Resolved
RESOLVED that, subject to the above, the minutes of Full Council held on 12 October 2021 be confirmed as a correct record.
County Council decided this item on Tuesday 7 December 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that, subject to the above, the minutes of Full Council held on 12 October 2021 be confirmed as a correct record.
COUNTY COUNCIL
Minutes of a meeting of the County Council held in via VIDEO CONFERENCE on Tuesday, 12 October 2021 at 10.00 am.
PRESENT
Councillors Brian Blakeley, Joan Butterfield, Ellie Chard, Ann Davies, Meirick Davies, Hugh Evans, Peter Evans, Bobby Feeley, Rachel Flynn, Huw Hilditch-Roberts, Alan Hughes, Alan James (Chair), Brian Jones, Pat Jones, Gwyneth Kensler, Geraint Lloyd-Williams, Richard Mainon, Christine Marston (Vice-Chair), Barry Mellor, Melvyn Mile, Bob Murray, Merfyn Parry, Paul Penlington, Pete Prendergast, Arwel Roberts, Anton Sampson, Peter Scott, Glenn Swingler, Rhys Thomas, Tony Thomas, Julian Thompson-Hill, Graham Timms, Joe Welch, David Williams, Eryl Williams, Huw Williams, Emrys Wynne and Mark Young
ALSO PRESENT
Chief Executive (GB), Corporate Director: Communities (NS), Head of Legal, HR and Democratic Services (GW), Head of Finance and Property (SG), Head of Highways and Environmental Services (TW), Head of Children’s Services (RM), Flood Risk Engineer (WH), Webcast Zoom Host (SJ), Committee Administrator (SLW)
1 APOLOGIES
Apologies for absence were received from Councillors Jeanette Chamberlain- Jones, Tony Flynn, Martyn Holland, Hugh Irving, Tina Jones, Andrew Thomas and Cheryl Williams
2 DECLARATIONS OF INTEREST
None.
3 URGENT MATTERS AS AGREED BY THE CHAIR
None.
4 MINUTES
The minutes of Full Council held on 7 September 2021 were submitted.
RESOLVED that the minutes of Full Council held on 7 September 2021 be confirmed as a correct record. 5 9 FEBRUARY 2020 FLOOD EVENT - SECTION 19 FLOOD INVESTIGATION REPORT
The Lead Member for Waste, Transport and the Environment, Councillor Brian Jones, introduced the 9 February 2020 Flood Event - Section 19 Flood Investigation Report (previously circulated).
On the 9th of February 2020, extensive flooding occurred across Denbighshire as a result of Storm Ciara. Council officers, as well as officers from Natural Resources Wales (NRW) and Dŵr Cymru Welsh Water, had since carried out investigations into the flooding to understand the reason why the flooding occurred, the likelihood of it happening again and to assess whether measures could be put in place to reduce flooding in future.
Keith Ivens of NRW commenced with the queries raised regarding St. Asaph. He confirmed that the event in February 2020 had been an extreme event. The new defences were constructed, built and designed on a 1 in 100 year standard of protection including allowance for climate change. What had been seen in the event analysis in Appendix B was a hydrological analysis of occurrences due to Storm Ciara.
Storm Ciara was estimated to be a 1 in 250 / 1 in 300 year event at peak flow. Immediately after the event it had been queried why there had been overtopping in one particular location. Extensive discussions had taken place with the designers, and an extensive post event modelling carried out with the designers to understand what happened in that location. It had been resolved with the designers which had led to the works which were currently being carried out in St. Asaph. The community of St. Asaph had very good protection and 370 properties had been protected which would have been flooded otherwise.
Failure of water level recorder in St. Asaph under the A55. The type of equipment installed at that location was a pressure transducer which was set with an upper and lower limit, but it had exceeded the upper limit. The pressure transducer was still in place but an additional downward facing ultrasonic level sensor was now situated on the new Spring Gardens Bridge which allowed NRW to monitor water levels and that fed into the flood forecasting model for the River Elwy
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MINUTESMinutes | 212 KB | DownloadRead as text |
Follow County Council at Denbighshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Jul 2026 | MINUTESRESOLVED that the minutes of the meeting held on the 12 May 2026 subject to the agreed corrections be received and co... | Agreed | Open |
| 7 Jul 2026 | Council performance self-assessment 2025 to 2026 and performance update report october 2025 to march 2026RESOLVED that the Council I. noted the six-monthly Performance Update Report and Citizens' Voice Report; II. noted th... | Noted | Open |
| 7 Jul 2026 | Strategic equality and diversity group (sedg) annual statement 2025 to 2026RESOLVED that Council: I. acknowledged the Strategic Equality and Diversity Group Annual Statement for 2025/26; and I... | Decided | Open |
| 7 Jul 2026 | Pay policy statement 2026/27RESOLVED that Council: I. approved the Pay Policy Statement for 2026/27 as recommended by the Senior Leadership Remun... | Approved | Open |
| 7 Jul 2026 | Appointment of county councillor to the standards committeeRESOLVED that Councillor Andrea Tomlin be appointed as the County Council representative on the Standards Committee. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.