RESOLVED that Cabinet – (a) notes the position of the approved Clwyd West Levelling Up projects in Ruthin; (b) approves the next phase of the project, commencement of the detailed design, and (c) confirms that it has read, understood and taken account of the Wellbeing Impact Assessment as set out in Appendix 1 to the report as part of its consideration.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Title Clwyd West Levelling Up Fund (LUF) Projects: St. Peter’s Square & Cae Ddol Park
1. What is the report about? 1.1. This report is about the two Clwyd West LUF projects in Ruthin – public realm improvements to St. Peter’s Square and Cae Ddol Park.
2. What is the reason for making this report? 2.1. A decision is required on progressing the project to concept design stage following consultation.
3. What are the Recommendations?
3.1That Cabinet notes the position of the approved Clwyd West Levelling Up projects in Ruthin.
3.2That Cabinet approves the next phase of the project, commencement of the detailed designs.
3.3That Cabinet confirms that it has read, understood, and taken account of the Well- being Impact Assessment, attached as Appendix 1 as part of its consideration. 4. Report details Background
4.1These projects were approved within Denbighshire County Council’s application for funding under round two of the UK Government Levelling Up Fund (LUF). The application was a package bid with two projects: Project 1 – Ruthin’s Unique Heritage and Wellbeing, Project 2 – Rural Communities and Wellbeing
4.2Both schemes are part of Project 1: Ruthin’s Unique Heritage and Wellbeing and are based on work undertaken by the Ruthin Future working group of the Town Council, who developed and consulted a long-term vision for Ruthin. Each of the schemes have specific outputs, and share an output relating to a length of improved cycle ways. The contracted outputs, and what each scheme is projected to deliver can be viewed at Appendix 2.
4.3The focus for St Peter’s Square was the creation of an events space (facilitated by the removal of the roundabout), wider and safer pavements for pedestrian and wheeled user access, maintenance of vehicle access to include parking, improved drop off and disabled provision, a design that calms and slows traffic and discourages the use of the town centre as a quick through route, and the introduction of an active travel route. For Cae Ddol the brief was less defined, as there was a wish list for the long-term vision for the park, which could not be achieved in its entirety within the funding available. The design for the park has been based on what is thought to be achievable, delivers the outputs, and is acceptable to the key stakeholders.
4.4The scope of what can be achieved within Cae Ddol includes a new cycle way between the entrance of the park and highway adjacent to the Rugby Club, which includes a replacement bridge to active travel standards, and the relocation of some gym equipment, a new scooter and bike track (pump track), located adjacent to the existing skate park, improved access to the river in one location, a small area of wild flower planting, and (subject to the outcome from the ongoing discussions regarding public toilet provision) a limited improvement of the toilet facilities. 4.5. Given the longer term vision for the park, the concept design work included the production of a master plan for the park, to ensure that the LUF scheme proposed doesn’t inhibit the development of future areas of the park, as and when future funding opportunities arise.
4.6The Council’s Streetscene team are currently undertaking a separate project for the refurbishment of the existing play area within the park together, which includes additional pieces of play equipment. This is being funded via Shared Prosperity Fund and is due to be delivered this summer.
Progress
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.