Resolved
RESOLVED that the Planning Committee note the Planning Appeal Decisions – Mindale Farm, Prestatyn .
Planning Committee noted this item on Wednesday 15 June 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Planning Committee note the Planning Appeal Decisions – Mindale Farm, Prestatyn .
RESIDENTIAL DEVELOPMENT AT MINDALE FARM, MELIDEN
Planning applications 43/2018/0750 & 43/2018/0751/PF
1. Background to the decisions
1.1Two planning applications were submitted to Denbighshire LPA in relation to residential development at Mindale Farm, Meliden.
1.2The main application (43/2018/0750/PF) sought full planning permission for the demolition of existing dwelling and outbuildings at Mindale Farm and the erection of 133No.dwellings, construction of internal estate roads, sewers, SUDS drainage and open spaces, strategic and hard/ soft landscaping and ancillary works. This is referred to as ‘Application A’ and ‘Appeal A’.
1.3The second application (43/2018/0751/PF) sought full planning permission for the construction of a new road from Ffordd Talargoch to land at Mindale Farm. This is referred to as ‘Application B’ and ‘Appeal B’.
1.4Members will be aware that prior to the above planning applications, there was a previous application for residential development at the same site, which was refused by Planning Committee, and subsequently dismissed at appeal. This is referred to as ‘the 2017 appeal decision’.
1.5The two applications subject of this report were accompanied by a raft of technical documents including a Transport Assessment, an Ecological Assessment, an Arboricultural Impact Assessment/ Method System, a Flood Consequence Assessment, an Archaeological Assessment, an outline drainage strategy, a Community Linguistic Statement Report and Impact Assessment, a Geophysical Survey Report, and a Water Conservation Strategy.
1.6In addition, neighbour letters were distributed to some 220 addresses in the vicinity of the site, site notices were posted around the site and the application was advertised in the press. Responses were received from over 50 different addresses.
1.7The individual objections received in the main focussed on the following issues: - The principle of the development and the need for housing - Highway concerns - Flooding and drainage - Ecological impacts - Impacts on local schools and hospitals - Land ownership issues
1.8The applications were presented to Planning Committee for consideration in September 2019. The Officers’ report detailed the proposals, responses to consultation and publicity, the material considerations, and matters which had arisen in the course of progressing the application. The report advised on the Council’s adopted planning policies and the Site Development Brief relating to the development of the site and an adjoining allocated site.
1.9The reports concluded on the basis of the responses from the key ‘technical’ consultees, that there were limited land use planning grounds to oppose the grant of permission, and that there were reasonable controls which could be exercised through planning conditions and a legal agreement to mitigate impacts, sufficient to merit a positive recommendation. The matters it was suggested could be dealt with through a legal agreement included off site highway improvements, and contributions to affordable housing, education provision, and mitigation of impact on the Welsh language.
1.10The applications were discussed at length at Committee. The local member provided some background history to the site, which had been included in the LDP following allocation by the Planning Inspector, who he understood had indicated that if the infrastructure was not in place, then planning permission could be refused. It was argued that the existing local infrastructure was not adequate to cope with the scale of the development, particularly in terms of highways and drainage/flooding. Prestatyn Members concurred with the comments made by the Local Member, elaborating further on those issues and their concerns regarding the impact of the development on the village and its infrastructure. The committee generally shared those concerns, which had also been raised by members who had attended the Site Inspection Panel meeting.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Mindale DecisionDecisions | 330 KB | Download |
PDF |
Mindale Update report 2022Report | 244 KB | DownloadRead as text |
PDF |
MindaleCost Decision 3243545 and 3243547Decisions | 263 KB | Download |
PDF |
SPECIAL REPORT: LAND NORTH OF MELIDEN ROAD AND WEST OF FFORDD TY NEWYDD, MELIDEN, PRESTATYNReport | 91 KB | Download |
Follow Planning Committee at Denbighshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | MINUTESthat the minutes from the meeting held on the 15 July 2026 be received and approved as a true and correct record of t... | Approved | Open |
| 15 Jul 2026 | MINUTESthat the minutes from the meeting held on the 17 June 2026 be received and approved as a true and correct record of t... | Approved | Open |
| 17 Jun 2026 | MINUTESthat the minutes of the Planning Committee meeting held on the 13 May 2026 be received and approved as a true and cor... | Approved | Open |
| 13 May 2026 | Appointment of chairRESOLVED that Councillor Mark Young be appointed Chair of the Planning Committee for the 2026/27 municipal year. | Decided | Open |
| 13 May 2026 | Appointment of vice-chairRESOLVED that Councillor Alan James be appointed Vice-Chair of the Planning Committee for the 2026/27 municipal year. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.