NORTH WALES CONSTRUCTION PARTNERSHIP (NWCP) SMALL VALUE WORKS FRAMEWORK - INITIATE PROJECT APPROVAL
ApprovedExecutive4 papers
AI summaryDenbighshire Cabinet approves a North Wales Construction Partnership Small Value Works Framework for projects between £30,000 and £300,000, to be hosted by Denbighshire.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSmall Value Works Framework established across six North Wales councils
Money£8,680 set-up; £6,746 a yearSet-up funded by NWCP; running costs shared by partners
What happens nextProcurement to beginDenbighshire to host the framework, subject to Cabinet sign-off on appointments
Who it affectsNot stated
What was decided
Cabinet approved establishing the NWCP Small Value Works Framework for construction projects between £30,000 and £300,000 across the six partner authorities. Report P7, 3.1
Cabinet confirmed it had read, understood and taken account of the Well-being Impact Assessment at Appendix 1. Report P35
The framework is to be hosted by Denbighshire, with governance through the NWCP operational board and compliance with the Procurement Act 2023. Report P15, 4.3
Why
Current small-value procurement is fragmented, inefficient and often excludes small and medium-sized firms, and the new framework is intended to streamline processes and embed social value. Report 2.2, 1.2
The framework aims to deliver value for money, support local SME participation, embed apprenticeships and training, and contribute to Net Zero goals. Report 1.2, 4.5, P30
The business case estimates a potential pipeline of £30m+ annually across the six councils, with a framework ceiling of £200m. Report 4.5
What happens next
A one-stage procurement process will appoint up to 8 contractors plus 2 reserves per lot, with a contract term of 2 plus 2 years. Report 4.4, P21, 4.6
An Inter Authority Agreement will spread any legal challenge costs across partner authorities over the next four years. Report 6.5
The framework will be reviewed annually to check financial viability and budgetary alignment. Report 8.2
The money
£30,000 and £300,000 Project value range for the framework Report P7, 3.1
£6,746 Annual running cost for staff Report P32
£8,680 Initial set-up cost, funded via NWCP Report P32
£1,500 per annum each Partner authority contributions to running costs Report P32
0.5% of contract value Access fee from non-partner users Report P32
£30m+ Estimated annual pipeline across the six North Wales councils Report 4.5
Chosen: Approve establishment of the NWCP Small Value Works Framework. Streamlines procurement, supports SMEs, and embeds social value across the six councils Report P7, 1.2, 2.2
Chosen: Take account of the Well-being Impact Assessment (Appendix 1). Assessment scored 33/36 with broadly positive impacts across well-being goals Report P35
Implications
Financial: Framework running costs shared across six partner authorities at £1,500 a year each, with non-partner access fees of 0.5% of contract value. Report P32
Legal: An Inter Authority Agreement is required so that costs of any procurement legal challenge are shared across the collaborative authorities for four years. Report 6.5
Equalities: Well-being Impact Assessment No. 1500 scored 33/36, with positive contributions across all well-being goals. Report P35, 5.2
Climate: Framework scope includes energy retrofit works and is intended to advance Net Zero through carbon reduction. Report 4.1, P30
Risk: Main risk is that local SMEs may not be appointed; mitigated by market engagement, contractor briefing events, Business Wales involvement and a fair procurement process. Report P40
Other: Procurement is designed to embed apprenticeships, fair work, and training opportunities across the region. Report P30, 4.7
Who and where
The six NWCP partner local authorities in North Wales Report 1.2, 4.1
Local construction SMEs bidding for small-value works Report 1.2, P40
Contractors and suppliers in disciplines including refurbishment, maintenance, modular builds, highways, drainage and energy retrofit Report 4.1
Timeline
10th February 2026: Cabinet decision to approve the framework Report P2
2+2 years: Proposed contract term for the framework Report 4.4
Annual review: Financial viability and budget alignment check Report 8.2
Plain English for the jargon
NWCP: North Wales Construction Partnership, formed by the six North Wales local authorities.
SVWF: Small Value Works Framework, the new procurement framework for projects between £30,000 and £300,000.
SME: Small and Medium-sized Enterprise.
IAA: Inter Authority Agreement between partner councils to share legal and governance arrangements.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9
Resolved
RESOLVED that Cabinet – (a) approve the establishment of a North Wales Construction Partnership Small Value Works Framework (SVWF), designed to deliver construction projects valued between £30,000 and £300,000 across the region, and (b) confirms that it has read, understood and taken account of the Well-being Impact Assessment (Appendix 1 to the report) as part of its consideration.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Title North Wales Construction Partnership (NWCP) Small Value Works Framework - Initiate Project approval
1. What is the report about? 1.1. This report seeks approval to establish a North Wales Construction Partnership Small Value Works Framework (SVWF), designed to deliver construction projects valued between £30,000 and £300,000 across the region.
1.2The Framework will provide a structured, transparent, and efficient procurement route for small-scale works to the six NWCP partner authorities, with the aim of supporting local SME participation, embedding social value, and ensuring compliance with the Procurement Act 2023.
2. What is the reason for making this report? 2.1. A decision is required on the initiation and approval of the SVWF project.
2.2Current procurement routes for small-value works are fragmented, inefficient, and often exclude SMEs. The new Framework will streamline processes, potentially reduce procurement and project costs, and strengthen community benefits 3. What are the Recommendations?
3.1That Cabinet approve the establishment of a North Wales Construction Partnership Small Value Works Framework (SVWF), designed to deliver construction projects valued between £30,000 and £300,000 across the region. 3.2. That Cabinet confirms that it has read, understood and taken account of the Well- being Impact Assessment (Appendix 1) as part of its consideration.
4. Report details Procurement Strategy – Overview
4.1The operational board of the NWCP, formed by the six North Wales local authorities, seeks to create a collaborative small value works construction framework as the established NWCP Framework has proven effective; the proposed SVWF will extend this model to projects valued £30k–£300k, including refurbishments, maintenance, modular builds, highways, drainage, and energy retrofit works.
4.2Each region (East and West) will have two lots (£30k–£99k and £100k–£300k), appointing up to 8 contractors plus 2 reserves per lot. Call-offs will be managed via direct award (ranked and rotating) or mini competition, ensuring fairness and transparency.
Project Governance
4.3The Framework will be overseen by the NWCP operational board, with governance and reporting structures ensuring accountability, compliance with the Procurement Act 2023, and Cabinet approval before contractor appointments. As per NWCP it is intended that the Small Value Framework will be hosted by Denbighshire.
Procurement Strategy – Overview
4.4Contractors will be appointed to the Framework through a one-stage procurement process, designed to reduce administrative burden and accelerate delivery. Evaluation will be based on proportional criteria, embedding standardised approaches, shared best practice, consistent specifications, and compliance with the Procurement Act 2023. The Framework will appoint suppliers by discipline and lot, with clear ranking and reserve mechanisms to ensure resilience. The contract term will be 2+2 years, balancing stability with flexibility.
Value and Scope of Programme
4.5The main driver for the project is to deliver value for money in public procurement and maximise community benefits across the region. This is best achieved through common, simpler procurement approach of small construction projects and other public sector initiatives. The business case estimates a potential pipeline of £30m+ annually across the six North Wales councils, with a ceiling value of £200m for the Framework.
Lotting Structure
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.