RESOLVED that Cabinet – (a) confirms that it has read, understood and taken account of the Well-being Impact Assessment (Appendix 1 to the report) as part of its consideration, and (b) approves the re-tendering of the Council Housing Voids Refurbishment Framework.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Lead Member / Officer Councillor Rhys Thomas - Lead Member for Housing & Communities/ Mark Cassidy – Lead Officer for Housing Property
Head of Service Liz Grieve, Head of Housing & Communities Service
Report author Mark Cassidy – Lead Officer for Housing Property
Title Council Housing Voids Refurbishment Framework
1. What is the report about? 1.1. The re-tendering of Denbighshire County Council’s Community Housing Voids Framework.
2. What is the reason for making this report? 2.1. To seek Cabinet approval for the re-tendering of the Framework
3. What are the Recommendations?
3.1That the Committee confirms that it has read, understood and taken account of the Well-being Impact Assessment (Appendix 1) as part of its consideration. 3.2. That Cabinet approves the re-tendering of the Framework
4. Report details 4.1. The Council’s Housing Service manages and maintains circa 3,480 tenanted properties. Tenant movement results in approximately 250 properties becoming void annually (empty while new tenants are allocated).
4.2The Council takes this opportunity to refurbish the units to the new lettable standard resulting in expenditure in excess of £4M Million p/a. 4.3. A Housing Voids Framework minimises costs and time in respect of undertaking works on void housing units, minimising spend from the Housing Revenue Account while maintaining the high standards that have been established by Denbighshire set in terms of quality housing for the Council’s housing tenants.
4.4The current, first, Voids Framework was authorised by Cabinet in 2018.
4.5The current Framework has proved that, by having nominated local contractors working with Denbighshire over the lifetime of the Framework, an improved service is delivered, in terms of quality and value.
4.6With the contractors being local, the monies stay in Denbighshire, and with them being local, we have fast turn around times for remedial works and also for tendering of new void works.
4.7In 2017 Denbighshire Housing made a strategic decision to offer an improved void standards to our tenants. This commitment is under constant review, to ensure value for money. The standard will be revised in line with the new mandated Welsh Housing Quality Standards 2023, known as WHQS 2023.
4.8The first Voids Framework was launched in response to the identified need to improve the procurement of voids works. The first framework has delivered improvements and the next iteration of the framework is designed to continue the improvements.
4.9Value and Scope of the Programme: The anticipated value of the programme is up to £16million over four (2+1+1) years, refurbishing circa 250 council homes per year.
4.10Process Overview: The tender will be split into 4 Lots according to value of projects. Lots 1 & 2 lower value (Up to £8000 per contract) with a geographical County split of North and South (of the A55). Similarly Lots 3 & 4 used the same split for higher value (£8000-£50,000 per contract).
4.11An Open (1 stage) procurement procedure will be utilised. This approach removes potential barriers for local SME’s to compete with the larger national companies. This has proved extremely successful with the current Framework
4.12The quality/price weighting for all lots will be 60/40. 4.13. A maximum of 4 contractors is set for the lower value Lot award and a maximum of 5 contractors will be set for each higher value Lot award.
4.14Subject to Cabinet decision, The OJEU notice will be published in May 2024.
5. How does the decision contribute to the Corporate Plan 2022 to 2027: The Denbighshire We Want? 5.1. The renewed Framework will support priorities within the current 2022 to 2027 Corporate Plan in terms of:
5.2A Denbighshire of quality housing that meets people's needs. We will be providing homes that meet our tenant’s needs and also complying with WHQS 2023.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.