Resolved
RESOLVED that Cabinet note the budgets set for 2020/21 and progress against the agreed budget strategy.
Cabinet noted this item on Tuesday 19 January 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that Cabinet note the budgets set for 2020/21 and progress against the agreed budget strategy.
Report to Cabinet
Date of meeting 19th January 2021
Lead Member / Officer Julian Thompson Hill
Report author Steve Gadd, Head of Finance and Property
Title Finance Report (December 2020/21)
1. What is the report about?
The report gives details of the council’s revenue budget and savings as agreed for 2020/21. The report also provides a summary update of the Capital Plan as well as the Housing Revenue Account and Housing Capital Plan.
2. What is the reason for making this report?
The purpose of the report is to provide an update on the council’s current financial position and confirm the agreed service budgets for 2020/21.
3. What are the Recommendations?
3.1Members note the budgets set for 2020/21 and progress against the agreed strategy.
4. Report details
The report provides a summary of the council’s revenue budget for 2020/21 detailed in Appendix 1. The council’s net revenue budget is £208.302m (£198.538m in 19/20). The position on service and corporate budgets is a forecast overspend of £2.242m (£2.476m last month). Narrative around the current risks and assumptions underlying this assessment are outlined in Section 6 and Appendix 2 which also highlights the gross overspend. The 2020/21 budget required service savings and efficiencies of £4.448m to be identified and agreed as detailed below: Corporate savings identified relating to the triennial actuarial review of the Clwyd Pension Fund (£2m) Schools savings of 1% (£0.692m) Service efficiencies and savings (£1.756m) The corporate savings have already been achieved and the schools’ savings are delegated to the governing bodies to monitor and deliver. On top of this £1.086m of the service savings had originally been designated as savings that have already been implemented.
5. How does the decision contribute to the Corporate Priorities?
Effective management of the council’s revenue and capital budgets and delivery of the agreed budget strategy underpins activity in all areas, including corporate priorities.
6. What will it cost and how will it affect other services?
Significant service narratives explaining variances and risks are detailed in Appendix 2, however the following should also be noted:
Impact of Corona Virus - The current short term strategy of working with Welsh Government has helped secure significant funding that has been detailed in previous reports. A system of monthly expenditure claims and quarterly income loss claims has been established. Due to the recent lockdown the £264m announced in August may not be sufficient but we are working with WLGA and WG to ensure the position is monitored closely.
The table below summarises the position of the expenditure claims for DCC. The ‘Holding’ column indicates items that WG are requesting further information on: Original total FSM Net Claim Month Disallowed Holding claim adjustment paid to date
March 2020 £61,701 £0 £0 £61,701 April 2020 £666,927 (£8,865) £0 £658,062 May 2020 £1,200,170 (£21,076) (£190,316) £988,778 June 2020 £1,027,489 (£29,226) (£158,614) £839,649 July 2020 £608,569 0 (£248,013) £360,556 August 2020 £449,370 £433,376 £882,746 September 2020 £753,407 (£33,248) £720,159 October 2020 £808,964 (£27,234) (£236,403) £545,327 November 2020 £820,502 (£6,300) (£6,032) (£92,955) £715,215
Submitted to date £6,397,099 (£125,949) (£169,599) (£329,358) £5,772,193
The table below summarises the position relating to the quarterly income loss claims:
Original total Quarter Disallowed Holding Paid by WG claim
Loss of income Qtr 1 £4,007,786 (£567,923) (£122,240) (£3,317,623) Loss of income Qtr 2 £3,232,679 (£74,999) (£453,378) (£2,704,302)
Grand Total £7,240,465 (£642,922) (£575,618) (£6,021,925)
The tables above illustrate that so far Welsh Government have paid a total of £11.794m. Quarter 3 claim is currently being collated and will be reported on next month
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
FINANCE REPORT: App 1 Revenue SummaryAppendix | 233 KB | Download |
PDF |
FINANCE REPORT: App 2 Service Variance AnalysisAppendix | 450 KB | Download |
PDF |
FINANCE REPORT: App 3 Summary of Capital PlanAppendix | 198 KB | Download |
PDF |
FINANCE REPORT: App 4 Major Capital Projects UpdateAppendix | 478 KB | Download |
PDF |
FINANCE REPORTReport | 462 KB | DownloadRead as text |
Follow Cabinet at Denbighshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Jul 2026 | ApologiesChief Executive | Decided | Open |
| 28 Jul 2026 | Declaration of interestsCouncillor Jason McLellan – Personal and Prejudicial Interest – Agenda Item Nos. 9 & 10 | Decided | Open |
| 28 Jul 2026 | Urgent mattersNo urgent matters had been raised. | Decided | Open |
| 28 Jul 2026 | MINUTESRESOLVED that the minutes of the meeting held on 30 June 2026 be received and confirmed as a correct record. | Decided | Open |
| 28 Jul 2026 | Denbighshire county council digital strategy 2026 - 2031RESOLVED that Cabinet – (a) approve the Denbighshire County Council Digital Strategy 2026 – 2031 (Appendix 1 to the r... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.