Resolved
Vote taken: 8 in favour, 0 against, 0 abstentions RESOLVED that Cabinet approves to allocate £1.5m of funding to the project to enable the demolition and complete the planning process .
Cabinet approved this item on Tuesday 22 September 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
Vote taken: 8 in favour, 0 against, 0 abstentions RESOLVED that Cabinet approves to allocate £1.5m of funding to the project to enable the demolition and complete the planning process .
Report to Cabinet
Date of meeting Tuesday 22nd September 2020
Lead Member / Officer Cllr Hugh Evans OBE Leader of the Council Lead Member for the Economy and Corporate Governance
Report author Graham Boase Corporate Director: Economy & Public Realm
Title Former Savoy Hotel and the Queen’s Market, Theatre and Hotel, Rhyl
1. What is the report about? This report has been prepared to update Cabinet on the future development of the former Savoy Hotel and the Queen’s Market, Theatre and Hotel, Rhyl, along with the associated risks and the additional funding required.
2. What is the reason for making this report? To provide Cabinet with information about the future development of the former Savoy Hotel and the Queen’s Market, Theatre and Hotel, Rhyl, along with the associated risks and a request for additional funding.
3. What are the Recommendations? That Cabinet approves to allocate £1.5m of funding to the project to enable the demolition and complete the planning process.
4. Report details In March 2019, Denbighshire County Council (DCC) acquired a number of adjacent buildings in Rhyl town centre fronting onto the seafront promenade, known collectively as Queen’s Buildings. The buildings were in a dilapidated state, with no active uses on upper floors (the seafront buildings are four stories) and significant void levels on the ground floor. We have developed ambitious plans for the mixed use redevelopment of the site, plans of which are attached in appendix 1. The redevelopment of this site will not only remove a significant eyesore, but is critical to the regeneration and future economic success of Rhyl town centre.
The redevelopment is planned to progress in the following stages:
Phase 1 – development of an indoor market hall and flexible event space, with associated external landscaping (further details of phase 1 attached in appendix 2) Phase 2a – the development of a 5 storey office building on Queen Street Phase 2b – the development of a 5 storey commercial/residential building on West parade Phase 3 – the development of a further 5 storey commercial/residential building on West Parade (subject to additional property acquisition)
At this stage we are only looking to deliver phase 1, with additional phases subject to review in light of the COVID impact on public finances and associated grant funding and the impact of the pandemic on the economy and property market. Delivery timescales for phase 1 are attached as appendix 3.
The cost of delivering phase 1 is estimated at £11,734,571. The costs have been subject to extensive examination and we are confident that the project can be delivered within this funding envelope. However, these estimates are considerably more than the original estimate and as a result the project has a current shortfall of £4.3 million. The table below details the funding secured to date:
Funding Source Amount
WEFO – Building for the Future £2,500,000
Welsh Government – Targeted Match Funding £2,500,000
DCC Capital £1,900,000
DCC Asbestos Budget £252,000 DCC (WG Economic Stimulus Grant) £311,000
TOTAL £7,463,000
Costs have risen from the original estimate for a number of reasons including:
The estimated budget for demolition and facade retention being over optimistic. This has resulted in the cost of demolition now exceeding £1m; The amount and type of asbestos in the building is far worse than we had originally anticipated. The costs for asbestos removal is now costing almost £500k; The cost on securing vacant possession and clearing the buildings to prepare for demolition has increased and stands at over £500k; Additional costs to clear the building of all the contents and detritus left by the previous owner of approximately £75k; and The cost of carrying out the required surveys to support the planning application has increased by approx. £30k.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
FORMER SAVOY HOTEL AND THE QUEEN'S MARKET, THEATRE AND HOTEL, RHYLReport | 398 KB | DownloadRead as text |
PDF |
QUEENS RHYL: APP 1 SITE MASTERPLANAppendix | 614 KB | Download |
PDF |
QUEENS RHYL: APP 2 PHASE 1 PROPOSALSAppendix | 8.1 MB | Download |
PDF |
QUEENS RHYL: APP 3 DELIVERY TIMESCALESAppendix | 41 KB | Download |
Follow Cabinet at Denbighshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Jul 2026 | ApologiesChief Executive | Decided | Open |
| 28 Jul 2026 | Declaration of interestsCouncillor Jason McLellan – Personal and Prejudicial Interest – Agenda Item Nos. 9 & 10 | Decided | Open |
| 28 Jul 2026 | Urgent mattersNo urgent matters had been raised. | Decided | Open |
| 28 Jul 2026 | MINUTESRESOLVED that the minutes of the meeting held on 30 June 2026 be received and confirmed as a correct record. | Decided | Open |
| 28 Jul 2026 | Denbighshire county council digital strategy 2026 - 2031RESOLVED that Cabinet – (a) approve the Denbighshire County Council Digital Strategy 2026 – 2031 (Appendix 1 to the r... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.