CONSTRUCTION OF 15 APARTMENTS FOR SOCIAL RENT AT THE DELL, PRESTATYN - CONTRACT AWARD

Approved Executive 2 papers

Cabinet approved this item on Tuesday 21 September 2021. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

RESOLVED that Cabinet – (a) approve the award of a contract to RL Davies & Sons Limited as per the Contract Award Recommendation Report (Appendix 1 to the report), and (b) confirms that it has read, understood and taken account of the Well-being Impact Assessment (Appendix 2 to the report) as part of its consideration.
Word for word from the decision Denbighshire published for this meeting. Source: moderngov.denbighshire.gov.uk

Follow this further

Built from Denbighshire's papers

What the report saysPro

Report to Cabinet

Report to Cabinet

Date of report 21st September 2021

Lead Member / Officer Councillor Tony Thomas Lead Member for Housing & Communities

Councillor Julian Thompson-Hill Lead Member for Finance, Performance & Strategic Assets

Report author Mark Dixon

Title Construction of 15 apartments for social rent at The Dell in Prestatyn - Contract Award

1. What is the report about?

1.1This report summarises the process undertaken during the procurement exercise and recommends the award of a contract to appoint a Principal Contractor to construct 15 apartments for social rent at The Dell in Prestatyn.

2. What is the reason for making this report? 2.1 A Cabinet decision is required to enable RL Davies & Sons Limited to be awarded the contract for the construction of 15 apartments for social rent at The Dell in Prestatyn.

3. What are the Recommendations? 3.1 That Cabinet approve the award of a Contract to RL Davies & Sons Limited as per the Contract Award Recommendation Report in Appendix 1.

3.2That Cabinet confirms that it has read, understood and taken account of the Well- being Impact Assessment (Appendix 2) as part of its consideration. 4. Report details 4.1. Further to the Cabinet decision of 30th July 2019, Denbighshire County Council wishes to appoint a Contractor to construct 15 apartments for social rent at The Dell in Prestatyn.

4.2A contract notice with an estimated value of £4,100,183.71 was published on the Sell2Wales procurement portal on 26th January 2021 with a deadline for submission of 2nd March 2021. Following representations from a number of tenderers this deadline was extended to 19th April 2021.

4.3Four tender submissions were received.

4.4Following an evaluation exercise using a scoring methodology with a weighting of 70% for price and 30% for quality, a preferred contractor has been selected. Further details can be found in the draft Contract Award Recommendation Report in Appendix 1.

5. How does the decision contribute to the Corporate Priorities? 5.1. The Council’s Corporate Plan includes a priority to ensure that everyone is supported to live in homes that meet their needs. Theme 2 of the Housing & Homelessness Strategy adopted by the County Council at its meeting on 8th December 2020 concerns creating a supply of affordable homes and includes headline actions to facilitate the building of Council homes and the provision of accommodation suited to the older demographic profile of the county’s population. This decision will contribute towards the delivery of the Corporate Plan and Housing & Homelessness Strategy by enabling the construction of accessible homes for social rent.

5.2The proposed development will contribute towards the delivery of the Climate & Ecological Change Strategy adopted by the County Council on 23rd February 2021 by building new Council premises which will be low carbon in operation through the inclusion of renewable energy and heat technologies. This will be achieved by avoiding the use of hydrocarbons for space and water heating in the development. 6. What will it cost and how will it affect other services? 6.1. The total estimated cost submitted by the successful tenderer, RL Davies & Sons Limited was £3,021,361.96. This is within the budget for the project in the Housing Stock Business Plan.

6.2Development of the site will enable the management issues with the land which faced the Council’s Countryside Service to be addressed as it has hitherto been a location for anti-social behaviour and fly tipping, and it harbours vermin.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CONSTRUCTION OF 15 APARTMENTS FOR SOCIAL RENT AT THE DELL, PRESTATYN: CONTRACT AWARDReport 133 KB DownloadRead as text
PDF
CONTRACT AWARD: THE DELL PRESTATYN WBIAReport 102 KB Download

More from Denbighshire Cabinet

All decisions
MeetingDecisionOutcome
28 Jul 2026 ApologiesChief Executive Decided Open
28 Jul 2026 Declaration of interestsCouncillor Jason McLellan – Personal and Prejudicial Interest – Agenda Item Nos. 9 & 10 Decided Open
28 Jul 2026 Urgent mattersNo urgent matters had been raised. Decided Open
28 Jul 2026 MINUTESRESOLVED that the minutes of the meeting held on 30 June 2026 be received and confirmed as a correct record. Decided Open
28 Jul 2026 Denbighshire county council digital strategy 2026 - 2031RESOLVED that Cabinet – (a) approve the Denbighshire County Council Digital Strategy 2026 – 2031 (Appendix 1 to the r... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies