RESOLVED that Cabinet – (a) approve an additional £1.299m in capital expenditure for the purpose of procuring additional recycling vehicles funded by prudential borrowing; (b) approves an additional £1.067m of revenue costs in order to ensure the service change can deliver as planned on a sustainable footing. This includes the revenue costs for the prudential borrowing for the vehicles referred to in paragraph 3.1 of the report; (c) agrees that the decision be implemented immediately without call-in, in accordance with section 7.25 of the Council’s Constitution, and (d) confirms that it has read, understood and taken account of the Wellbeing Impact Assessment (Appendix A to the report) as part of its consideration.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Lead Member Cllr Barry Mellor, Lead Member for Environment and Transport
Report author Corporate Director: Environment and Economy & Head of Highways & Environmental Services
Title Additional resources required for the new weekly trollibocs recycling service and associated waste collection functions.
1. What is the report about?
1.1This report is about the implementation of the new weekly trollibocs recycling service and associated waste collection functions and what adjustments are required to ensure sufficient resources are allocated so that the new system can operate on a sustainable footing.
2. What is the reason for making this report?
2.1A decision is required to approve additional resources to ensure the new weekly trollibocs recycling service and associated waste collection functions can operate as envisaged.
3. What are the recommendations?
3.1That Cabinet approve an additional £1.299m in capital expenditure for the purpose of procuring additional recycling vehicles funded by prudential borrowing. 3.2. That Cabinet approves an additional £1.067m of revenue costs in order to ensure the service change can deliver as planned on a sustainable footing. This includes the revenue costs for the prudential borrowing for the vehicles referred to in 3.1.
3.3That Cabinet agrees that the decision be implemented immediately without call- in, in accordance with section 7.25 of the Council Constitution.
3.4That Cabinet confirms they have read, understood and taken account of the Wellbeing Impact Assessment (Appendix A) as part of its consideration.
4. Report details
4.1On 3rd June 2024 the Council implemented a new waste/recycling service. The costs for the service change was originally approved by Cabinet on 19th December 2018 and was subsequently reviewed by Cabinet on 12th April 2022.
4.2Forecasting for complex service changes such as this can only ever be a best estimate due to the number of variables. Those estimates can only ever be fully tested following implementation of the changes. This service change has been in the planning stage in excess of 6 years e.g. pre the original Cabinet decision in 2018 through to implementation in 2024. Much has changed during this time, including key variables associated with this service change (e.g. increases in construction costs, costs of vehicles, development of more housing in the County requiring a waste service etc).
4.3It soon became apparent after the roll out of the new service that some of the assumptions were flawed. The main issue being some of the daily recycling rounds had been designed with too many properties requiring collection. This meant we were seeing several rounds per day not completing, resulting in large and unacceptable numbers of missed collections.
4.4There will be full review of how the roll out was planned and implemented which will include an examination of the assumptions underpinning the design of the new service. Elected Members and residents will be involved in the review.
4.5The assumption regarding the number of properties per round can only be amended by reducing the number of dwellings in those affected rounds. This will necessitate the introduction of additional daily rounds and associated resources.
4.6Without committing additional resources the new service cannot be delivered successfully and sustainably and we will continue to spend significantly more on inefficient short term day to day decisions to ensure missed collections are minimised/corrected.
4.7The day-to-day management decisions since the roll out have focused on the hire of additional vehicles, increase in the use of agency staff, and the use of overtime for existing staff. Whilst this has been at a cost, it would have been unacceptable not to respond to the issues faced by our residents as a result of the number of missed collections.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.