AI summaryDenbighshire Cabinet approves re-tender of its Reactive Maintenance Framework, with the current arrangement expiring in July 2026 and a new process to start by February 2026.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedCabinet agreed to start the re-tender exercise
MoneyNot stated
What happens nextTender to start by February 2026To run before the existing framework ends in July 2026
Who it affectsCouncil buildings and schoolsIncludes locally based contractors able to bid
What was decided
Cabinet approved starting the re-tender exercise for the Reactive Maintenance Framework. Report 3.1
Cabinet confirmed it had read, understood and taken account of the Wellbeing Impact Assessment (Appendix A). Report 3.1
Why
The existing framework, originally awarded on a four-year term, expires in July 2026, so a new process must start no later than February 2026 to keep services running and stay within procurement rules. Report P8, 2.2
Re-tendering is intended to secure best value from maintenance contractors and to set response times and performance monitoring for building repairs. Report P7, 5.5
What happens next
Officers will start the re-tender process, with the new framework expected to be a two-year contract with the option to extend on a 1 plus 1 basis, totalling a potential four-year term. Report 4.2
A Prior Information Notice will be issued through Sell2Wales to alert current and potential contractors to the upcoming opportunity. Report 8.3, P28
The money
approximately £2M per annum Current annual spend on repairs and maintenance
circa £8M over the life of the Framework Estimated total spend across the framework term
Implications
Financial: Framework spend of about £2M a year is funded from base budgets held centrally and within individual service areas, external capital and revenue grant funding, and a centrally provided capital bloc allocation. Report P27
Legal: The decision is made under the Local Government Act 2000, the Local Government Act 1972 and Regulation 33 of the Public Contracts Regulations 2015. Report P30
Risk: Risks include local contractors not tendering, hourly rates rising, and contractors under-performing, addressed through a Prior Information Notice, competitive tendering, and frequent performance reviews. Report P28, 10.2
Equalities: A Wellbeing Impact Assessment rated the approach 27 out of 36 against the four sustainable development principles (3 of 4 stars) and judged impact on most well-being goals as positive. Report 7.2, P21
Who and where
Schools and other council building users Report P12, 4.2
Current and potential maintenance contractors, including local firms Report 8.2
The Council's Property Maintenance Team and Helpdesk Report P12
Timeline
20th January 2026: Cabinet meeting approving re-tender Report P2
No later than February 2026: New tender process to commence Report P8
July 2026: Current Reactive Maintenance Framework expires Report P8
Plain English for the jargon
Framework (procurement): An agreement with approved contractors who can be called on to carry out work as needed, usually with set rates and terms.
Prior Information Notice (PIN): A notice published on Sell2Wales to tell suppliers that a contract opportunity is coming up.
Wellbeing Impact Assessment: An assessment of how a decision affects the well-being goals set out for public bodies in Wales.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
RESOLVED that Cabinet – (a) approve the initiation of the re-tender exercise for the Reactive Maintenance Framework, and (b) confirms that it has read, understood and taken account of the Wellbeing Impact Assessment (Appendix A to the report) as part of its consideration .
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
1. What is the report about? 1.1. The re-tendering of the reactive maintenance framework to ensure the Council is receiving best value from its maintenance contractors and to ensure service delivery continues following the completion of the current framework.
2. What is the reason for making this report? 2.1. A decision is required regarding the re-tendering of the Council’s Reactive Maintenance Framework. The existing framework, originally awarded on a four-year term, will expire in July 2026. To ensure continuity of service and compliance with procurement regulations, a new tender process will need to commence no later than February 2026.
2.2Following the Council’s Contract Procedure Rules, a decision is required at Cabinet to initiate this retender due to the likely contract value of the framework per annum and over the contract life (see section 6.1).
3. What are the Recommendations?
3.1For Cabinet to approve the initiation of the re-tender exercise for the Reactive Maintenance Framework. 3.2. That Cabinet confirms that it has read, understood and taken account of the Well- being Impact Assessment (Appendix A) as part of its consideration.
4. Report details 4.1. Denbighshire County Council’s Property Maintenance Team plays a key role in keeping our buildings safe and functional. We provide a responsive repair service for schools and other council properties, ensuring issues are addressed quickly and safely. Repairs are carried out by approved contractors, selected through a fair process that considers cost, quality, and specialist skills such as electrical, mechanical, or general building work. All requests are managed by our Property Maintenance Helpdesk, which acts as the main point of contact for building users and coordinates work with contractors.
4.2The current Framework is now due for re-tendering and is expected to be awarded on a two-year contract with the option to extend on a 1 plus 1 basis, totalling a potential 4-year contract.
5. How does the decision contribute to the Corporate Plan 2022 to 2027: The Denbighshire We Want? 5.1. A prosperous Denbighshire - By reducing downtime and preventing prolonged property issues, reactive maintenance helps services and building users operate without disruption. This stability encourages continued service delivery and protects property assets, contributing to local prosperity. The proposed lotting structure for the framework will allow locally based contractors to tender for a place on the framework.
5.2A healthier and happier, caring Denbighshire - Prompt repairs to heating, water, and sanitation systems safeguards public health and wellbeing. A reliable maintenance response demonstrates care for service users and staff, reducing stress and improving overall satisfaction with council services.
5.3A learning and growing Denbighshire - Maintaining educational facilities through reactive repairs ensures schools and education facilities remain safe and operational. This minimises disruption to learning environments and supports education levels within the authority.
5.4A greener Denbighshire - Reactive maintenance can include energy-efficient repairs and sustainable material choices. Addressing issues like insulation failures or inefficient heating systems promptly reduces energy waste and supports environmental goals.
5.5A well-run, high performing council - A structured reactive maintenance framework with clear response times and performance monitoring demonstrates accountability and efficiency. It builds trust in the council’s ability to manage assets effectively and deliver high-quality services.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.