WG PROVISIONAL FUNDING SETTLEMENT & BUDGET SETTING 2026-27

Agreed Scrutiny 3 papers

AI summaryDenbighshire scrutiny committee reviewed Welsh Government's provisional funding settlement, noting a £14.686m funding rise but a £21.011m budget pressures gap, ahead of February 2026 budget setting.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedDiscussed provisional settlement and 2026/27 budget pressures
Money£14.686m anticipated funding increaseCombined settlement rise of 6.8% versus a £21.011m budget pressures gap
What happens nextNot stated
Who it affectsResidents and service users across DenbighshirePlacemaking services face cuts to fund statutory duties

What was decided

The committee noted the impact of the Welsh Government provisional settlement and the updated budget pressures and savings proposals. Report 3.1

Members noted this is the fourth consecutive year the budget gap has exceeded £20m, and thanked officers for identifying contingency measures and reserves. Report P24

Members recognised the work of the Budget and Transformation Board, which meets fortnightly, to identify cost reductions and transform service delivery.

Why

The Council is legally required to set a balanced budget before the start of each financial year under Section 151 of the Local Government Act 1972. Report P9, 11.1

Demand and complexity of need have grown in Education, Social Care and Homelessness, with costs rising well above inflation in areas of statutory duty. Report P23

Welsh Government issued the provisional settlement on 24 November 2025, and a Plaid Cymru budget agreement on 9 December 2025 added further funding. Report P13, P18

What happens next

The final Welsh Government budget is to be published on 20 January 2026, after which revised allocations will be confirmed. Report P19

Cabinet will consider a report to set a balanced budget and Council Tax on 10 February 2026. Report P9, P29

Council will consider the same on 12 February 2026, including final pressures, savings and any Council Tax increase. Report P9, P29

The money

  • £226.092m Provisional Aggregate External Finance for 2026/27 Report P13
  • £220.048m Restated 2025/26 Aggregate External Finance Report P14
  • £6.044m Headline increase in AEF, or 2.7% Report P14
  • £4.797m In-year funding for pay awards and employer national insurance in 2025/26 Report P15
  • £10.841m True impact of provisional settlement increase, or 5% Report P15
  • £112.8m Additional Welsh local government funding from Plaid Cymru agreement Report P18
  • £14.686m Combined anticipated settlement increase, or 6.8% on 2025/26 Report P19
  • £21.011m Current budget pressures proposed for 2026/27, equal to 7.23% of 2025/26 budget Report P24, P27
  • £14.868m Increase in funding from Welsh Government settlement for 2026/27 Report P27

Options considered

  • Under consideration: Efficiencies, income, transformation, service reductions, collaboration and other savings (as set out in Appendix 2). Work continues to identify further savings ahead of final budget setting in February 2026 Report P28
  • Rejected: Around 10% settlement increase. Would have been required to fund all pressures but not delivered; current settlement is 4.5% to 6.8% Report P27, P19
  • Chosen: Reductions in placemaking services to protect statutory services. High statutory demand pressures leave no option but to reduce universal community services Report P25

Implications

  • Financial: Pressures of £21.011m exceed settlement increase of £14.868m, leaving a gap that requires Council Tax rises and savings. Report P27
  • Legal: The Council must set a balanced budget under Section 151 of the Local Government Act 1972. Report 11.1
  • Equalities: An overall Well-being Impact Assessment is being produced for 2026/27 budget setting, covering combined reductions in recent years. Report 7.1
  • Risk: Failure to agree proposals without viable alternatives risks not achieving a balanced budget for 2026/27. Report 10.1
  • Other: Continued transformation through the Budget and Transformation Board is required to reduce the structural gap.
  • Staffing: Welsh Government Minister's stated ambition includes safeguarding jobs while setting the final budget. Report P17

Who and where

  • Residents and vulnerable individuals requiring Education, Social Care and Homelessness services Report P23, P25
  • Users of placemaking services such as street cleansing, road maintenance, public toilets and libraries Report P25
  • Council Tax payers across Denbighshire Report P9
  • School budgets, via the School Budget Forum Report P36
  • Trade unions, consulted through the Local Joint Consultative Committee Report P36
  • All 22 Welsh local authorities through the funding formula Report P16

Timeline

  • 24th November 2025: Provisional Funding Settlement received by the Council Report P13
  • 9th December 2025: Welsh Government and Plaid Cymru announce budget agreement adding £112.8m for local government Report P18
  • 20th January 2026: Final Welsh Government Budget to be published Report P19
  • 29th January 2026: Performance Scrutiny Committee considers this report Report P2
  • 10th February 2026: Cabinet to consider balanced budget and Council Tax proposals Report P9
  • 12th February 2026: Council to set the 2026/27 budget and Council Tax Report P9

Plain English for the jargon

  • AEF: Aggregate External Finance, made up of Revenue Support Grant and the council's share of non-domestic rates.
  • RSG: Revenue Support Grant from Welsh Government.
  • NDR: Non-Domestic Rates pool share allocated to councils.
  • MTFP: Medium-Term Financial Plan, the council's multi-year financial planning document.
  • BAT Board: Budget and Transformation Board, which meets fortnightly to oversee transformational projects.
  • Quantum: The total amount of funding available for distribution across Welsh local authorities.
  • WIA: Well-being Impact Assessment covering combined budget reduction measures.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

Agreed that including a summary of the procedure and the outcomes of the process might be beneficial. Confirmed that maintaining contingency plans was very important when reviewing the budget and any departmental overspends. Members were reminded that the authority held a reserve for unforeseen circumstances and challenges. Thanked Members for raising concerns regarding the 2026/27 budget gap. It was confirmed that this was the fourth consecutive year in which the gap had exceeded £20m, highlighting the need for continued improvement. Work was ongoing through the Budget and Transformation (BAT) Board to identify how the authority could operate more cost‑effectively and differently to reduce the gap. This Board met on a fortnightly basis to monitor the development of transformational projects put forward by services. Members were reminded that a formula determined the distribution of funding between authorities, while the ‘quantum’ represented the ... view the full minutes text for item 6.
Word for word from the decision Denbighshire published for this meeting. Source: moderngov.denbighshire.gov.uk

Follow this further

Built from Denbighshire's papers

What the report saysPro

Report to Performance Scrutiny Committee, 6 pages

Report to Performance Scrutiny Committee

Date of meeting 29th January 2026

Lead Member / Officer Lead Member for Finance / Head of Finance and Audit

Report author Head of Finance and Audit

Title Welsh Government’s Provisional Funding Settlement for Local Government and update on budget setting for 2026/27

1. What is the report about?

Updating the Committee on the Welsh Government’s (WG) Provisional Funding Settlement for Local Government 2026/27 and its implications for setting a balanced budget for 2026/27.

2. What is the reason for making this report?

The Council is legally required to set a balanced budget before the start of each financial year and to set the resulting level of Council Tax. Cabinet, at its next meeting on 10th February 2026 will consider a report to set a balanced budget and Council Tax for 2026/27. Proposals will then be considered by Council at its meeting on 12th February 2026. This report builds on previous reports to the Committee during the year with updated information for overview and scrutiny prior to Cabinet and Council meetings to set the 2026/27 budget.

3. What are the Recommendations?

3.1To note the impact of the WG Provisional Settlement 2026/27 in section 4.1 of the report and review the updated budget pressures and savings in sections 4.2 and 4.3 of the report. 4. Report details

4.1Provisional Funding Settlement for Local Government 2026/27

4.1.1 The Provisional Settlement for 2026/27 was received by the Council on 24th November 2025. The Council’s provisional AEF (Aggregate External Finance, which consists of the Revenue Support Grant[RSG], and our share of the non- domestic rates pool[NDR]) from WG for 2026/27 equates to £226.092m.

4.1.2 WG have produced tables so that funding levels in 2025/26 and 2026/27 can be compared on a like for like basis across all Welsh councils. The Council’s 2026/27 funding compares with a restated 2025/26 AEF of £220.048m. A headline increase of £6.044m or 2.7%.

4.1.3 Over the course of the year, Welsh Government have allocated additional in year funding to Local Government for teaching and non-teaching pay awards and the increase in employers national insurance contributions. For Denbighshire these total £4.797m in 2025/26. This in year funding has been amalgamated into the base budget and therefore has the effect of increasing the funding in 2026/27 over and above the 2.7%. The true impact of the provisional settlement is therefore an increase of £10.841m or 5% (£10.841m / £215.251m).

4.1.4 The funding for Welsh Local Government as a whole has seen an increase of 2.7%. Ranked on percentage increase Denbighshire’s increase is the 9 th highest in Wales. That reflects increases in pupil, population and free school meals data being used in the formula to distribute funding, and a corresponding increase in demand for services as a result.

4.1.5 The Welsh Government’s draft budget did not allocate all of the resources available. In the accompanying letter to all Welsh councils the Minister noted that this stage was the beginning of the budget process for Welsh Government and that it was her ambition to ‘secure a final budget which uses all the resources available for 2026/27, safeguards jobs, protect frontline public services and does not lead to large increases in council tax’.

4.1.6 On 9th December 2025 Welsh Government announced that a budget agreement had been reached with Plaid Cymru which will allow its budget for 2026/27 to pass. The agreement allocates an additional £112.8m of funding for local government in 2026/27. This provides for an overall 4.5% increase to the local government settlement with all councils receiving increases of above 4%.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
WG PROVISIONAL FUNDING SETTLEMENT & BUDGET SETTING 2026-27Report 6 pages DownloadRead as text
PDF
WG Prov Funding Settlement & Budget Setting 2026-27 Report: App 1 290126Appendix 4 pages Download
PDF
WG Prov Funding Settlement & Budget Setting 2026-27 Report: App 2 290126Appendix 4 pages Download

At this meeting

Whole meeting

On this subject at Denbighshire

Search all
  1. WG PROVISIONAL FUNDING SETTLEMENT & BUDGET SETTING 2026-27This decision
  2. Welsh government's provisional funding settlement for local government 2026/27Decided
  3. Welsh government's provisional funding settlement for local government 2025/26Approved

More from Denbighshire Performance Scrutiny Committee

All decisions
MeetingDecisionOutcome
16 Jul 2026 Minutes of the last meetingResolved : that the minutes of the Performance Scrutiny Committee meeting held on 11 June 2026 be approved as a true ... Approved Open
16 Jul 2026 Scrutiny work programmeResolved : subject to the changes and additions reported during the report’s presentation, along with those agreed du... Agreed Open
11 Jun 2026 Appointment of vice-chairResolved : to elect Councillor Gareth Sandilands as Vice-Chair of Performance Scrutiny Committee for the 2026/27 muni... Decided Open
11 Jun 2026 Minutes of the last meetingResolved : subject to the inclusion of Councillor Ellis’ name in the list of apologies, that the minutes of the Perfo... Approved Open
11 Jun 2026 Scrutiny work programmeResolved : subject to the inclusions agreed during the course of the meeting, to confirm its programme of future work... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies