Decided | Open |
| 28 Jul 2026 | MINUTESRESOLVED that the minutes of the meeting held on 30 June 2026 be received and confirmed as a correct record. | Decided | Open |
| 28 Jul 2026 | Denbighshire county council digital strategy 2026 - 2031RESOLVED that Cabinet – (a) approve the Denbighshire County Council Digital Strategy 2026 – 2031 (Appendix 1 to the r... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.