RESOLVED subject to the above comments, I. to support the proposal to re-establish a Denbighshire County Council Working Group to oversee the development of a new Flood Risk Management Strategy. II. that a representative be sought from each Member Area Group to serve on the Working Group; and III. that all stakeholders be made aware of the Working Group, invited and given sufficient notice of proposed meeting dates to ensure maximum attendance and engagement.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Lead Member / Officer Cllr Barry Mellor, Lead Member for Highways & Environment) / Andy Clark, Interim Head of Highways & Environmental Services.
Report author Tim Towers, Risk and Asset Manager / Andy Clark
Title Flood Risk Working Group / Flood Risk Management Strategy
1. What is the report about? 1.1. The report is about the requirement for the Denbighshire Council to produce a new Flood Risk Management (FRM) Strategy by 2024.
2. What is the reason for making this report? 2.1. To update the Committee on work that has taken place since the previous report from the multi-agency and riparian landowners information sharing working group was presented to the Committee on 10th March 2022.
2.2To request that the Committee support a proposal to re-establish a DCC Working Group to oversee the development of a new FRM Strategy.
3. What are the Recommendations? 3.1. That the Committee support the proposal to re-establish a DCC Working Group to oversee the development of a new FRM Strategy.
4. Report details Update since previous report to the Committee 4.1. A report was presented to the Committee on 10th March 2022 to highlight the findings of the multi-agency Flood Risk Management and Riparian Land Ownership Working Group. That report explored potential methods for strengthening communication channels and building effective working relationships between all parties and organisations that have responsibilities for managing flood risk from rivers and watercourses across Denbighshire. The committee resolved to endorse the contents of the report, including the following recommendations:
4.1.1. that a Flood Risk Working Group comprising of the flood risk management authorities and landowner representatives continue to meet on an annual basis for an updated position on issues and expectations, and report on its discussions to Communities Scrutiny Committee.
4.1.2. that the Local Flood Risk Management Strategy page on the Council’s website be re-launched including:
a) links to related Natural Resources Wales and Dŵr Cymru/Welsh Water web pages; and
b) an explanation of the responsibilities of Flood Risk Management Authorities and riparian landowners,
4.1.3. that working in partnership with Natural Resources Wales and Dŵr Cymru/Welsh Water a generic information leaflet/letter be created on the responsibilities of riparian landowners and distributed to properties adjacent to the Rhyl Cut and Prestatyn Gutter; and
4.1.4. that the report presented to the Committee be translated and circulated to City, Town and Community Councils for inclusion on their websites.
4.2With respect to these actions the update is as follows:
4.2.1 The Flood Risk Working Group hasn’t met recently but this current paper is designed to give it new impetus and focus.
4.2.2 Due to the loss of a member of staff it hasn’t been possible to improve communication relating to the web page or with Town and Community Councils but this will remain as an action that we will work to achieve in the next few months. 4.2.3 Meetings and discussions with Officers from DCC and those from NRW are taking place and progress is being made. Both organisations have commission work to look at the issue and it is anticipated that a draft document will be available to share shortly.
Proposal to re-establish a FRM Working Group
4.3DCC currently has a local Flood Risk Management Strategy, but all local authorities are required to produce and publish a revised Flood Risk Management Strategy during 2024. Officers are proposing to establish a member-led Working Group to oversee the development of our new FRM Strategy. A draft Terms of Reference is attached at Appendix A.
4.4There is an existing Flood Risk Management Strategy which has been in place since 2014 but there is a requirement now to revisit, revise and adapt it to create a new one. At the beginning of that document the Executive Summary included the following:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.