RESOLVED that Cabinet – (a) endorses the Denbighshire Local Area Energy Plan (LAEP) Main Report and Technical Report (Appendix 1 and 2 to the report), understanding that the LAEP actions assigned to Denbighshire County Council were subject to securing and maintaining necessary funding, and (b) confirms that it has read, understood and taken account of the Wellbeing Impact Assessment (Appendix 3 to the report) as part of its consideration.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Lead Member / Officer Cllr Barry Mellor / Jane Hodgson
Head of Service Helen Vaughan-Evans
Report author Jane Hodgson
Title Denbighshire’s Local Area Energy Plan
1. What is the report about? 1.1. This report is about the Local Area Energy Plan (LAEP) that has been developed for Denbighshire, as part of a Welsh Government project. It recommends endorsing the Denbighshire Local Area Energy Plan.
2. What is the reason for making this report? 2.1. A decision is required on whether to endorse the Denbighshire Local Area Energy Plan Main Report and Technical Report (Appendix 1 and 2). Cabinet noted the commencement of LAEP on 21 February 2023.
3. What are the Recommendations? 3.1. That Cabinet endorses the attached Denbighshire Local Area Energy Plan Main Report and Technical Report (Appendix 1 and 2), understanding that the LAEP actions assigned to Denbighshire County Council are subject to securing and maintaining necessary funding.
3.2That the Committee confirms that it has read, understood and taken account of the Well-being Impact Assessment (Appendix 3) as part of its consideration. 4. Report details Progress to date
4.1Local Area Energy Planning (LAEP) is a data driven and whole energy system, evidence-based approach that sets out to identify the most effective route for the local area to contribute towards meeting the national net zero target, as well as meeting its local [area based] net zero target.
4.2LAEP aims to: account for local and national conditions to achieve net zero; consider how cooperation with adjacent areas can bring success; and increase local stakeholder awareness to increase consent and facilitate credible commitments to achieve the plan.
4.3LAEPs feed into regional energy strategies, which relate to national policies: Future Wales: the national plan 2040 (Cymru’r Dyfodol: y cynllun cenedlaethol 2040), climate change targets (targedau newid hinsawdd), and National Energy Plan 2024 (Cynllun Ynni Cenedlaethol 2024).
4.4On behalf of the Welsh Government, Ambition North Wales are managing a contract with consultants developing the LAEP for Denbighshire, and the other north Wales counties. The LAEP was authored by The Carbon Trust and Arup, following an internationally recognised method, and was based on modelling, insights from data, and stakeholder plans and ideas, including through workshops.
4.5The plans will fall under the ownership of each local authority in Wales. They are aimed at being a guidance tool in how best to work towards a fully decarbonised energy system by 2050. All LAEPs will be aggregated to inform the development of the National Energy Plan by the end of the year.
4.6Local authorities are requested to endorse the Local Area Energy Plan through due process. The LAEP has been reviewed by Greener Denbighshire Board, the Cross-Party Political Working Group (Climate Change and Ecological Emergency), Strategic Planning Group and Communities Scrutiny Committee.
4.7The final versions of the Local Area Energy Plan and the Technical Report are attached as appendices 1 and 2 respectively. Next steps – future stages and timetable
4.8A Members’ Briefing is being organised for later in the autumn to provide a opportunity to increase understanding of and consider the details in the LAEP.
4.9With Ambition North Wales and other counties in Wales, a delivery/ monitoring mechanism to progress LAEP actions will be developed, including:
Agreeing on a governance structure Align north Wales Regional Energy Strategy (+Action Plan) with the LAEPs Identify KPI’s Regional Steering Group
4.10The LAEP is provisionally due to be reviewed in five years’ time, as we approach 2030 and the public sector net carbon zero target deadline.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.