RESOLVED that Cabinet – (a) delegates authority to award a Contract for the construction of Phase 1 of the Queen’s Building development to the preferred Contractor to the Chief Executive in consultation with the Section 151 Officer, Monitoring Officer and relevant Lead Members at the conclusion of the detailed design stage providing the cost plan is within the envelope of affordability for the works; (b) approves the immediate implementation of the Delegated Decision due to the urgency to award a Contract to allow works to commence on site as soon as possible to meet grant funding deadlines, and (c) confirms that it has read, understood and taken account of the Wellbeing Impact Assessment as part of its consideration (Appendix 1 to the report).
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Lead Member / Officer Cllr Hugh Evans OBE, Leader of the Council and Lead Member for the Economy and Corporate Governance
Cllr Julian Thompson-Hill, Deputy Leader of the Council and Lead Member for Finance, Performance and Strategic Assets
Report author Russell Vaughan
Title Queens Buildings Phase 1 – construction contract award
1. What is the report about? This report is about the second stage of the process to award a contract for the construction of the Queen’s Buildings development in Rhyl.
2. What is the reason for making this report? To seek the approval of Cabinet to award a Contract to the preferred Contractor via Delegated Decision.
3. What are the Recommendations? 3.1. That Cabinet delegates authority to award a Contract for the construction of Phase I of the Queen’s Building development to the preferred Contractor to the Chief Executive in consultation with the Section 151 Officer, Monitoring Officer and relevant Lead Members at the conclusion of the detailed design stage providing the cost plan is within the envelope of affordability for the works;
3.2That Cabinet approves the immediate implementation of the Delegated Decision due to the urgency to award a Contract to allow works to commence on site as soon as possible to meet grant funding deadlines; and
3.3That Cabinet confirms that it has read, understood and taken account of the Well- being Impact Assessment as part of its consideration (Appendix 1). 4. Report details
4.1In March 2019, Denbighshire County Council acquired a number of adjacent buildings in Rhyl town centre on the seafront, known collectively as Queen’s Buildings. The buildings were in a dilapidated state, with no active uses on upper floors (the seafront buildings are four storeys) and significant areas of vacant floor space at the ground floor level. Towards the end of 2020 the Council developed ambitious plans for a mixed use, phased development of the site. All buildings other than the Queen’s Chambers on the Sussex Street frontage have now been demolished and a full Planning approval for Phase 1 and an outline approval for subsequent phases was granted at the Planning Committee in September 2021.
4.2In April 2021, Cabinet approved the procurement strategy to deliver Phase 1 of the Queens Buildings development. This was to appoint a contractor on a two-stage process via Lot 3 of the North Wales Construction Partnership (NWCP) framework. Wynne Construction were successful in this first stage and were appointed to work the scheme up from Planning approved, through detailed design to construction. We will shortly be at a stage where the Contractors Proposals (CP’s) have been received and agreed, and are in a position to let the construction contract to Wynne Construction to deliver Phase 1 of the development.
4.3Having secured the budget required to deliver Phase I of the project, the final stages of detailed design work is taking place including preparation of the CP’s and the contract specification ready for construction, which is due to start in mid/late April. As the letting of the construction contract will fall after the last Cabinet meeting of this Council, approval to award the contract through a Delegated Decision is required to ensure that the tight timescales for project delivery are achieved. All of the outputs need to be delivered and funding drawn down by 28th February 2023 or we would have to return in excess of £5.5m of grant funding received or for which offers are in place.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.