CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Denbighshire County Council
Cabinet, Tuesday 22 September 2020 at 10.00am

FORMER SAVOY HOTEL AND THE QUEEN'S MARKET, THEATRE AND HOTEL, RHYL

Approved Executive 4 papers

Cabinet approved this item on Tuesday 22 September 2020. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

Vote taken: 8 in favour, 0 against, 0 abstentions RESOLVED that Cabinet approves to allocate £1.5m of funding to the project to enable the demolition and complete the planning process .
Word for word from the decision Denbighshire published for this meeting. Source: moderngov.denbighshire.gov.uk

Follow this further

Built from Denbighshire's papers

What the report saysPro

Report to Cabinet

Report to Cabinet

Date of meeting Tuesday 22nd September 2020

Lead Member / Officer Cllr Hugh Evans OBE Leader of the Council Lead Member for the Economy and Corporate Governance

Report author Graham Boase Corporate Director: Economy & Public Realm

Title Former Savoy Hotel and the Queen’s Market, Theatre and Hotel, Rhyl

1. What is the report about? This report has been prepared to update Cabinet on the future development of the former Savoy Hotel and the Queen’s Market, Theatre and Hotel, Rhyl, along with the associated risks and the additional funding required.

2. What is the reason for making this report? To provide Cabinet with information about the future development of the former Savoy Hotel and the Queen’s Market, Theatre and Hotel, Rhyl, along with the associated risks and a request for additional funding.

3. What are the Recommendations? That Cabinet approves to allocate £1.5m of funding to the project to enable the demolition and complete the planning process.

4. Report details In March 2019, Denbighshire County Council (DCC) acquired a number of adjacent buildings in Rhyl town centre fronting onto the seafront promenade, known collectively as Queen’s Buildings. The buildings were in a dilapidated state, with no active uses on upper floors (the seafront buildings are four stories) and significant void levels on the ground floor. We have developed ambitious plans for the mixed use redevelopment of the site, plans of which are attached in appendix 1. The redevelopment of this site will not only remove a significant eyesore, but is critical to the regeneration and future economic success of Rhyl town centre.

The redevelopment is planned to progress in the following stages:

 Phase 1 – development of an indoor market hall and flexible event space, with associated external landscaping (further details of phase 1 attached in appendix 2)  Phase 2a – the development of a 5 storey office building on Queen Street  Phase 2b – the development of a 5 storey commercial/residential building on West parade  Phase 3 – the development of a further 5 storey commercial/residential building on West Parade (subject to additional property acquisition)

At this stage we are only looking to deliver phase 1, with additional phases subject to review in light of the COVID impact on public finances and associated grant funding and the impact of the pandemic on the economy and property market. Delivery timescales for phase 1 are attached as appendix 3.

The cost of delivering phase 1 is estimated at £11,734,571. The costs have been subject to extensive examination and we are confident that the project can be delivered within this funding envelope. However, these estimates are considerably more than the original estimate and as a result the project has a current shortfall of £4.3 million. The table below details the funding secured to date:

Funding Source Amount

WEFO – Building for the Future £2,500,000

Welsh Government – Targeted Match Funding £2,500,000

DCC Capital £1,900,000

DCC Asbestos Budget £252,000 DCC (WG Economic Stimulus Grant) £311,000

TOTAL £7,463,000

Costs have risen from the original estimate for a number of reasons including:

 The estimated budget for demolition and facade retention being over optimistic. This has resulted in the cost of demolition now exceeding £1m;  The amount and type of asbestos in the building is far worse than we had originally anticipated. The costs for asbestos removal is now costing almost £500k;  The cost on securing vacant possession and clearing the buildings to prepare for demolition has increased and stands at over £500k;  Additional costs to clear the building of all the contents and detritus left by the previous owner of approximately £75k; and  The cost of carrying out the required surveys to support the planning application has increased by approx. £30k.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
FORMER SAVOY HOTEL AND THE QUEEN'S MARKET, THEATRE AND HOTEL, RHYLReport 398 KB DownloadRead as text
PDF
QUEENS RHYL: APP 1 SITE MASTERPLANAppendix 614 KB Download
PDF
QUEENS RHYL: APP 2 PHASE 1 PROPOSALSAppendix 8.1 MB Download
PDF
QUEENS RHYL: APP 3 DELIVERY TIMESCALESAppendix 41 KB Download

At this meeting

Whole meeting

More from Denbighshire Cabinet

All decisions
MeetingDecisionOutcome
28 Jul 2026 ApologiesChief Executive Decided Open
28 Jul 2026 Declaration of interestsCouncillor Jason McLellan – Personal and Prejudicial Interest – Agenda Item Nos. 9 & 10 Decided Open
28 Jul 2026 Urgent mattersNo urgent matters had been raised. Decided Open
28 Jul 2026 MINUTESRESOLVED that the minutes of the meeting held on 30 June 2026 be received and confirmed as a correct record. Decided Open
28 Jul 2026 Denbighshire county council digital strategy 2026 - 2031RESOLVED that Cabinet – (a) approve the Denbighshire County Council Digital Strategy 2026 – 2031 (Appendix 1 to the r... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies