Resolved
RESOLVED that permission be GRANTED in accordance with officer recommendations as detailed within the report and supplementary papers.
Planning Committee decided this item on Wednesday 13 July 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that permission be GRANTED in accordance with officer recommendations as detailed within the report and supplementary papers.
Location plan Condition of existing coastal defences Proposed rock scour protection (eastern section from Splash Point to SeaQuarium): Proposed rock scour protection (eastern section from Splash Point to SeaQuarium): Proposed new concrete stepped revetment, raised and widened promenade and new seawall (western section from SeaQuarium to Drift Park) Proposed new concrete stepped revetment, raised and widened promenade and new seawall (western section from SeaQuarium to Drift Park) New East Rhyl coastal defences (rock revetment) at Splash Point Existing prom & defences (east near Splash Point) Existing promenade & defences Existing promenade and defences Existing promenade and defences Existing promenade and defences Existing promenade and defences Existing promenade and defences Existing promenade and defences Existing promenade and defences Existing promenade and defences Existing promenade and defences West Rhyl Coastal Defences (ramped & rock revetment) Denise Shaw WARD : Rhyl West and Rhyl West
WARD MEMBER(S): Cllr Joan Butterfield & Cllr Alan James (c) (Rhyl West) Cllr Justine Evans & Cllr Barry Mellor (Rhyl East)
APPLICATION NO: 45/2022/0271/ PF
PROPOSAL: Construction of coastal protection scheme, incorporating; new sea wall, repair works and engineering operations including scour protection to existing sea wall. Installing new concrete step revetments. Raising and widening of promenade including new and amended accesses, landscaping and associated works. Ecological mitigation and access works at Barkby Beach
LOCATION: Central Rhyl Coastal Defences Scheme Rhyl
APPLICANT: Denbighshire County Council [name removed]: PUBLICITY Site Notice - Yes UNDERTAKEN: Press Notice - Yes Neighbour letters - Yes
REASON(S) APPLICATION REPORTED TO COMMITTEE: Scheme of Delegation Part 2 Referral by Head of Planning / Development Control Manager
CONSULTATION RESPONSES: RHYL TOWN COUNCIL: No objections.
CONWY COUNTY BOROUGH COUNCIL: No objections, but requests that restrictions are included on delivery times, in order to mitigate the impact of construction traffic on the residents of Kinmel Bay.
NATURAL RESOURCES WALES: Recommends the imposition of a condition to satisfy concerns relating to Protected Sites, for reasons summarised below:
Protected Sites NRW note the submission of the Report to Inform a Habitats Regulations Assessment (HRA) and are satisfied all of the relevant protected sites have now been included and assessed. NRW advise that the submitted Environmental Management Plan (First Iteration) (September 2021 Mott MacDonald) should form the basis of a detailed Environmental Management Plan (EMP) which should be secured by condition to ensure no adverse effects on the integrity of Liverpool Bay SPA, alone or in-combination with other plans or projects, which should be secured by condition.
Flood Risk NRW Flood Risk Map confirms the site to be within Zone C2 and C1 of the Development Advice Map (DAM) contained in TAN15 and the Flood Map for Planning (FMfP) identifies the application site to be at risk of flooding and falls into Flood Zone 2 and 3 Sea. Section 6 of TAN15 requires the Local Planning Authority to determine whether the development at this location is justified. Therefore, we refer you to the tests set out in section 6.2 of TAN15. NRW welcomes proposals to reduce flood risk to the town of Rhyl. The increased standard of protection in relation to sea flooding has been detailed in the Flood Consequence Assessment & it is noted that the West Rhyl Coastal defence work (section I) was completed in 2015 and that the East Rhyl works are nearing completion/have been completed.
The scheme will reduce the risk of flooding from the sea within the study area. Please be aware that Rhyl is also at risk from other sources such as from the river Clwyd estuary and fluvially from the Rhyl Cut.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
45-2022-0271Report | 4.3 MB | DownloadRead as text |
PDF |
APPLICATION NO. 45/2022/0271/ PF: CENTRAL RHYL COASTAL DEFENCES SCHEME, RHYLFrontsheet | 6 KB | Download |
Follow Planning Committee at Denbighshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | MINUTESthat the minutes from the meeting held on the 15 July 2026 be received and approved as a true and correct record of t... | Approved | Open |
| 15 Jul 2026 | MINUTESthat the minutes from the meeting held on the 17 June 2026 be received and approved as a true and correct record of t... | Approved | Open |
| 17 Jun 2026 | MINUTESthat the minutes of the Planning Committee meeting held on the 13 May 2026 be received and approved as a true and cor... | Approved | Open |
| 13 May 2026 | Appointment of chairRESOLVED that Councillor Mark Young be appointed Chair of the Planning Committee for the 2026/27 municipal year. | Decided | Open |
| 13 May 2026 | Appointment of vice-chairRESOLVED that Councillor Alan James be appointed Vice-Chair of the Planning Committee for the 2026/27 municipal year. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.