RESOLVED that Cabinet – (a) approve the proposed tendering exercise as detailed within the report, and (b) confirm it has read, understood and taken account of the Wellbeing Impact Assessment (Appendix 1 to the report) as part of its consideration.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Lead Member / Officer Cllr Brian Jones: Lead Member for Waste, Transport and the Environment / Tony Ward: Head of Highways, Facilities & Environmental Services
Report author(s) Peter Clayton, Project Manager and Tony Ward, Head of Highways, Facilities & Environmental Services
Title Proposed approach to Tendering for Phase 2 new DCC Waste Transfer Station (WTS) at Colomendy Industrial Estate, Denbigh.
1. What is the report about?
1.1This report is about a proposal to undertake a tendering process to identify a main contractor to deliver Phase 2 new DCC Waste Transfer Station (WTS) at Colomendy Industrial Estate, Denbigh. The proposed Waste Transfer Station is required to support the planned service change for household waste collections.
2. What is the reason for making this report?
2.1A decision is required to give approval to the proposed tendering exercise to identify a main contractor to deliver Phase 2 new DCC Waste Transfer Station (WTS) at Colomendy Industrial Estate, Denbigh.
3. What are the Recommendations?
3.1That Cabinet grant approval to undertake the proposed tendering exercise NOTE: A further report will be brought back to Cabinet for approval of the subsequent Contract Award following the tendering exercise, which will also confirm contract management arrangements, tendered costs, and contract details.
3.2That the Committee confirms it has read, understood and taken account of the Well-being Impact Assessment (Appendix 1) as part of its consideration.
4. Report details
4.1Outline timescale for the proposed tender exercise are detailed below. Given the potential works value, OJEU timescales apply. In setting up and running the tendering exercise, officers will work with (and take advice from) Legal & Procurement. The tender will be issued via Sell2Wales using the Proactis system. Key milestones and their target dates for this tendering exercise are shown below:
Target Date Milestone 29/10/2021 Final contract terms, specification & evaluation methodology agreed by Procurement/Legal
01/11/2021 Tender advertised
10/12/2021 Tender closed to responses, start evaluation
18/02/2022 Evaluation finalised (start of 10 day standstill period following issue of award letters)
30/03/2022 Contract award
25/04/2022 Contract start (Works)
4.2The anticipated contract value is estimated at £5.25M which is within the current budget allocated for delivery of the new WTS to support the wider proposed waste service remodelling. 5. How does the decision contribute to the Corporate Priorities?
5.1Although not directly mentioned within the current Corporate Plan, the planned changes to household waste collection will have a positive on the Corporate Priority, “Environment: Attractive and Protected, supporting well-being & economic prosperity”. It will increase the quantity and quality of recycling collected from households, and increase opportunities for closed loop recycling. It will also enable the potential expansion of local businesses, leading to employment opportunities and economic growth.
6. What will it cost and how will it affect other services?
6.1The cost of the proposed tender exercise will solely be in officer time associated with the work. As noted already, further approvals will be sought via Cabinet for Contract Award to the successful contractor at the end of the tendering process.
7. What are the main conclusions of the Well-being Impact Assessment?
7.1This Report is simply seeking approval to issue an Invitation to Tender (ITT), See Appendix 1 for further detail of WBIA undertaken for overall Waste Service Remodelling within which the development of a new Waste Transfer Station is a key element to support the proposed new service model. The overall outcome of the Well-being Impact Assessment is positive.
8. What consultations have been carried out with Scrutiny and others?
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.