Vote taken: 8 in favour, 0 against, 0 abstentions RESOLVED that Cabinet – (a) note the budgets set for 2020/21 and progress against the agreed budget strategy; (b) approve the recommended use of the Schools Maintenance Grant which has been awarded to the Council by the Welsh Government, as recommended by the Strategic Investment Group and as detailed in the report and Appendices 5, 6 and 7 to the report; (c) approve the recommended use of the Welsh Government indicative grant allocation awarded to the Council for damage to highways assets as recommended by the Strategic Investment Group and as detailed in the report and Appendices 8, 9 and 10 to the report, and (d) approve the recommended use of the Childcare Capital Grant which has been awarded to the Council by the Welsh Government, as recommended by the Strategic Investment Group and as detailed in the report and Appendices 11 and 12 to the report.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Report author Steve Gadd, Head of Finance and Property
Title Finance Report (November 2020/21)
1. What is the report about?
The report gives details of the council’s revenue budget and savings as agreed for 2020/21. The report also provides a summary update of the Capital Plan as well as the Housing Revenue Account and Housing Capital Plan.
2. What is the reason for making this report?
The purpose of the report is to provide an update on the council’s current financial position and confirm the agreed service budgets for 2020/21.
3. What are the Recommendations?
3.1Members note the budgets set for 2020/21 and progress against the agreed strategy.
3.2Members approve the recommended use of the Schools Maintenance Grant which has been awarded to the Council by the Welsh Government, as recommended by the Strategic Investment Group and detailed in this report and Appendices 5, 6 and 7.
3.3Members approve the recommended use of Welsh Government indicative grant allocation awarded to the Council for damage to highways assets as recommended by the Strategic Investment Group and detailed in this report and Appendixes 8, 9 and 10. 3.4 Members approve the recommended use of the Childcare Capital Grant which has been awarded to the Council by the Welsh Government, as recommended by the Strategic Investment Group and detailed in this report and Appendices 11 and 12.
4. Report details
The report provides a summary of the council’s revenue budget for 2020/21 detailed in Appendix 1. The council’s net revenue budget is £208.302m (£198.538m in 19/20). The position on service and corporate budgets is a forecast overspend of £2.476m (£5.492m last month). This overspend now includes £2.7m paid in respect of the ‘income loss’ grant for Quarter 2 (full claim amounted to £3.233m). Narrative around the current risks and assumptions underlying this assessment are outlined in Section 6 and Appendix 2 which also highlights the gross overspend.
The 2020/21 budget required service savings and efficiencies of £4.448m to be identified and agreed as detailed below: Corporate savings identified relating to the triennial actuarial review of the Clwyd Pension Fund (£2m) Schools savings of 1% (£0.692m) Service efficiencies and savings (£1.756m) The corporate savings have already been achieved and the schools’ savings are delegated to the governing bodies to monitor and deliver. On top of this £1.086m of the service savings had originally been designated as savings that have already been implemented.
5. How does the decision contribute to the Corporate Priorities?
Effective management of the council’s revenue and capital budgets and delivery of the agreed budget strategy underpins activity in all areas, including corporate priorities.
6. What will it cost and how will it affect other services?
Significant service narratives explaining variances and risks are detailed in Appendix 2, however the following should also be noted: Impact of Corona Virus - The current short term strategy of working with Welsh Government has helped secure significant funding that has been detailed in previous reports. A system of monthly expenditure claims and quarterly income loss claims has been established. Due to the recent lockdown the £264m announced in August may not be sufficient but we are working with WLGA and WG to ensure the position is monitored closely.
The table below summarises the position of the expenditure claims for DCC. The ‘Holding’ column indicates items that WG are requesting further information on:
Original total FSM Net Claim Month Disallowed Holding claim adjustment paid to date
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.