RESOLVED : · Delegate approval of the final Local Impact Report to Officers, in consultation with the affected Ward Councillors · Submit representations to the Planning Inspectorate to raise no objection to the proposed Elwy Solar Farm, subject to the imposition of conditions set out in the Local Impact Report.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
REPORT BY THE HEAD OF PLANNING, PUBLIC PROTECTION AND COUNTRYSIDE SERVICES
ELWY SOLAR ENERGY FARM - DEVELOPMENT OF NATIONAL SIGNIFICANCE
APPROVAL TO SUBMIT A LOCAL IMPACT REPORT AND FORMAL REPRESENTATIONS TO THE PLANNING INSPECTORATE
1. PURPOSE OF THIS REPORT 1.1 The Elwy Solar Energy Farm Development of National Significance application has been formally accepted by the Planning Inspectorate, who will consider the application on behalf of Welsh Ministers. 1.2 Denbighshire County Council is required to submit a Local Impact Report and has been invited to make formal representations on the application. 1.3 This report seeks Members approval to submit a Local Impact Report, and to seek a formal resolution on the representations to be made in response to the application. 2. BACKGROUND 2.1 Applications for Developments of National Significance (DNS) are submitted to the Planning Inspectorate and determined by Welsh Government rather than local planning authorities. 2.2 An application for a Solar Park at land at Gwernigron Farm, The Roe, St. Asaph with an export capacity of 62MW has been submitted to Welsh Ministers by Solar Century Holdings Ltd under the Developments of National Significance (Wales) Regulations 2016. The application was formally accepted by the Planning Inspectorate on 22 June 2021. 2.3 The Council is now required to submit a Local Impact Report to the Planning Inspectorate. The Council is also invited to submit formal representations on the proposal. The Local Impact Report and any representations must be submitted to the Planning Inspectorate by 27 July 2021. 2.4 In accordance with the Scheme of Delegation, Committee approval is required to submit Local Impact Reports and any formal representations on major infrastructure projects. 2.5 Members may remember that the proposal was subject to formal pre-application consultation during the summer / autumn of 2020. In response to the developer’s pre-application consultation, in November 2020 Planning Committee resolved to “support in principle the pre-application consultation, subject to the formal application and subject to the local impact report.” 3. THE ELWY SOLAR ENERGY FARM PROPOSAL: 3.1 Solar Century (the developer) are proposing a solar energy farm development on land to the north of the A55 and to the west of A525 in St Asaph. The proposed grid connection corridor also forms part of the application; the corridor, crosses through the St Asaph Business Park to the south of the A55 and extends to the existing National Grid substation which is located to the south of Glascoed Road. 3.2 The site is approximately 156 hectares in size and the solar energy farm would have an installed capacity of 62MW (megawatts). 3.3 The site lies within the St Asaph West, Bodelwyddan and Trefnant Ward Areas. 3.4 The location plan and proposed site layout plan is attached at the front of this report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.