RESOLVED that Cabinet – (a) note the budgets set for 2024/25 and progress against the agreed strategy; (b) approve the Council Tax Base for setting the 2025/26 budget as detailed in Appendix 3 to the report; (c) approve the use of the capital contingency to fund the overspend on the L ô n Parcwr scheme as detailed in Section 6.8 to the report, and (d) approve the Ysgol y Castell business case for submission to the Welsh Government Capital Programme as detailed in Section 6.9 and Appendix 5 to the report.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
The report gives details of the Council’s revenue budget and savings as agreed for 2024/25.
2. What is the reason for making this report?
2.1The report provides an update on the Council’s current financial position and confirms the agreed service budgets for 2024/25.
3. What are the Recommendations?
3.1Members note the budgets set for 2024/25 and progress against the agreed strategy.
3.2Members approve the Council Tax Base for setting the 2025/26 budget as detailed in Appendix 3.
3.3Members approve the use of the capital contingency to fund the overspend on the Lôn Parcwr scheme as detailed in 6.8.
3.3Members approve the Ysgol Y Castell business case for submission to the Welsh Government Capital Programme, as detailed in section 6.9 and Appendix 5 4. Report details
4.1The Council’s net revenue budget is £271.021m (£250.793m in 23/24) as detailed in Appendix 1. The position on service and corporate budgets is a forecast under spend of £4.285m (£479k underspend last month). The movement this month is due to Welsh Government awarding additional in year funding to support pay pressures and Teachers’ pension costs. Further details are outlined in Section 6 and Appendix 2.
4.2In setting its budget for 2024/25 the Council faced pressures of £24.6m from inflationary increases such as pay and increases in demand and costs of providing social care. The increase in Welsh Government funding and in the level of Council Tax meant the 2024/25 budget required service savings and efficiencies of £10.384m to be identified, as summarised below: Major Savings Proposals – large-scale saving projects (£2.388m) Non-Strategic savings – Operational efficiencies/smaller scale savings within Head of Service delegated responsibility in consultation with Lead Members (£5.296m). Schools received funding to cover all inflationary pressures including pay awards, pension contributions and energy, and an increase for demography. Given the scale of the challenges, schools were asked to find savings of 3% (£2.7m). The net position was an increase of £4.916m (5.82%).
4.3Monitoring Delivery of Savings – Due to the timing of implementation, some of the proposals will not realise a full year saving in 2024/25 and these in-year pressures are monitored with the service budget.
4.4Council Tax Base – The Council is required to calculate annually its Council Tax Base (CT Base) for the following financial year. The CT Base is an amount required by the Local Government Finance Act 1992 to be used in the calculation of council tax for billing authorities and major precepting authorities and in the calculation of the amount of a precept payable by each billing authority to a major precepting authority. The CT Base is a measure of the tax raising capacity of an authority. It is expressed in terms of the number of Band D equivalent dwellings in an authority’s area, taking into account exemptions, discounts, disablement relief and the authority’s estimate of its collection rate for Council Tax. The details for each community area in Denbighshire, for Cabinet approval, is in Appendix 3. 5. How does the decision contribute to the Corporate Priorities? Effective management of the Council’s budgets and delivery of the agreed budget strategy underpins activity in all areas. The 2024/25 budget include allocations to continue to support both corporate and service priorities.
6. What will it cost and how will it affect other services? Significant service narratives explaining pressures and risks of over- and under-spend are detailed in Appendix 2, however the following should also be noted:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.