CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Denbighshire County Council
Cabinet, Tuesday 22 October 2024 at 10.00am

REPLACEMENT OF THE SOCIAL CARE INFORMATION MANAGEMENT SYSTEM - CONTRACT AWARD

Approved Executive 1 paper

Cabinet approved this item on Tuesday 22 October 2024. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

RESOLVED that Cabinet – (a) approves the Contract Award report attached at Appendix 2 to the report, and (b) continues to support Denbighshire’s participation in the national Connecting Care programme.
Word for word from the decision Denbighshire published for this meeting. Source: moderngov.denbighshire.gov.uk

Follow this further

Built from Denbighshire's papers

What the report saysPro

Report to Cabinet

Report to Cabinet

Date of meeting 22nd October 2024

Lead Member / Officer Lead Member for Corporate Strategy, Policy and Equalities, Lead Member for Health and Social Care, and Lead Member for Education, Children and Families / Corporate Director: Social Services and Education

Head of Service Heads of Adult Social Care and Homelessness; Education and Children’s Services; and Corporate Support: Performance, Digital and Assets

Report author Corporate Director: Social Services and Education and ICT Business Partners

Title Replacement of the Social Care Information Management System – Contract Award

1. What is the report about? 1.1. Cabinet approved Denbighshire’s participation in a procurement process for a replacement social care information management system based on the Business Case presented to its meeting of 30th July 2024. This report seeks authorisation to award a contract to the successful bidder.

2. What is the reason for making this report? 2.1. To seek approval for the contract award and continued participation in the national Connecting Care programme.

3. What are the Recommendations? That Cabinet:

3.1approves the Contract Award report attached as Appendix two. 3.2. Continues to support Denbighshire’s participation in the national Connecting Care programme.

4. Report details

4.1Further to the Cabinet report of 30th July 2024, Denbighshire, as part of a cluster of the six north Wales authorities advertised the opportunity to contract for a social care information management system with a second cluster of authorities. The advertisement was managed by Rhondda Cynon Taff. 4.2. Tenders closed on 26th August 2024 and a local evaluation process took place internally. The scores from that process were taken forward to a regional moderation session on 18th September 2024. 4.3. A further moderation session with the other cluster took take place on 2nd October and both clusters’ scoring was similar and we were able to reach consensus on those which varied. This means that both clusters will seek to award contracts to the same successful bidder. 4.4. To date, each authority has been participating in the programme on a ‘no obligation’ basis, but we have now reached the point where we need to decide whether to award a contract to the preferred supplier. The current timeline shows that RCT will be advising the bidders of the outcome on 24 th October and the outcome of the discussions and selection process remain confidential and commercially sensitive until then. 4.5. The current timeline sees contracts awarded on 5th November following a 10-day standstill period. 4.6. Contracts awarded as a result of the tender process will have an initial term of 7 years, with the option to extend in 2-year intervals up to a maximum of 21 years. Each authority will award its own contract and will be responsible for its own contract management arrangements. 4.7. A summary of the costs for the tender is included in appendix one which is an updated version of the table presented to Cabinet as part of the Business Case. 4.8. A draft copy of the Contract Award report as required by the Contract Procedure Rules is available at appendix two. 5. How does the decision contribute to the Corporate Plan 2022 to 2027: The Denbighshire We Want? 5.1. The replacement of the Social Care Information Management System will contribute to the following themes within the Corporate Plan:

 A healthier and happier, caring Denbighshire  A learning and growing Denbighshire  A fairer, safe and more equal Denbighshire

6. What will it cost and how will it affect other services? 6.1. Costs are included in Appendixes one and two.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
REPLACEMENT OF THE SOCIAL CARE INFORMATION MANAGEMENT SYSTEM: CONTRACT AWARDReport 324 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Denbighshire

Search all
  1. REPLACEMENT OF THE SOCIAL CARE INFORMATION MANAGEMENT SYSTEM - CONTRACT AWARDThis decision
  2. Replacement of the social care information management systemApproved

More from Denbighshire Cabinet

All decisions
MeetingDecisionOutcome
28 Jul 2026 ApologiesChief Executive Decided Open
28 Jul 2026 Declaration of interestsCouncillor Jason McLellan – Personal and Prejudicial Interest – Agenda Item Nos. 9 & 10 Decided Open
28 Jul 2026 Urgent mattersNo urgent matters had been raised. Decided Open
28 Jul 2026 MINUTESRESOLVED that the minutes of the meeting held on 30 June 2026 be received and confirmed as a correct record. Decided Open
28 Jul 2026 Denbighshire county council digital strategy 2026 - 2031RESOLVED that Cabinet – (a) approve the Denbighshire County Council Digital Strategy 2026 – 2031 (Appendix 1 to the r... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies