RESOLVED that Cabinet – (a) directly award the contract to the contractor currently undertaking Phase 1 of the works based on the competitive rates via the Welsh Procurement Alliance Energy Framework as agreed by Procurement, and (b) that the 5-day call in period requirement prior to implementing the Cabinet decision is waived on the basis that the current contract ends on 30 September 2022 and any delay in contract award will lead to additional costs and programme delays leading to the risk of missing grant stipulated spending deadlines.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Lead Member / Officer Rhys Thomas – Lead Member for Housing & Communities /David Lorey – Lead Officer Corporate Property & Housing Stock
Report author Katrina Allen
Title Phase 2 Social Housing Retrofit Works – Rhydwen Drive Rhyl
1. What is the report about? 1.1. To seek approval to proceed with a Direct Award contract to Sustainable Building Services for our energy retrofit works. This work falls within the Capital Planned Works with approved Cabinet commitment to a £2.5M Lot spend.
2. What is the reason for making this report? 2.1. To advise Cabinet of the proposals for us to continue works in Rhydwen Drive Rhyl to mitigate fuel insecurities.
3. What are the Recommendations?
3.1To directly award the contract to the contractor currently undertaking phase 1 of the works based on the competitive rates via the Welsh Procurement Alliance Energy Framework as agreed by Procurement.
3.2That the 5 day call in period requirement prior to implementing the Cabinet decision is waived on the basis that the current contract ends on 30th September 2022 and any delay in contract award will lead to additional costs and programme delays leading to the risk of missing grant stipulated spending deadlines. 4. Report details 4.1. In December 2020 the Welsh Government invited bids for rounds 1, 2.1 and 2.2 of the Optimised Retrofit Programme (ORP). Denbighshire has already secured circa £5.8Million from previous bids for both core and innovative works to our homes. ORP 3.0, this year, will not be based on invited bids but based on a stock formula so we are guaranteed funding this year for our Core energy works.
4.2ORP funding 2.1 was sought for 55 houses on Rhydwen Drive/Close. The funding did not stretch to all, approx. 100 council houses, on the street. We are asking to continue our Planned Capital Energy Works to those left, reaching a further 44 houses. We do not want to lose continuity on site The benefits of continuing this scheme early Oct is that:
We can retain the 12 local apprentices we’ve gained from Phase 1 and continue their employment for a further 26 weeks. They walk to work as cannot afford a car. 6 of them are on tailor made roofing courses to help with individual disabilities. The site is already mobilised and we can save costs by not having to remove then set up again. The Supply chain are holding onto stock as to not cause potential time/cost delay. All our subcontractors (except the renderers) are local companies. Costs are secured through the Welsh Procurement Alliance Framework so we can ensure Value for Money. We can retain the continued quality of workmanship.
4.3The improvements have included integrated solar PV, increased wall insulation via external wall insulation (EWI) and the installation of battery technology to harness solar gain, we have also been able to upskill local businesses in green technology installs and had 12 new local apprenticeships on site.
4.4We’ve produced solar and IES guides for our tenants and hold drop in sessions for those wanting more information on using the solar PV. 4.5. Our Capital Planned Works are scheduled outside the bird/bat nesting seasons so these works are best commenced Sept-March to help mitigate delays and disruption to tenants.
4.6We need to scale and pace these works in light of current fuel insecurities. This work generates a significant increase with regards to improving our Energy Performance Certificate (EPC) data. Early indications from our current Phase 1 programme has confirmed that we have increased these homes from an EPC D to an EPC B/A by adopting retrofit techniques and tenants are seeing a saving in their electricity bills. However, an amount of tenant energy advise/education is still required to help those truly optimise those benefits.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.